Castleport Test Prep

EPA 608 Type 3 Practice Test: 50 Free Questions

Two original 25-question practice tests for the EPA Section 608 Type III (low-pressure) section, checked against the current federal rules on September 27, 2026. The answer and a sourced explanation sit under every question, and 18 of 25 is the reference line for each test.

50 questions · two 25-question tests · answers under each question · no sign-up

Practice Test A: questions 1–25

Work it closed book, the way the real section runs. Pick your answer before you open the explanation.

Question 1

T3-A01 · Scope and pressure-temperature

A plant has two chillers: a centrifugal chiller running R-123 and a screw chiller running R-22. Which one takes Type III certification to service?

Rule scope: General Type III
Reveal answer for Question 1

Answer: A. Only the R-123 chiller.

Why: Type III follows the refrigerant's pressure class, not the style of equipment. EPA lists R-123 as a low-pressure refrigerant (liquid saturation pressure below 45 psia at 104°F) and R-22 as a high-pressure one. Low-pressure appliances are Type III; high-pressure appliances are Type II.

Why not the others: "Chiller" doesn't decide the Type, so "every chiller is Type III" and "chillers are Type II" both fail. Picking only the R-22 chiller flips the two refrigerants. A Universal card covers both machines.

Source: 40 CFR 82.152 (definitions), low-pressure and high-pressure appliance · 40 CFR 82.161, (a)(1)(ii)–(iii)

Question 2

T3-A02 · Recovery requirements

A 1,200-lb R-123 chiller needs its compressor replaced. The tech's recovery machine was built in 2024. What level must the chiller reach before it's opened?

Rule scope: General Type III
Reveal answer for Question 2

Answer: D. 25 mm Hg absolute.

Why: Removing a compressor is a major repair. For low-pressure appliances, Table 1 lists one level, 25 mm Hg absolute, in both the pre- and post-November 15, 1993 equipment columns. There's no 200-lb split for low-pressure appliances.

Why not the others: 15 and 10 in. Hg come from the medium- and high-pressure rows, where charge size matters. 0 psig is the ceiling for certain non-major repairs, not for this job.

Source: 40 CFR 82.156, Table 1 · 40 CFR 82.152 (definitions), major maintenance, service, or repair

Question 3

T3-A03 · Recovery requirements

A compound gauge reads vacuum in inches of mercury. About what reading equals 25 mm Hg absolute?

Rule scope: General Type III
Reveal answer for Question 3

Answer: C. About 29 in. Hg vacuum.

Why: 25 mm is 0.98 in. Table 1 measures vacuum against a 29.9 in. Hg atmosphere, so 29.9 − 0.98 ≈ 28.9 in. Hg vacuum. That's close to a full vacuum. It's also 25,000 microns.

Why not the others: 25 in. Hg vacuum is the classic mm/inches mix-up; it still leaves about 5 in. Hg absolute in the shell. "About 1 in. Hg vacuum" confuses the absolute reading with the vacuum reading. 15 in. Hg vacuum is a medium-pressure level.

Source: 40 CFR 82.156, Table 1 header and low-pressure row

Question 4

T3-A04 · Recovery requirements

Replacing a sight glass leaves a 1.5-square-inch opening uncovered for about two hours. No compressor, condenser, evaporator, or auxiliary heat-exchange coil comes out. Under EPA's definition, is this a major repair?

Rule scope: General Type III
Reveal answer for Question 4

Answer: B. No, because the opening isn't more than 4 square inches of flow area.

Why: Without a major component removed, work is major only if it uncovers more than 4 square inches of flow area for more than 15 minutes. Both conditions have to be true. A 1.5-square-inch opening fails the size test no matter how long it stays open.

Why not the others: The time condition alone isn't enough. Not every opening of the circuit is major; the definition sets the line. Charge size isn't part of the definition.

Source: 40 CFR 82.152 (definitions), major maintenance, service, or repair

Question 5

T3-A05 · Recovery requirements

A tech is replacing a sensor well on an R-123 chiller. It's a non-major repair, and the chiller won't be evacuated to the atmosphere afterward. The section can't be isolated. After bringing the chiller to 0 psig, what else does the rule require?

Rule scope: General Type III
Reveal answer for Question 5

Answer: D. Cover the openings, because isolation isn't possible.

Why: For a non-major repair on a low-pressure appliance, the rule says to pressurize it to no higher than 0 psig and to cover openings when isolation isn't possible. Covering the opening keeps air and moisture out and refrigerant in.

Why not the others: 25 mm Hg absolute is the full Table 1 level for major repairs. Nitrogen to 5 psig breaks two rules: 5 psig is the oil-change allowance, and nitrogen isn't allowed for refrigerants that boil at or below 85°F, like R-123.

Source: 40 CFR 82.156, (a)(1)(ii)

Question 6

T3-A06 · Recovery techniques and equipment

A tech connects the recovery machine to a vapor connection on top of a 900-lb R-11 chiller and starts pulling vapor. What would speed the job up most?

Rule scope: General Type III
Reveal answer for Question 6

Answer: A. Transfer the liquid refrigerant first, then recover the remaining vapor.

Why: EPA's Type 3 list says recovering liquid at the start speeds up recovery, and that vapor still has to be recovered afterward. A pound of liquid moves far faster than the same pound as low-pressure vapor.

Why not the others: Staying on vapor has it backward. Nitrogen mixes a noncondensable into the refrigerant you're recovering. Shutting off the condenser water cools the refrigerant and lowers its pressure, which slows recovery; EPA lists heating the source, not cooling it, as a way to speed things up.

Source: EPA Test Topics, Type 3 → Recovery Techniques; Type 2 → Recovery Techniques

Question 7

T3-A07 · Recovery techniques and equipment

Before draining oil from an R-123 chiller, the tech heats the oil to 130°F. What's the point?

Rule scope: General Type III
Reveal answer for Question 7

Answer: B. Warm oil holds less dissolved refrigerant, so less refrigerant leaves with the oil.

Why: Refrigerant dissolves in chiller oil. EPA's Type 3 list says to heat the oil to 130°F before removing it to minimize refrigerant release. Heating drives the refrigerant out of the oil and back into the system.

Why not the others: Warm oil may drain more easily, but that isn't the reason EPA gives. Freezing oil isn't the concern, and no rule requires hot oil for disposal.

Source: EPA Test Topics, Type 3 → Recovery Techniques

Question 8

T3-A08 · Recovery techniques and equipment

A tech is pulling vapor from an R-123 chiller's evaporator while the tubes hold stagnant water. The shell reaches 25 in. Hg vacuum. Why is that a problem?

Rule scope: General Type III
Reveal answer for Question 8

Answer: A. At that pressure R-123's saturation temperature is far below 32°F, so water in the tubes can freeze and split them.

Why: As shell pressure drops, so does the refrigerant's saturation temperature. At 25 in. Hg vacuum, R-123 is well below water's freezing point, so standing water in the tubes can freeze. EPA's Type 3 topic list says to circulate or remove water during evacuation to prevent freezing.

Why not the others: R-123 doesn't decompose from low pressure. A rupture disc relieves overpressure, not vacuum. The purge unit isn't what's at risk here; the tubes are.

Source: EPA Test Topics, Type 3 → Recovery Techniques · Hudson Technologies pressure-temperature charts (refrigerant-specific charts)

Question 9

T3-A09 · Recharging

An evacuated chiller still has water in its tubes. What can happen if the tech opens the liquid charging line first?

Rule scope: General Type III
Reveal answer for Question 9

Answer: B. The liquid flashes to vapor at the very low pressure, and the cooling can freeze water in the tubes.

Why: Liquid entering a deep vacuum boils instantly and gets very cold. EPA's Type 3 list says to introduce vapor before liquid to prevent freezing water in the tubes. Once vapor has raised the pressure past the point where the refrigerant boils at 32°F, liquid can follow.

Why not the others: Liquid-first ignores the freeze risk. Liquid entering a vacuum doesn't overpressure the shell, so the rupture disc isn't the issue. The purge unit removes noncondensables, not liquid refrigerant.

Source: EPA Test Topics, Type 3 → Recharging Techniques

Question 10

T3-A10 · Recharging

To save hose, a tech plans to charge an R-123 centrifugal chiller through a vent connection on top of the condenser. Where does EPA's topic list say to charge a centrifugal?

Rule scope: General Type III
Reveal answer for Question 10

Answer: D. Through the evaporator charging valve.

Why: EPA's Type 3 list names the evaporator charging valve as the place to charge centrifugals.

Why not the others: The purge unit removes noncondensables; it isn't a charging port. The rupture disc is a pressure-relief device and should never be used as a service connection.

Source: EPA Test Topics, Type 3 → Recharging Techniques

Question 11

T3-A11 · Scope and pressure-temperature

An R-11 chiller's evaporator gauge reads 18 in. Hg vacuum. About what saturation temperature is that?

Rule scope: General Type III
Reveal answer for Question 11

Answer: B. About 32°F.

Why: On a pressure-temperature chart, R-11 at about 18 in. Hg vacuum (about 5.8 psia) boils at roughly 32°F. Reading a low-pressure P-T chart in inches of vacuum is part of EPA's Type 3 refrigeration topic.

Why not the others: 0°F is far deeper in vacuum. About 75°F is R-11's boiling point at atmospheric pressure (0 psig), not at 18 in. of vacuum.

Source: EPA Test Topics, Type 3 → Refrigeration · Hudson Technologies pressure-temperature charts (refrigerant-specific charts)

Question 12

T3-A12 · Leak detection, relief, and safety

Over three months, the purge unit on an R-123 chiller runs more and more often. What's the right response?

Rule scope: General Type III
Reveal answer for Question 12

Answer: D. Treat it as a sign of a leak letting air in, then find and repair the leak.

Why: Much of a low-pressure chiller runs below atmospheric pressure, so leaks pull air and moisture in. The purge unit removes those noncondensables. EPA lists excessive purging as a sign of leakage into a low-pressure system.

Why not the others: Resetting the timer or closing the discharge hides the symptom and leaves the air in. Adding refrigerant treats the loss without fixing the leak, and each addition feeds the leak-rate calculation.

Source: EPA Test Topics, Type 3 → Leak Detection · Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), p. 30 (purge removes noncondensables)

Question 13

T3-A13 · Leak detection, relief, and safety

One major manufacturer's manual for its low-pressure centrifugal chillers puts the rupture disc where, and says it breaks when?

Rule scope: General Type III
Reveal answer for Question 13

Answer: B. On the evaporator side (suction); it breaks if shell pressure goes above about 15 psig.

Why: That manual puts the rupture disk on the suction elbow and says it breaks when evaporator pressure goes above 15 psig. Low-pressure shells aren't built for high internal pressure, which is why leak-test pressure has to stay well below the disc. Other models and newer relief assemblies can differ, so check the unit in front of you.

Why not the others: "High side" placement is a common error in free study material. 10 psig and 50 psig aren't the disc rating. A rupture disc relieves pressure, not vacuum.

Source: Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), p. 31

Question 14

T3-A14 · Leak detection, relief, and safety

There's no hot-water setup or built-in pressurizing device, so a tech will use nitrogen to leak-test a low-pressure centrifugal chiller. Which plan is right?

Rule scope: General Type III
Reveal answer for Question 14

Answer: D. Dry nitrogen through a regulator, kept well below the rupture-disc rating and within the manufacturer's limit.

Why: EPA ranks hot water or a built-in pressurizing device first and nitrogen second, and calls for nitrogen with a pressure regulator rather than compressed air. The allowable nitrogen pressure is equipment-specific: the cited Trane manual limits this product line to 8 psig and describes a rupture disk that relieves at about 15 psig evaporator pressure. Follow the nameplate and current manual for the unit being serviced.

Why not the others: 15 psig and 25 psig are not defensible generic leak-test settings; on the cited Trane product line they reach or exceed the documented relief point. Shop air adds moisture and oxygen; EPA's public test topics specify nitrogen, not compressed air, for leak detection.

Source: EPA Test Topics, Type 3 → Leak Detection; Core → Safety · Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), pp. 9, 31

Question 15

T3-A15 · Leak repair rules

Refrigerant is added to a 450-lb R-123 comfort-cooling chiller, and the leak-rate calculation comes out at 14%. What has to happen within 30 days?

Rule scope: Part 82 / ODS
Reveal answer for Question 15

Answer: B. A certified technician does a leak inspection to find the leaks, and they're repaired, unless the owner chooses to retrofit or retire the chiller.

Why: R-123 is an ozone-depleting refrigerant and the charge is over 50 lb, so 40 CFR 82.157 applies. Comfort cooling triggers above 10%. The owner has 30 days to find and fix the leaks, and the leak inspection must be done by a certified technician. Retrofitting or retiring under a written plan is the alternative.

Why not the others: 15% is the pre-2019 comfort-cooling figure. The chronic-leaker report is for 125% or more in a calendar year. Retirement has a one-year plan timeline, not 30 days.

Source: 40 CFR 82.157, (c)(2)(iii), (d), (d)(1)

Question 16

T3-A16 · Leak repair rules

During a required leak inspection on a 500-lb R-123 chiller, one valve can only be reached by lifting a worker about 3 meters. Which is true?

Rule scope: Part 82 / ODS
Reveal answer for Question 16

Answer: A. That valve doesn't have to be inspected, but a certified technician must inspect all other visible, accessible components.

Why: The rule excuses components where someone would have to be raised more than 2 meters above a support surface, along with insulated, inaccessible, or unsafe components. The inspection itself must be done by a certified technician.

Why not the others: The rule lists exceptions, so "no exceptions" is wrong. One hard-to-reach valve doesn't cancel the whole inspection. Any employee won't do; the rule names a certified technician.

Source: 40 CFR 82.157, (g)(2)–(g)(3)

Question 17

T3-A17 · Leak repair rules

When does the owner of a 400-lb R-123 comfort-cooling chiller have to calculate its leak rate?

Rule scope: Part 82 / ODS
Reveal answer for Question 17

Answer: B. Every time refrigerant is added, except right after a retrofit, a new installation, or an addition that counts as a seasonal variance.

Why: Under 40 CFR 82.157(b), the owner calculates the leak rate every time refrigerant is added, with only those three exceptions. Whoever adds the refrigerant has to give the owner the service documentation needed to do it.

Why not the others: There's no annual-only schedule and no size cutoff for the addition. Purge behavior isn't the trigger; adding refrigerant is.

Source: 40 CFR 82.157, (b)

Question 18

T3-A18 · Leak repair rules

A 600-lb R-123 chiller cooling an office building received 90 lb of refrigerant over the past 365 days. Using the rolling average method, what's the leak rate, and what follows?

Rule scope: Part 82 / ODS
Reveal answer for Question 18

Answer: B. 15%, which is over the 10% comfort-cooling threshold, so repair (or a retrofit or retirement plan) is required.

Why: Rolling average: pounds added over the past 365 days ÷ full charge × 100. So 90 ÷ 600 × 100 = 15%. Office cooling is comfort cooling, and comfort cooling triggers above 10%.

Why not the others: 6.7% divides the charge by the refrigerant added (600 ÷ 90). 20% is the commercial refrigeration threshold. 1.5% slips a decimal.

Source: 40 CFR 82.152 (definitions), leak rate, rolling average method · 40 CFR 82.157, (c)(2)(iii)

Question 19

T3-A19 · Leak repair rules

A plant's R-123 chiller sends 55% of its capacity to a manufacturing process and 45% to office cooling. Which leak-rate threshold applies?

Rule scope: Part 82 / ODS
Reveal answer for Question 19

Answer: C. 30% for industrial process refrigeration.

Why: EPA counts an appliance as industrial process refrigeration when 50% or more of its operating capacity serves the industrial process. At 55%, this chiller is industrial process refrigeration, with a 30% threshold.

Why not the others: 10% would apply only if comfort cooling were the larger use. Commercial refrigeration means retail food and cold storage. There's no averaging rule.

Source: 40 CFR 82.152 (definitions), industrial process refrigeration · 40 CFR 82.157, (c)(2)(ii)

Question 20

T3-A20 · Leak repair rules

It's 2026. A 400-lb R-245fa centrifugal chiller cools an office tower. Which federal leak-repair rule applies?

Rule scope: Part 84 / HFC
Reveal answer for Question 20

Answer: A. 40 CFR 84.106 (the AIM Act rule), at 10% for comfort cooling.

Why: R-245fa is an HFC, not an ozone-depleting substance, so 40 CFR 82.157 doesn't reach it. Since January 1, 2026, 40 CFR 84.106 covers appliances holding 15 lb or more of an HFC or a substitute with a GWP above 53. Comfort cooling is 10% under that rule too. An R-123 chiller would stay under 82.157.

Why not the others: 40 CFR 82.157 is the wrong rulebook for an HFC. "No rule" was true for HFC equipment before 2026. 20% is the commercial refrigeration threshold.

Source: 40 CFR 82.157, (a) · 40 CFR 84.106, (a), (c)(2)(iii)

Question 21

T3-A21 · Leak repair rules

A leak repair meant evacuating part of an R-123 chiller. When do the initial and follow-up verification tests happen?

Rule scope: Part 82 / ODS
Reveal answer for Question 21

Answer: A. Initial test before any refrigerant is added back; follow-up within 10 days of the chiller reaching normal operating conditions.

Why: When a repair required evacuation, the initial verification test comes before any refrigerant goes back in. The follow-up test comes within 10 days of the chiller reaching normal operating characteristics and conditions.

Why not the others: 12 months and 30 days aren't the test windows. Both tests are required on each repaired leak.

Source: 40 CFR 82.157, (e)(1)(ii), (e)(2)

Question 22

T3-A22 · Leak repair rules

The owner of an R-123 chiller leaking above threshold decides to retire it instead of repairing it. What's the timeline?

Rule scope: Part 82 / ODS
Reveal answer for Question 22

Answer: C. A written plan within 30 days, with the work finished within one year of the plan's date.

Why: The owner must write a retrofit or retirement plan within 30 days, and the work must be finished within one year of the plan's date (no more than 13 months from when the plan was required), unless EPA grants more time.

Why not the others: A one-year plan and five-year retirement stretch both deadlines. Retirement still needs a plan. Ten days isn't in the rule.

Source: 40 CFR 82.157, (h)(1), (h)(5)(i)

Question 23

T3-A23 · Leak repair rules

After repairs pass both verification tests, when are a chiller's leaks presumed repaired?

Rule scope: Part 82 / ODS
Reveal answer for Question 23

Answer: B. If no refrigerant is added for 12 months after the repair, or the required leak inspections find no leaks.

Why: Under 40 CFR 82.157(d)(2), repairs are presumed successful if there's no further refrigerant addition for 12 months after the repair, or if the required leak inspections find no leaks. The leak-rate calculation at the next addition also confirms it.

Why not the others: The initial test shows the repair held at that moment; the presumption comes later. Purge cycles and EPA site visits aren't the test.

Source: 40 CFR 82.157, (d)(2)

Question 24

T3-A24 · Leak repair rules

A facility pipes its chiller purge exhaust to a device that destroys the refrigerant at a verified 99% efficiency. How does that refrigerant count in the leak-rate calculation?

Rule scope: Part 82 / ODS
Reveal answer for Question 24

Answer: A. It's left out, because destruction efficiency is 98% or higher, as long as the records and EPA notice are in place.

Why: Purged refrigerant destroyed at a verifiable 98% efficiency or better isn't counted toward the leak rate. The owner has to keep monitoring records and notify EPA within 60 days of first using the exclusion.

Why not the others: There's no doubling and no 10-lb cutoff. Without the destruction, purged refrigerant would count as loss.

Source: 40 CFR 82.157, (k), (l)(9), (m)(5)

Question 25

T3-A25 · Leak detection, relief, and safety

An R-123 chiller sits in an indoor equipment room. Under the ASHRAE Standard 15 guidance a chiller manufacturer summarizes, what should the room's refrigerant monitor do?

Rule scope: General Type III
Reveal answer for Question 25

Answer: D. Detect refrigerant within the acceptable exposure level, set off alarms inside the room and outside each entrance, and start the mechanical ventilation.

Why: EPA's Type 3 list names the ASHRAE Standard 15 equipment-room refrigerant sensor for R-123. A manufacturer's manual spells out what that setup typically includes: a monitor that alarms within the acceptable exposure level, audible and visual alarms inside the room and outside every entrance, and mechanical ventilation the monitor can start.

Why not the others: A log alone warns no one. Stopping the pumps doesn't clear the air. The rupture disc protects the chiller from overpressure; it has nothing to do with room air.

Source: EPA Test Topics, Type 3 → Safety · Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), p. 8

Practice Test B: questions 26–50

Question 26

T3-B01 · Scope and pressure-temperature

Which refrigerant would NOT make an appliance a Type III (low-pressure) appliance?

Rule scope: General Type III
Reveal answer for Question 26

Answer: A. R-134a.

Why: EPA names R-11, R-113, R-123, and R-245fa as low-pressure examples. R-134a is one of its medium-pressure examples (45 to 170 psia at 104°F), so R-134a equipment is Type II.

Why not the others: R-11, R-113, and R-245fa are all on EPA's low-pressure list.

Source: 40 CFR 82.152 (definitions), low-pressure and medium-pressure appliance

Question 27

T3-B02 · Scope and pressure-temperature

A demolition contractor will recover refrigerant from an R-11 chiller before the building is gutted and the chiller is scrapped. What certification does the person doing the recovery need?

Rule scope: General Type III
Reveal answer for Question 27

Answer: C. Type III (or Universal).

Why: Type III covers people who maintain, service, repair, or dispose of low-pressure appliances. The only disposal exemption is for small appliances, motor vehicle air conditioners, and MVAC-like appliances.

Why not the others: "No certification" applies only to those exempt categories. Type I is small appliances. Section 609 is motor vehicle A/C.

Source: 40 CFR 82.161, (a)(1)(iii), (a)(1)(vii)

Question 28

T3-B03 · Recovery requirements

The liquid has been transferred out of a 700-lb R-123 chiller, and the shell gauge reads 0 psig. The chiller is headed for a major repair. What's next?

Rule scope: General Type III
Reveal answer for Question 28

Answer: B. Keep recovering vapor until the shell reaches 25 mm Hg absolute, and confirm that level before opening.

Why: A big shell at 0 psig still holds a lot of refrigerant as vapor. EPA's Type 3 list stresses recovering vapor as well as liquid, Table 1 sets 25 mm Hg absolute for low-pressure appliances, and the tech must verify the level has been reached before opening.

Why not the others: Opening at 0 psig releases the vapor still inside. Nitrogen contaminates what's left. Sending refrigerant out through the purge on purpose is venting.

Source: EPA Test Topics, Type 3 → Recovery Techniques · 40 CFR 82.156, (a) and Table 1

Question 29

T3-B04 · Recovery requirements

R-123 boils at about 82°F at atmospheric pressure. For a non-major repair on an R-123 chiller, why can the tech raise the pressure with heat but not finish with nitrogen?

Rule scope: General Type III
Reveal answer for Question 29

Answer: D. For refrigerants that boil at or below 85°F, the rule bars methods like nitrogen that have to be purged out later.

Why: The rule draws its line at an 85°F boiling point. At or below it, low-pressure appliances can't be pressurized with methods such as nitrogen that require later purging. Nitrogen left inside is a noncondensable that would have to be purged out later.

Why not the others: The rule isn't about chemistry or speed, and there's no 10 psig nitrogen allowance.

Source: 40 CFR 82.156, (a)(1)(ii) · Hudson Technologies pressure-temperature charts (refrigerant-specific charts)

Question 30

T3-B05 · Recovery requirements

Same kind of job, but the chiller uses R-113, which boils at about 118°F. What does the rule allow?

Rule scope: General Type III
Reveal answer for Question 30

Answer: C. Heat to raise the pressure as far as it will go, then nitrogen from there up to atmospheric.

Why: Above 85°F, the rule requires heat first and allows nitrogen to finish the rise to atmospheric pressure. R-113 is on EPA's low-pressure list, so the rule applies.

Why not the others: Heat can't be skipped. R-113 chillers aren't exempt. 25 mm Hg absolute is the major-repair level, not the non-major pressurizing rule.

Source: 40 CFR 82.156, (a)(1)(ii) · 40 CFR 82.152 (definitions), low-pressure appliance · Hudson Technologies pressure-temperature charts (refrigerant-specific charts)

Question 31

T3-B06 · Recovery requirements

An R-123 chiller has a tube leak. Pulling the evaporator down to 25 mm Hg would draw water into the refrigerant. What's the highest pressure the leaking section can be left at before it's opened?

Rule scope: General Type III
Reveal answer for Question 31

Answer: A. 0 psig.

Why: When leaks make the Table 1 level impossible or would badly contaminate the refrigerant, the tech isolates leaking parts where possible, takes non-leaking parts to the Table 1 level, and takes leaking parts as low as possible without substantial contamination. That level can't be higher than 0 psig.

Why not the others: 5 psig is the oil-change allowance. 10 and 15 psig aren't ceilings anywhere in this rule.

Source: 40 CFR 82.156, (a)(2)

Question 32

T3-B07 · Recovery requirements

A major repair touches only one section of a large chiller, and that section's refrigerant can be isolated into a system receiver. What does the rule allow?

Rule scope: General Type III
Reveal answer for Question 32

Answer: C. Evacuate only that section to the required level, confirm the level, then open it.

Why: Technicians can evacuate either the whole appliance or just the part being serviced, when that part's refrigerant can be isolated to a system receiver. Either way, the tech must verify the required level has been reached before opening.

Why not the others: Evacuating the whole chiller is more than the rule requires. Opening without evacuating skips the part being opened. 0 psig is the non-major ceiling, not the level for a major repair.

Source: 40 CFR 82.156, (a) · 40 CFR 82.152 (definitions), system receiver

Question 33

T3-B08 · Recovery techniques and equipment

A hospital's in-house tech services only the hospital's own chillers, which have permanently attached pump-out units. Which statement is accurate?

Rule scope: General Type III
Reveal answer for Question 33

Answer: D. The tech doesn't need certified self-contained recovery equipment for these chillers.

Why: People who service only appliances they own that have pump-out units are exempt from the requirement to use certified self-contained recovery equipment. System-dependent equipment is barred on appliances over 15 lb unless it's permanently attached as a pump-out unit.

Why not the others: The exemption covers the separate machine, so the tech doesn't have to bring one. Pump-out units are the allowed case over 15 lb, not a banned one. Owning the equipment doesn't remove the technician-certification requirement.

Source: 40 CFR 82.156, (e), (f) · 40 CFR 82.161, (a)(1)(iii)

Question 34

T3-B09 · Recovery techniques and equipment

A university recovers R-123 from a chiller it's retiring and wants it charged into another R-123 chiller the university owns across campus. What does the recovery rule require first?

Rule scope: General Type III
Reveal answer for Question 34

Answer: D. Nothing further; recovered refrigerant can go into another appliance owned by the same person.

Why: Refrigerant can go back into the appliance it came from, or into another appliance owned by the same person, without recycling or reclaiming. "Person" includes organizations like a university.

Why not the others: Reclaiming is required when refrigerant changes owners. Destruction and recycling aren't required here.

Source: 40 CFR 82.156, (h) · 40 CFR 82.152 (definitions), person

Question 35

T3-B10 · Recovery techniques and equipment

A tech builds a recovery rig from a spare compressor and a clean cylinder. Can it be used to recover refrigerant from a low-pressure chiller before a major repair?

Rule scope: General Type III
Reveal answer for Question 35

Answer: A. No; the recovery must use recovery or recycling equipment certified under EPA's rules.

Why: Before opening or disposing of these appliances, refrigerant must be evacuated using a recovery or recycling machine certified under 40 CFR 82.158. A homemade rig isn't certified equipment, whatever vacuum it pulls.

Why not the others: Reaching the level doesn't fix uncertified equipment. The tech's card and the chiller's size don't change the equipment rule.

Source: 40 CFR 82.156, (a)

Question 36

T3-B11 · Recharging

A tech charges vapor into an evacuated R-123 chiller with water in the tubes. Of these readings, which is the LOWEST at which R-123's saturation temperature has reached about 32°F, so liquid can follow without freezing the water?

Rule scope: General Type III
Reveal answer for Question 36

Answer: A. 20 in. Hg vacuum.

Why: R-123's saturation pressure at 32°F is about 4.7 psia, roughly 20.3 in. Hg vacuum. 20 in. Hg vacuum (about 4.9 psia) is just past that point, so the refrigerant now boils at about 33°F. In practice, keep some margin and follow the manufacturer.

Why not the others: At 29 and 25 in. Hg vacuum, R-123 boils far below freezing. 5 psig is above freezing too, but it isn't the lowest reading listed.

Source: EPA Test Topics, Type 3 → Recharging Techniques · Hudson Technologies pressure-temperature charts (refrigerant-specific charts)

Question 37

T3-B12 · Recharging

An R-123 chiller is 20 lb short. The shop has half a cylinder of recovered R-11. What should go in?

Rule scope: General Type III
Reveal answer for Question 37

Answer: B. Only the refrigerant the chiller is built for, R-123 per the nameplate; don't mix refrigerants.

Why: EPA's Core list stresses avoiding mixed refrigerants, and chiller makers tell techs to use the refrigerant on the unit nameplate. A mix can't be reclaimed as either refrigerant and changes how the machine runs.

Why not the others: Sharing a pressure class doesn't make refrigerants interchangeable. A blend, or R-11 with a note, creates exactly the mix EPA warns about.

Source: EPA Test Topics, Core → Recovery Techniques · Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), p. 3 (nameplate refrigerant)

Question 38

T3-B13 · Scope and pressure-temperature

An idle R-123 chiller sits in a 70°F equipment room with its water loops also at 70°F. Assuming no air in the system, about what should the shell gauge read?

Rule scope: General Type III
Reveal answer for Question 38

Answer: C. About 7 in. Hg vacuum.

Why: R-123 boils at about 82°F at atmospheric pressure, so below that temperature it sits in a vacuum. At 70°F its saturation pressure is about 11.4 psia, roughly 6.6 in. Hg vacuum. That's why low-pressure chillers draw air in through leaks.

Why not the others: 10 psig would take a temperature well above 100°F. 0 psig matches about 82°F. 29 in. Hg vacuum is near the recovery level, not a resting chiller.

Source: 40 CFR 82.152 (definitions), low-pressure appliance · Hudson Technologies pressure-temperature charts (refrigerant-specific charts)

Question 39

T3-B14 · Leak detection, relief, and safety

Where should a low-pressure chiller's rupture-disc vent line and purge discharge end up?

Rule scope: General Type III
Reveal answer for Question 39

Answer: B. Outdoors, following ASHRAE Standard 15 and local code, where the discharge won't spray anyone.

Why: A manufacturer's ASHRAE 15 guidance says the purge discharge and the rupture disk must be piped to the outdoors, ending where a release won't spray anyone and can't be blocked or fill with rainwater.

Why not the others: A floor drain puts refrigerant into the building. Piping relief back to the low side defeats the relief device. A cylinder on the line would block the relief path.

Source: Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), pp. 8, 30–31

Question 40

T3-B15 · Leak detection, relief, and safety

The equipment room around an R-123 chiller regularly hits 110°F in summer. What relief-device risk does one chiller manufacturer warn about?

Rule scope: General Type III
Reveal answer for Question 40

Answer: C. The rupture disk can fatigue and break at less than its roughly 15 psig rating.

Why: The cited manufacturer warns that ambient temperatures above 104°F can fatigue the unit's rupture disk so it may break at a pressure lower than its approximately 15 psig design relief point. That warning is product-specific, so use the current manual for the chiller in front of you.

Why not the others: Heat can reduce the rupture disk's margin rather than sealing it. The purge unit removes noncondensables; it doesn't add refrigerant or protect the relief device from excessive ambient temperature.

Source: Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), p. 16

Question 41

T3-B16 · Leak detection, relief, and safety

A large R-123 release has filled a basement equipment room. Someone must go in before it has been ventilated. What protection fits?

Rule scope: General Type III
Reveal answer for Question 41

Answer: A. A self-contained breathing apparatus (SCBA).

Why: Refrigerant vapor displaces oxygen. EPA's Core safety list names SCBA for extreme cases, and a chiller manual notes that SCBA should be kept near the equipment room where codes require it. Better still, let the mechanical ventilation clear the room first.

Why not the others: A dust mask and glasses don't supply air. The purge unit has nothing to do with the room's air.

Source: EPA Test Topics, Core → Safety · Trane CVHE/CVHF/CVHG IOM manual (CVHE-SVX02H-EN, 2015), p. 8

Question 42

T3-B17 · Leak repair rules

An owner wants a room-air automatic leak detection system to replace required leak inspections on an indoor R-123 chiller. Which setup meets the rule?

Rule scope: Part 82 / ODS
Reveal answer for Question 42

Answer: B. Detects 10 ppm, alerts the owner at 100 ppm, has sensors near the compressor, evaporator, and condenser, and is audited or calibrated every year.

Why: A continuously monitoring system that's audited or calibrated every year can replace the quarterly or annual inspections. A room-air system must be indoors, have sensors near high-risk components, detect 10 ppm, and alert the owner at 100 ppm.

Why not the others: 100 ppm detection with a 1,000 ppm alert and five-year calibration misses the required levels and the annual audit. "Any hardwired detector" has no specs. A log-only system never alerts anyone.

Source: 40 CFR 82.157, (g)(4)(i)

Question 43

T3-B18 · Leak repair rules

A 700-lb R-123 chiller serves only an industrial process. It went over 30%, and the leaks were repaired and verified. How often does it need leak inspections now?

Rule scope: Part 82 / ODS
Reveal answer for Question 43

Answer: D. Every three months, until four quarters in a row show it hasn't leaked above 30%.

Why: Industrial process refrigeration and commercial refrigeration appliances with 500 lb or more get quarterly leak inspections until the owner can show four straight quarters under the threshold.

Why not the others: Annual inspections apply to smaller systems and to comfort cooling. Monthly isn't in the rule. Verification tests don't replace the inspection schedule.

Source: 40 CFR 82.157, (g)(1)(i)

Question 44

T3-B19 · Leak repair rules

A certified tech finishes a required leak inspection on an R-123 chiller. What documentation does the tech owe the owner?

Rule scope: Part 82 / ODS
Reveal answer for Question 44

Answer: D. The date, the method or methods used, the location of each leak found, and a certification that all visible and accessible parts were inspected.

Why: Technicians who do leak inspections must give the owner documentation with the inspection date, methods, each leak's location, and a certification that all visible and accessible parts were inspected. The owner keeps it at least three years.

Why not the others: The rule puts a duty on the tech, so "nothing" fails. A card copy isn't an inspection record. A leak-free statement isn't what's required, and may not be true.

Source: 40 CFR 82.157, (l)(3), (l)

Question 45

T3-B20 · Leak repair rules

A 500-lb R-123 comfort-cooling chiller needed 30 lb. The last addition was 400 days ago. Using the annualizing method, what's the leak rate?

Rule scope: Part 82 / ODS
Reveal answer for Question 45

Answer: A. 6%.

Why: The annualizing method uses the shorter of the days since the last addition or 365. So (30 ÷ 500) ÷ (365 ÷ 365) × 100 = 6%. That's under the 10% comfort-cooling threshold.

Why not the others: 5.5% divides by 400 ÷ 365 instead of capping the days at 365. 6.6% multiplies by 400 ÷ 365. 30% forgets to divide by the full charge.

Source: 40 CFR 82.152 (definitions), leak rate, annualizing method · 40 CFR 82.157, (c)(2)(iii)

Question 46

T3-B21 · Leak repair rules

Because of a seasonal change, a technician removes 40 lb of R-123 from a chiller in the fall and adds back 35 lb in the spring, all within one 12-month period. How does the spring addition count?

Rule scope: Part 82 / ODS
Reveal answer for Question 46

Answer: C. As a seasonal variance, which isn't used in the leak-rate calculation if the owner keeps the required records.

Why: EPA defines a seasonal variance as refrigerant removed because of a seasonal change in ambient conditions, then added back in an amount no greater than what was removed, within one 12-month period. Owners don't calculate a leak rate for that addition but must document that they're using the flexibility.

Why not the others: The addition is smaller than the removal, so it isn't treated as leak makeup. There's no 10-lb rule, and nothing here requires reclaimed refrigerant.

Source: 40 CFR 82.152 (definitions), seasonal variance · 40 CFR 82.157, (b), (l)(10)

Question 47

T3-B22 · Leak repair rules

Which is NOT an allowed way to set a chiller's full charge for leak-rate math?

Rule scope: Part 82 / ODS
Reveal answer for Question 47

Answer: C. An estimate from the compressor motor's horsepower.

Why: EPA allows four methods: the manufacturer's figure, a calculation from component sizes, refrigerant density, and piping volume, actual measurements, or an established range using its midpoint. Motor horsepower isn't one of them.

Why not the others: The manufacturer's figure, the component calculation, and actual measurements are all on EPA's list.

Source: 40 CFR 82.152 (definitions), full charge

Question 48

T3-B23 · Leak repair rules

Which item must a retrofit plan for a leaking R-11 chiller include?

Rule scope: Part 82 / ODS
Reveal answer for Question 48

Answer: D. An itemized procedure for converting to the new refrigerant, including compatibility changes, and a schedule of no more than one year.

Why: A retrofit or retirement plan must list, among other things, an itemized conversion procedure with compatibility changes, plans for the recovered refrigerant, and a schedule of no more than one year. It's signed by an authorized company official and kept on site.

Why not the others: The rule doesn't require a manufacturer letter, an exam score, or advance EPA approval of the plan.

Source: 40 CFR 82.157, (h)(2)–(h)(3)

Question 49

T3-B24 · Leak repair rules

A leaking chiller is mothballed partway through the repair timeline. What does that mean, and what does it do to the deadlines?

Rule scope: Part 82 / ODS
Reveal answer for Question 49

Answer: C. Its refrigerant is evacuated to at least atmospheric pressure and it's temporarily shut down; the repair deadlines pause until refrigerant is added again.

Why: To mothball means to evacuate the refrigerant to at least atmospheric pressure and temporarily shut the appliance down. The repair time frames pause while it's mothballed and start again the day refrigerant is added back. The owner keeps records of both dates.

Why not the others: Shutting down with the charge inside is an ordinary shutdown, not mothballing. Mothballing is temporary, so retirement and cancelled deadlines are wrong.

Source: 40 CFR 82.152 (definitions), mothball · 40 CFR 82.157, (d)(3), (l)(8)

Question 50

T3-B25 · Leak repair rules

A 300-lb R-245fa chiller leaked 130% of its full charge during calendar year 2026. What must the owner do?

Rule scope: Part 84 / HFC
Reveal answer for Question 50

Answer: C. Report it to EPA by March 1, 2027, under the HFC leak-repair rule, 40 CFR 84.106.

Why: Under 40 CFR 84.106, appliances holding 15 lb or more of a covered HFC that leak 125% or more of their full charge in a calendar year must be reported to EPA by March 1 of the following year. R-245fa is an HFC, so 82.157 doesn't apply.

Why not the others: "Nothing" was true for HFC equipment before 2026. Ten days isn't the deadline. 40 CFR 82.157 is the ozone-depleting-refrigerant rule.

Source: 40 CFR 84.106, (j), (m)(4)

Score Test B: count your correct answers in questions 26–50. 18 or more meets the reference line.

Score your Type 3 practice

Score your Type 3 practice
TestQuestionsYour scoreReference line
Practice Test A1–25___ / 2518
Practice Test B26–50___ / 2518

Why 18? The federal rule sets a 70% passing score for the closed-book Type III test (Appendix D, section e). On 25 questions, 17 correct is 68% and 18 correct is 72%, so 18 is the first whole-question score that clears 70%.

What your score means. It's how you did on these 50 original questions. It isn't an official score, and it can't predict your result on the real exam. Two 25-question tests are a useful checkpoint, not a precise measurement.

The real Type III section is scored on its own, and you also need a passing Core section to get any Section 608 card. A strong Test A doesn't make up for a weak Core.

Review your misses by topic

Circle the question numbers you missed, then start with the row that has the most circles.

Review your misses by topic
TopicTest ATest BWhat to reread
Scope and pressure-temperature1, 1126, 27, 38Which refrigerants are low-pressure, and how to read a low-pressure P-T chart in inches of vacuum. See the refrigerant table.
Recovery requirements2, 3, 4, 528, 29, 30, 31, 3225 mm Hg absolute, the major-repair definition, and the 0 psig, 5 psig, and 85°F rules in 40 CFR 82.156.
Recovery techniques and equipment6, 7, 833, 34, 35Liquid first, vapor after, 130°F oil, water in the tubes, certified recovery equipment, and pump-out units.
Recharging9, 1036, 37Vapor before liquid, the evaporator charging valve, and never mixing refrigerants.
Leak detection, relief, and safety12, 13, 14, 2539, 40, 41Excessive purging, rupture discs, leak-test pressure, venting relief outdoors, room monitors, and SCBA.
Leak repair rules15–24 · 16, 17, 18, 19, 20, 21, 22, 2342–50 · 43, 44, 45, 46, 47, 48, 49Thresholds, calculations, inspections, verification tests, plans, and the 2026 HFC rule in 40 CFR 82.157 and 40 CFR 84.106.

Reread each missed explanation, close it, and say the rule out loud. Recognizing an answer isn't the same as producing it. Then retake the test another day; scoring well on the same questions an hour later mostly measures memory of these items.

Type 3 numbers to know

Type 3 numbers to know
NumberWhat it meansSource
Below 45 psia at 104°FThe line that makes a refrigerant low-pressure, and its equipment Type III82.152
25 mm Hg absoluteRequired level before opening for a major repair or disposing of a low-pressure appliance, whatever the recovery machine's age or the chiller's charge. That's about 29 in. Hg vacuum, or 25,000 microns.82.156, Table 1
More than 4 sq in for more than 15 minutesMakes work "major" even when no compressor, condenser, evaporator, or auxiliary coil comes out82.152
0 psigHighest pressure for a non-major repair; also the ceiling for leaking parts that can't reach 25 mm Hg82.156(a)(1)–(2)
5 psigHighest pressure for an oil change82.156(a)(1)(iii)
85°F boiling pointAt or below: heat only for non-major pressurizing. Above: heat first, then nitrogen up to atmospheric.82.156(a)(1)(ii)
130°FHeat the oil to this before draining itEPA Test Topics
About 15 psigWhere one manufacturer's chiller rupture disk breaks, on the evaporator sideTrane manual, p. 31
Manufacturer-specificNitrogen leak-test pressure is not a single generic number on this page. The cited Trane manual limits its product line to 8 psig dry nitrogen and describes an approximately 15 psig rupture-disk relief point. Use the current unit manual.Trane manual, pp. 9, 31
10% / 20% / 30%Leak-rate thresholds for comfort cooling / commercial refrigeration / industrial process refrigeration82.157(c), 84.106(c)
30 days · 10 days · 1 yearRepair window · follow-up verification test · retrofit or retirement82.157(d), (e), (h)
125% by March 1Chronic-leaker report for the prior calendar year82.157(j), 84.106(j)

EPA's Type 3 topic list also names the high-pressure cut-out setting for recovery units used on low-pressure chillers. This audit did not verify a current authoritative value, so this page does not teach or test a number for it.

Low-pressure refrigerants at a glance

Low-pressure refrigerants at a glance
RefrigerantFamilyBoils at 1 atmNon-major repair pressurizingBoils at 32°F when the gauge readsPressure at 104°FLeak-repair rule (at or above the charge trigger)
R-11CFC74.7°FHeat onlyabout 18 in. Hg vacuum25.3 psia40 CFR 82.157 (50 lb or more)
R-123HCFC82.1°FHeat onlyabout 20 in. Hg vacuum22.4 psia40 CFR 82.157 (50 lb or more)
R-113CFC117.7°FHeat, then nitrogen to atmosphericabout 25.5 in. Hg vacuum11.4 psia40 CFR 82.157 (50 lb or more)
R-245faHFC59.1°FHeat onlyabout 14 in. Hg vacuum36.4 psia40 CFR 84.106 (15 lb or more, since Jan. 1, 2026)

The pressure-temperature values are approximate and were cross-checked against published refrigerant-specific Hudson Technologies pressure-temperature charts; vacuum conversions are arithmetic. Printed charts can differ slightly. EPA names all four refrigerants as low-pressure examples in 40 CFR 82.152. The pressurizing column applies the 85°F rule in 40 CFR 82.156(a)(1)(ii).

Which leak rule applies? Read the refrigerant first.

  • CFC or HCFC (R-11, R-113, R-123), 50 lb or more: 40 CFR 82.157.
  • HFC such as R-245fa, or another substitute with a GWP above 53, 15 lb or more: 40 CFR 84.106, starting January 1, 2026. Appliances holding only an ozone-depleting refrigerant are excluded from this rule.
  • The thresholds match across both rules (10% comfort cooling, 20% commercial, 30% industrial process). What changes is which appliances are covered.

Old answers you'll still see

Older manuals, flashcard decks, and free quizzes still carry these.

Old answers you'll still see
You might seeCurrent answerPractice
"Recover low-pressure chillers to 25 in. Hg"25 mm Hg absolute, about 29 in. Hg vacuum (82.156, Table 1)2, 3, 28
Leak thresholds of 15% comfort cooling and 35% commercial or industrial10%, 20%, and 30% since 2019 (82.157(c))15, 18, 19
"The rupture disc is on the high side"One manufacturer's manual puts it on the evaporator's suction elbow (Trane manual, p. 31)13
"R-11 is an HCFC"R-11 is a CFC; EPA lists CFC-11 among the common CFCs (EPA Test Topics)Refrigerant table
"Every chiller is Type III"Only low-pressure appliances are; an R-22 chiller is Type II (82.152)1

Type 3 exam quick facts

Is Type 3 the same as Type III? Yes. EPA's topic page calls the section "Type 3 (Low-pressure)," and the regulation calls the certification Type III. It covers servicing and disposing of low-pressure appliances (EPA certification requirements).

How many questions, and what passes? Each test has at least 25 Core questions plus at least 25 from each technical group you're certifying in (82.161(c)). The closed-book passing score is 70% per section, which is 18 of 25 (Appendix D).

Is it open book? No. Type III is closed book, proctored, and given in a secure environment by an EPA-approved program (Appendix D, section a).

Does it expire? EPA says Section 608 technician credentials don't expire (EPA certification requirements).

Are these real EPA exam questions? No. They're original practice questions written by the Castleport Test Prep Editorial Team from EPA's public topic list and the current rules. EPA releases its test bank only to approved certification programs (82.161(c)).

Where to go next

Sources

Checked September 27, 2026.


Castleport Test Prep is an independent exam prep publisher. We are not affiliated with, endorsed by, or approved by the U.S. Environmental Protection Agency or any Section 608 certification program. These are original, unofficial practice questions, not real, recalled, or official exam items. Exam, certification, and product names identify their subjects, and trademarks belong to their respective owners. Current federal rules and your testing program's written terms control.

By the Castleport Test Prep Editorial Team. Last verified September 27, 2026: EPA Section 608 Type 3 topics, technician-certification and test rules, evacuation requirements, and the current Part 82 and Part 84 leak-repair rules. Found an error? Tell us.