Free NASCLA Practice Test: 50 Questions With Answers
These are 50 original, unofficial practice questions for the NASCLA Accredited Examination for Commercial General Building Contractors, proportioned to PSI's current 12-area content outline, and each one comes with the answer, an explanation, and the section to look up.
Free · no signup · not real exam questions · exam facts last verified October 4, 2026
Practice questions
Try each question before you read the answer below it. Questions from all 12 content areas are mixed together, and the content area is shown after each answer.
Question 1
NASCLA-F001
A crew is setting forms on an elevated deck of a commercial building. The deck has an unprotected edge 9 feet above the level below. Under OSHA's construction rules, which protection meets the general requirement for that edge?
Show answer
Answer: A. A guardrail system, safety net system, or personal fall arrest system
Any unprotected side or edge 6 feet or more above a lower level needs a guardrail, safety net, or personal fall arrest system. A safety monitor by itself is only an option for roofing work on low-slope roofs 50 feet wide or less, so it doesn't fit a deck. Hard hats protect against falling objects, not falls. Ten feet is the scaffold trigger, a separate rule.
Look it up: 29 CFR 1926.501(b)(1); compare 1926.501(b)(10) and 1926.451(g)(1).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.501 (eCFR); 29 CFR 1926.451 (eCFR)
Content area: General Requirements · Fall protection trigger height
Question 2
NASCLA-F002
Your estimated cost for a tenant-improvement job is $80,000. Your company prices work with a 20% markup on cost. What is the bid price?
Show answer
Answer: B. $96,000
Markup is applied to cost: $80,000 × 1.20 = $96,000. $100,000 is what you'd charge for a 20% gross margin ($80,000 ÷ 0.80), which is a different calculation (see the margin question later in this set). $64,000 subtracts 20% instead of adding it. $116,000 adds the markup twice.
Look it up: Calculation. Price = cost × (1 + markup).
Reference status: Calculation: every number you need is in the question.
Content area: Procurement and Contracting Requirements · Markup on cost
Question 3
NASCLA-F003
A trench for a storm line is 6 feet deep in ordinary soil, not stable rock. The competent person sees no sign of a cave-in. What does OSHA require for employees working in the trench?
Show answer
Answer: D. A protective system such as sloping, benching, shoring, or a shield
Every employee in an excavation must be protected from cave-ins unless the excavation is entirely in stable rock, or it is less than 5 feet deep and a competent person finds no sign of a potential cave-in. At 6 feet, the competent person's finding doesn't remove the requirement. OSHA sets no 10-foot or one-hour threshold.
Look it up: 29 CFR 1926.652(a)(1).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.652 (eCFR)
Content area: Site Construction · Trench protective systems
Question 4
NASCLA-F004
During steel erection, an ironworker who is not a connector and not in a controlled decking zone is working on a surface with an unprotected edge. Above what height does OSHA's steel erection standard require fall protection?
Show answer
Answer: C. 15 feet
Subpart R requires protection for steel erection workers on surfaces with an unprotected edge more than 15 feet above a lower level. Six feet is the general construction trigger in Subpart M, and 10 feet is the scaffold trigger. Thirty feet (or two stories, whichever is less) is the connector rule, which this worker is not covered by.
Look it up: 29 CFR 1926.760(a)(1) and (b)(1).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.760 (eCFR)
Content area: Metals · Steel erection fall protection
Question 5
NASCLA-F005
A slab on grade is 40 feet by 30 feet and 6 inches thick. You add 5% for waste and round the order up to the next half cubic yard. How many cubic yards do you order?
Show answer
Answer: B. 23.5 cubic yards
Convert thickness to feet first: 6 in = 0.5 ft. Volume = 40 × 30 × 0.5 = 600 cubic feet. One cubic yard is 3 × 3 × 3 = 27 cubic feet, so 600 ÷ 27 = 22.22 cubic yards. Add waste: 22.22 × 1.05 = 23.33, which rounds up to 23.5. 22.0 drops the waste and rounds down. 24.5 uses 10% waste (24.44, rounded up). 267 comes from using 6 instead of 0.5 for the thickness (7,200 ÷ 27 = 266.7).
Look it up: Calculation. A yard is 3 feet (NIST lists the foot as 0.3048 m and the yard as 0.9144 m), so a cubic yard is 27 cubic feet.
Reference status: Calculation: every number you need is in the question.
Source: NIST SP 811, Appendix B.8
Content area: Concrete · Concrete quantity
Question 6
NASCLA-F006
What top-edge height does OSHA require for the top rail of a guardrail system under the general fall protection rules?
Show answer
Answer: C. 42 inches, plus or minus 3 inches
The top rail must be 42 inches, plus or minus 3 inches, above the walking/working level. It can go above 45 inches when conditions warrant, if the system meets the other criteria. 39 inches is the lowest the top edge may deflect under the 200-pound test load, not the installed height. Scaffold guardrails follow their own range (38 to 45 inches for newer supported scaffolds).
Look it up: 29 CFR 1926.502(b)(1) and (b)(4); compare 1926.451(g)(4)(ii).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.502 (eCFR); 29 CFR 1926.451 (eCFR)
Content area: General Requirements · Guardrail height
Question 7
NASCLA-F007
A non-exempt carpenter earns a regular rate of $30 per hour and works 46 hours in one workweek. Applying only the federal Fair Labor Standards Act, what is the gross pay for that week?
Show answer
Answer: B. $1,470
Federal overtime is owed for hours over 40 in a workweek at no less than 1½ times the regular rate. 40 × $30 = $1,200, and 6 × $45 = $270, for $1,470. $1,380 pays all 46 hours at straight time. $1,560 pays the 6 overtime hours at double time. $2,070 pays every hour at time and a half. Some states add daily overtime rules; this question is federal only.
Look it up: 29 CFR 778.101 and 778.107.
Reference status: Not on PSI's reference list: federal rule (29 CFR Part 778).
Source: 29 CFR 778.101 (eCFR); 29 CFR 778.107 (eCFR)
Content area: Procurement and Contracting Requirements · Overtime pay
Question 8
NASCLA-F008
Using OSHA's sloping tables, what is the maximum allowable slope for a simple-slope excavation 20 feet deep or less in Type C soil?
Show answer
Answer: C. 1½ horizontal to 1 vertical
Type C soil allows a maximum slope of 1½:1 (H:V), the flattest of the three soil types. ¾:1 is the Type A maximum, and 1:1 is Type B. 2:1 is flatter than required; it is allowed but it isn't the maximum allowable slope. If you don't classify the soil at all, OSHA's first sloping option also defaults to 1½:1.
Look it up: 29 CFR 1926 Subpart P, Appendix B, Figure B-1; 1926.652(b)(1)(i).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926 Subpart P, Appendix B (eCFR); 29 CFR 1926.652 (eCFR)
Content area: Site Construction · Soil type and slope
Question 9
NASCLA-F009
A masonry crew will build a block wall 12 feet high. How wide must the limited access zone be, and on which side of the wall?
Show answer
Answer: B. 16 feet, on the unscaffolded side
The limited access zone equals the wall height plus 4 feet (12 + 4 = 16 feet), runs the full length of the wall, and goes on the unscaffolded side, where a falling wall would land with no one working there. It must be set up before the wall is started, and only the crew building the wall may enter it.
Look it up: 29 CFR 1926.706(a)(1) through (a)(4).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.706 (eCFR)
Content area: Masonry · Limited access zone
Question 10
NASCLA-F010
Workers are on a supported frame scaffold whose platform is 12 feet above the slab. It is not a type of scaffold with its own special rule. What fall protection does OSHA require?
Show answer
Answer: D. A guardrail system or a personal fall arrest system
Employees on a scaffold more than 10 feet above a lower level must be protected from falling. For scaffolds without their own specific rule, that means personal fall arrest systems or guardrail systems. Fifteen feet is the steel erection trigger. Toeboards and hard hats address falling objects, not falls. Safety monitors are a roofing option, not a scaffold option.
Look it up: 29 CFR 1926.451(g)(1) and (g)(1)(vii).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.451 (eCFR)
Content area: General Requirements · Scaffold fall protection
Question 11
NASCLA-F011
A 30-foot wall is framed with studs at 16 inches on center, starting with a stud at one end. Ignoring openings, corners, and doubled studs, how many studs do you need?
Show answer
Answer: C. 24
Convert to inches: 30 ft × 12 = 360 in. 360 ÷ 16 = 22.5 spaces, which rounds up to 23 spaces so the last stud lands at the end of the wall. Studs = spaces + 1 = 24. 23 forgets the starting stud. 22 drops the partial space. 30 assumes one stud per foot.
Look it up: Calculation. Members = (length ÷ spacing, rounded up) + 1.
Reference status: Calculation: every number you need is in the question.
Content area: Wood · Stud count
Question 12
NASCLA-F012
On your current pay application, the total value of work completed to date is $150,000. The contract withholds 10% retainage, and you've already been paid $90,000. How much should this payment be?
Show answer
Answer: A. $45,000
Earned to date less retainage: $150,000 × 0.90 = $135,000. Subtract what you've already been paid: $135,000 − $90,000 = $45,000. $60,000 ignores retainage. $54,000 treats the $60,000 difference as this period's work and holds 10% of it, which double-counts. $135,000 is the total earned to date, not this payment.
Look it up: Calculation. Payment due = (work completed to date × (1 − retainage)) − previous payments.
Reference status: Calculation: every number you need is in the question.
Content area: Procurement and Contracting Requirements · Retainage
Question 13
NASCLA-F013
Employees on a jobsite use temporary 120-volt, single-phase, 20-ampere receptacles that aren't part of the building's permanent wiring. The employer is not running an assured equipment grounding conductor program. What does OSHA require for these receptacles?
Show answer
Answer: A. Approved ground-fault circuit interrupters (GFCIs)
Employers must use either GFCIs or an assured equipment grounding conductor program. Without the program, all 120-volt, single-phase, 15- and 20-ampere receptacles not part of the permanent wiring and in use by employees need approved GFCIs. Weekly cord inspection isn't an alternative; the assured program itself requires daily visual inspection plus testing. The rule covers 20-ampere receptacles too, indoors or out.
Look it up: 29 CFR 1926.404(b)(1)(i) and (ii).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.404 (eCFR)
Content area: Electrical Systems · Ground-fault protection on jobsites
Question 14
NASCLA-F014
A roof has 2,400 square feet of actual roof surface. You add 10% for waste and order whole squares. How many squares do you order?
Show answer
Answer: C. 27
A roofing square covers 100 square feet. 2,400 ÷ 100 = 24 squares. Add waste: 24 × 1.10 = 26.4, and you can't order 0.4 of a square, so order 27. 24 skips the waste. 26 rounds down and leaves you short. 264 multiplies by 1.10 but forgets to divide by 100.
Look it up: Calculation. Squares = area ÷ 100, plus waste, rounded up.
Reference status: Calculation: every number you need is in the question.
Content area: Thermal and Moisture Protection · Roofing squares
Question 15
NASCLA-F015
A personal fall arrest system must be rigged so the worker can free fall no more than ___ and travel no more than ___ while decelerating.
Show answer
Answer: A. 6 feet; 3.5 feet
A personal fall arrest system must keep free fall to 6 feet or less, stop the worker without contacting any lower level, and limit deceleration distance to 3.5 feet. Two feet is the free-fall limit for positioning device systems, a different system. The other pairs aren't OSHA figures.
Look it up: 29 CFR 1926.502(d)(16)(iii) and (iv); compare 1926.502(e)(1).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.502 (eCFR)
Content area: General Requirements · Personal fall arrest limits
Question 16
NASCLA-F016
A rooftop unit is rated at 60,000 Btu per hour of cooling. What is that capacity in tons of refrigeration?
Show answer
Answer: B. 5 tons
One ton of refrigeration is 12,000 Btu per hour. 60,000 ÷ 12,000 = 5 tons. 6 tons comes from dividing by 10,000. 3 tons divides by 20,000. 12 tons confuses the 12,000 figure with the answer.
Look it up: NIST SP 811, Appendix B.9 (heat flow rate): ton of refrigeration = 12,000 Btu/h.
Reference status: Calculation using a standard conversion (NIST).
Source: NIST SP 811, Appendix B.9
Content area: Mechanical and Plumbing Systems · Cooling capacity in tons
Question 17
NASCLA-F017
A contractor's balance sheet shows total liabilities of $400,000 and owners' equity of $200,000. What is the debt-to-equity ratio?
Show answer
Answer: D. 2.0
Debt-to-equity = total liabilities ÷ equity = $400,000 ÷ $200,000 = 2.0. The company carries $2 of debt for every $1 of owner investment. 0.5 flips the fraction. 1.0 and 1.5 don't come from these two numbers.
Look it up: SEC Beginners' Guide to Financial Statements, "Financial Statement Ratios and Calculations."
Reference status: Calculation; formula from the SEC's guide to financial statements.
Source: SEC, Beginners' Guide to Financial Statements
Content area: Procurement and Contracting Requirements · Debt-to-equity ratio
Question 18
NASCLA-F018
A trench is 4½ feet deep. How far may employees have to travel laterally to reach a stairway, ladder, ramp, or other safe means of egress?
Show answer
Answer: B. No more than 25 feet
Trenches 4 feet or more deep need a safe means of egress located so employees travel no more than 25 feet laterally. Don't mix up the two depth triggers: egress starts at 4 feet, while protective systems start at 5 feet (unless the soil exception applies).
Look it up: 29 CFR 1926.651(c)(2); compare 1926.652(a)(1).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.651 (eCFR); 29 CFR 1926.652 (eCFR)
Content area: Site Construction · Trench egress
Question 19
NASCLA-F019
Vertical dowels stick up from a footing where workers could fall onto them. What does OSHA require?
Show answer
Answer: D. Guarding the bars to eliminate the hazard of impalement
All protruding reinforcing steel that employees could fall onto or into must be guarded to eliminate the impalement hazard. The rule has no height or bar-length threshold. Paint or flagging makes bars visible but doesn't eliminate impalement, which is what the standard requires.
Look it up: 29 CFR 1926.701(b).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.701 (eCFR)
Content area: Concrete · Protruding reinforcing steel
Question 20
NASCLA-F020
On the third floor, a window opening's outside bottom edge is 20 feet above grade. Its inside bottom edge (the sill) is 30 inches above the floor. Employees work near it. What protection does OSHA require?
Show answer
Answer: A. A guardrail system, safety net system, or personal fall arrest system
The wall-opening rule applies where the outside bottom edge is 6 feet or more above the lower level and the inside bottom edge is less than 39 inches above the walking surface. A 30-inch sill is under 39 inches, so a guardrail, safety net, or personal fall arrest system is required. Warning lines are a low-slope roofing tool, and the rule doesn't wait for frames.
Look it up: 29 CFR 1926.501(b)(14).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.501 (eCFR)
Content area: Doors, Windows, and Glazing · Wall openings during construction
Question 21
NASCLA-F021
A portable extension ladder gives access to an upper landing. How far must the side rails extend above the landing surface, if the ladder is long enough to do so?
Show answer
Answer: A. 3 feet
The side rails must extend at least 3 feet above the upper landing. If the ladder is too short, it must be secured at the top to a rigid support and a grasping device such as a grab rail provided. The other heights aren't the OSHA figure.
Look it up: 29 CFR 1926.1053(b)(1).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.1053 (eCFR)
Content area: General Requirements · Ladder extension
Question 22
NASCLA-F022
A contractor has $350,000 in current assets and $220,000 in current liabilities. What is its working capital?
Show answer
Answer: A. $130,000
Working capital = current assets − current liabilities = $350,000 − $220,000 = $130,000. It's the money left if the company paid its debts due within a year from its current assets. $570,000 adds instead of subtracting. 1.59 divides the two figures, which gives a ratio, not working capital. $220,000 is just the liabilities.
Look it up: SEC Beginners' Guide to Financial Statements, "Working Capital."
Reference status: Calculation; formula from the SEC's guide to financial statements.
Source: SEC, Beginners' Guide to Financial Statements
Content area: Procurement and Contracting Requirements · Working capital
Question 23
NASCLA-F023
Under OSHA's steel erection standard, connectors must be protected from fall hazards of more than what height?
Show answer
Answer: D. Two stories or 30 feet, whichever is less
Connectors must be protected from fall hazards of more than two stories or 30 feet, whichever is less. At heights over 15 feet and up to that connector threshold, they must be provided with a complete personal fall arrest system or other permitted protection and wear the equipment needed to be tied off. 'Whichever is greater' would allow a higher unprotected exposure than the rule does.
Look it up: 29 CFR 1926.760(b)(1) and (b)(3).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.760 (eCFR)
Content area: Metals · Connectors
Question 24
NASCLA-F024
A commercial project will clear and grade 2.5 acres. It isn't part of a larger plan of development. Under EPA's stormwater rules, does the construction activity need NPDES stormwater permit coverage?
Show answer
Answer: D. Yes, construction disturbing 1 acre or more needs coverage
Construction that disturbs at least 1 acre and less than 5 acres is "small construction activity," which needs permit coverage. Five acres or more is covered under the larger category. Permitting authorities can grant waivers in limited cases (for example, a low rainfall erosivity factor), and many states run their own NPDES programs, so the permit itself may come from your state. No 100-foot or public-owner rule applies.
Look it up: 40 CFR 122.26(b)(14)(x) and (b)(15)(i).
Reference status: Not on PSI's reference list as a rule; the listed EPA SWPPP guide covers stormwater plans. Rule: 40 CFR 122.26.
Source: 40 CFR 122.26 (eCFR)
Content area: Site Construction · Stormwater permit coverage
Question 25
NASCLA-F025
A room is 12 feet by 14 feet with 8-foot walls. You'll hang 4×8 drywall sheets on the walls and ceiling, with no deductions for openings, rounding up to whole sheets. How many sheets do you need?
Show answer
Answer: C. 19
Walls: perimeter 2 × (12 + 14) = 52 ft × 8 ft = 416 sq ft. Ceiling: 12 × 14 = 168 sq ft. Total = 584 sq ft. Each sheet covers 32 sq ft, so 584 ÷ 32 = 18.25, which rounds up to 19. 13 covers the walls only. 18 rounds down and leaves you short. 24 counts the ceiling twice.
Look it up: Calculation. Sheets = total area ÷ 32, rounded up.
Reference status: Calculation: every number you need is in the question.
Content area: Finishes · Drywall quantity
Question 26
NASCLA-F026
A supported scaffold has a 5-foot base width and will be built 22 feet tall. What does OSHA require because of its proportions?
Show answer
Answer: A. Restrain it from tipping by guying, tying, or bracing
Supported scaffolds with a height-to-base-width ratio of more than 4:1 must be restrained from tipping. 22 ÷ 5 = 4.4, which is more than 4:1. The 3-foot width figure only changes how often ties are repeated vertically. And scaffolds must be inspected by a competent person before each work shift, not weekly.
Look it up: 29 CFR 1926.451(c)(1) and (f)(3).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.451 (eCFR)
Content area: General Requirements · Scaffold tipping restraint
Question 27
NASCLA-F027
On a federal construction contract covered by the Miller Act, whom does the payment bond protect?
Show answer
Answer: D. People who supply labor and material for the work
The Miller Act requires two bonds. The payment bond protects all persons supplying labor and material for the contract work. The performance bond protects the Government. The surety issues the bonds; it isn't the party they protect.
Look it up: 40 U.S.C. 3131(b)(1) and (b)(2).
Reference status: Not on PSI's reference list: federal statute (40 U.S.C. 3131).
Source: 40 U.S.C. 3131 (Cornell LII)
Content area: Procurement and Contracting Requirements · Miller Act payment bond
Question 28
NASCLA-F028
During tensioning of post-tensioned tendons, who may stand behind the jack?
Show answer
Answer: D. Only employees essential to the post-tensioning operation
No employee except those essential to the post-tensioning operation may be behind the jack during tensioning. Signs and barriers must also limit access to the area. PPE doesn't create an exception, and the rule doesn't ban essential workers or single out inspectors.
Look it up: 29 CFR 1926.701(c)(1) and (c)(2).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.701 (eCFR)
Content area: Concrete · Post-tensioning safety
Question 29
NASCLA-F029
About how many Btu per hour does a 10-kilowatt electric duct heater put out?
Show answer
Answer: C. 34,100 Btu/h
NIST lists 1 Btu per hour as 0.2930711 watt, so 1 kW ≈ 3,412 Btu/h. 10 kW × 3,412 ≈ 34,100 Btu/h. 2,930 Btu/h multiplies by 0.293 instead of dividing. 12,000 Btu/h is one ton of refrigeration, an unrelated figure. 120,000 Btu/h multiplies 10 by that ton figure.
Look it up: NIST SP 811, Appendix B.9 (heat flow rate): Btu/h to watt.
Reference status: Calculation using a standard conversion (NIST).
Source: NIST SP 811, Appendix B.9
Content area: Mechanical and Plumbing Systems · Electric heat output
Question 30
NASCLA-F030
An employer who must keep OSHA injury and illness records must post the annual summary (Form 300-A) for the previous year during what period?
Show answer
Answer: B. February 1 through April 30
The annual summary must be posted no later than February 1 of the year after the year covered and stay up until April 30. A company executive must certify it first. The other windows aren't the rule.
Look it up: 29 CFR 1904.32(b)(3) and (b)(6).
Reference status: Not on PSI's reference list: federal rule (29 CFR Part 1904).
Source: 29 CFR Part 1904, Subpart D (eCFR)
Content area: General Requirements · OSHA 300-A posting
Question 31
NASCLA-F031
An excavation in Type B soil is 10 feet deep with a 4-foot-wide bottom. Both sides are cut as simple slopes at the maximum allowable slope. How wide is the excavation at the top?
Show answer
Answer: C. 24 feet
Type B allows a maximum slope of 1:1 (H:V), so each side runs back 10 feet over the 10-foot depth. Top width = 4 + 10 + 10 = 24 feet. 14 feet slopes only one side. 19 feet uses Type A's ¾:1 (7.5 feet per side). 34 feet uses Type C's 1½:1 (15 feet per side).
Look it up: 29 CFR 1926 Subpart P, Appendix B, Figure B-1.2. Calculation: top width = bottom width + 2 × (depth × H/V ratio).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926 Subpart P, Appendix B (eCFR)
Content area: Site Construction · Sloped excavation width
Question 32
NASCLA-F032
Your annual overhead is $240,000. On average, your gross margin is 20% of revenue. How much annual revenue do you need just to cover overhead?
Show answer
Answer: C. $1,200,000
Gross margin dollars must equal overhead at break-even: revenue × 0.20 = $240,000, so revenue = $240,000 ÷ 0.20 = $1,200,000. $288,000 marks overhead up 20%. $960,000 is 80% of the right answer. $4,800,000 divides by 0.05.
Look it up: Calculation. Break-even revenue = overhead ÷ gross margin %.
Reference status: Calculation: every number you need is in the question.
Content area: Procurement and Contracting Requirements · Break-even revenue
Question 33
NASCLA-F033
A roof deck needs 1,920 square feet of sheathing. You'll use 4×8 panels, add 10% for waste, and round up to whole panels. How many panels do you order?
Show answer
Answer: D. 66
Each 4×8 panel covers 32 sq ft. 1,920 ÷ 32 = 60 panels. Add waste: 60 × 1.10 = 66 panels. 60 skips waste. 54 subtracts the waste instead of adding it. 64 isn't tied to the stated waste factor.
Look it up: Calculation. Panels = (area ÷ 32) × (1 + waste), rounded up.
Reference status: Calculation: every number you need is in the question.
Content area: Wood · Sheathing quantity
Question 34
NASCLA-F034
A non-self-supporting extension ladder has a working length of 20 feet from its foot to the top support. About how far should the foot be from the wall?
Show answer
Answer: C. 5 feet
OSHA's rule is that the horizontal distance from the top support to the foot is about one-quarter of the working length: 20 ÷ 4 = 5 feet. 2.5 feet is the one-eighth ratio, which applies only to wood job-made ladders with spliced side rails. 10 feet would set the ladder far too flat.
Look it up: 29 CFR 1926.1053(b)(5)(i) and (ii).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.1053 (eCFR)
Content area: General Requirements · Ladder angle
Question 35
NASCLA-F035
You hire a laborer for ongoing work expected to last more than three business days. Under federal rules, when must you complete Section 2 of Form I-9?
Show answer
Answer: B. Within three business days of the hire
The employer must examine the documents and complete Section 2 within three business days of the hire. Only when the job lasts less than three business days must it be done at the time of hire. The employee completes Section 1 at the time of hire.
Look it up: 8 CFR 274a.2(b)(1)(ii) and (iii).
Reference status: Not on PSI's reference list: federal rule (8 CFR 274a.2).
Source: 8 CFR 274a.2 (eCFR)
Content area: Procurement and Contracting Requirements · Form I-9 timing
Question 36
NASCLA-F036
Unless otherwise supported against overturning and collapse, masonry walls over what height must be braced until permanent supporting elements are in place?
Show answer
Answer: A. 8 feet
Masonry walls over 8 feet high must be adequately braced to prevent overturning and collapse unless they are otherwise adequately supported. The bracing stays until permanent supports are in place. For walls over 8 feet, the limited access zone also stays until that bracing requirement is met.
Look it up: 29 CFR 1926.706(a)(5) and (b).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.706 (eCFR)
Content area: Masonry · Bracing masonry walls
Question 37
NASCLA-F037
A storefront schedule shows 24 windows, each with a glass area of 3 feet by 5 feet. You add 5% for breakage. How many square feet of glass do you order?
Show answer
Answer: B. 378 sq ft
Each window is 3 × 5 = 15 sq ft. 24 × 15 = 360 sq ft. Add 5%: 360 × 1.05 = 378 sq ft. 360 skips the allowance. 396 uses 10%. 432 uses 20%.
Look it up: Calculation. Area = count × width × height × (1 + allowance).
Reference status: Calculation: every number you need is in the question.
Content area: Doors, Windows, and Glazing · Glazing quantity
Question 38
NASCLA-F038
A federal construction contract sets liquidated damages at $500 per calendar day. The contractor reaches completion 12 days late with no approved time extension. How much in liquidated damages applies?
Show answer
Answer: B. $6,000
12 days × $500 = $6,000. Under the FAR, liquidated damages aren't punitive. They compensate the Government for probable damages, so the rate must be a reasonable forecast of the harm from late performance. That's why they're enforceable. $500 is one day, and $12,000 doubles the rate.
Look it up: FAR 11.501(b). Calculation: days late × daily rate.
Reference status: Not on PSI's reference list: federal regulation (FAR 11.501).
Source: FAR 11.501 (Acquisition.gov)
Content area: Procurement and Contracting Requirements · Liquidated damages
Question 39
NASCLA-F039
A guardrail top rail must withstand, without failure, a force of at least how much applied within 2 inches of the top edge?
Show answer
Answer: D. 200 pounds
Top rails must withstand at least 200 pounds in any outward or downward direction. Midrails and screens must withstand 150 pounds, and toeboards 50 pounds.
Look it up: 29 CFR 1926.502(b)(3), (b)(5), and (j)(2).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.502 (eCFR)
Content area: General Requirements · Guardrail strength
Question 40
NASCLA-F040
You'll paint 1,800 square feet of wall with two coats. The manufacturer's spread rate is 350 square feet per gallon. How many whole gallons do you buy?
Show answer
Answer: D. 11
Two coats double the area: 1,800 × 2 = 3,600 sq ft. 3,600 ÷ 350 = 10.29 gallons, which rounds up to 11 whole gallons. 10 rounds down and runs short. 6 is one coat (5.14, rounded up), and 5 is one coat rounded down.
Look it up: Calculation. Gallons = (area × coats) ÷ spread rate, rounded up.
Reference status: Calculation: every number you need is in the question.
Content area: Finishes · Paint quantity
Question 41
NASCLA-F041
You buy a skid steer for $60,000. You expect it to last 5 years and be worth $10,000 at the end. Using straight-line depreciation, how much do you record each year?
Show answer
Answer: A. $10,000
Straight-line depreciation spreads cost less salvage evenly: ($60,000 − $10,000) ÷ 5 = $10,000 per year. $12,000 ignores salvage value. $14,000 adds salvage instead of subtracting it. $50,000 is the total depreciation over all five years. Tax depreciation follows IRS methods, which this question doesn't test.
Look it up: Calculation. Annual depreciation = (cost − salvage) ÷ useful life. The SEC guide explains depreciation as spreading an asset's cost over the periods it's used.
Reference status: Calculation: every number you need is in the question.
Source: SEC, Beginners' Guide to Financial Statements
Content area: Procurement and Contracting Requirements · Straight-line depreciation
Question 42
NASCLA-F042
In a controlled decking zone (CDZ) during steel erection, what is the most unsecured metal decking allowed?
Show answer
Answer: B. 3,000 square feet
Unsecured decking in a CDZ may not exceed 3,000 square feet. The zone itself may be no more than 90 feet wide and 90 feet deep from any leading edge. 8,100 sq ft multiplies those two dimensions, which isn't the decking limit. Marking the boundaries is required, but it doesn't remove the limit.
Look it up: 29 CFR 1926.760(c)(3) and (c)(5).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.760 (eCFR)
Content area: Metals · Controlled decking zone
Question 43
NASCLA-F043
A rectangular tank is 6 feet long and 4 feet wide, and holds water 5 feet deep. Using 1 cubic foot ≈ 7.48 U.S. gallons, about how many gallons does it hold?
Show answer
Answer: C. 898 gallons
Volume = 6 × 4 × 5 = 120 cubic feet. 120 × 7.48 = 897.6, about 898 gallons. 120 stops at cubic feet. 449 uses half the depth. 1,197 uses a depth of 6.67 feet instead of 5. NIST's factors give 7.4805 gallons per cubic foot, which rounds to 7.48.
Look it up: NIST SP 811, Appendix B.9 (volume): cubic foot and U.S. gallon factors.
Reference status: Calculation using a standard conversion (NIST).
Source: NIST SP 811, Appendix B.9
Content area: Mechanical and Plumbing Systems · Tank capacity
Question 44
NASCLA-F044
A roofing crew on a low-slope roof uses a warning line system, and no mechanical equipment is in use. How far back from the roof edge must the warning line be?
Show answer
Answer: B. At least 6 feet
Without mechanical equipment, the warning line must be at least 6 feet from the roof edge. With mechanical equipment, it stays 6 feet from edges parallel to the equipment's travel and moves to 10 feet from edges perpendicular to it. The line itself must sit between 34 and 39 inches high.
Look it up: 29 CFR 1926.502(f)(1)(i), (f)(1)(ii), and (f)(2)(ii).
Reference status: On PSI's reference list: yes, 29 CFR Part 1926.
Source: 29 CFR 1926.502 (eCFR)
Content area: Thermal and Moisture Protection · Roofing warning lines
Question 45
NASCLA-F045
Under the Miller Act, unless the contracting officer finds in writing that it's impractical, what must the payment bond amount equal?
Show answer
Answer: B. The total amount payable under the contract
The payment bond must equal the total amount payable by the terms of the contract. The contracting officer may set a different amount only after a written determination, supported by specific findings, that this is impractical, and even then it can't be less than the performance bond. $100,000 is the contract-size threshold in the statute's text, not the bond amount.
Look it up: 40 U.S.C. 3131(b) and (b)(2).
Reference status: Not on PSI's reference list: federal statute (40 U.S.C. 3131).
Source: 40 U.S.C. 3131 (Cornell LII)
Content area: Procurement and Contracting Requirements · Payment bond amount
Question 46
NASCLA-F046
A small job has five activities. A (4 days) starts the job. B (6 days) follows A. C (3 days) follows A. D (5 days) follows C. E (2 days) follows both B and D. Which activity has float, and how much?
Show answer
Answer: A. B, with 2 days of float
Path A-B-E takes 4 + 6 + 2 = 12 days. Path A-C-D-E takes 4 + 3 + 5 + 2 = 14 days. The longest path, A-C-D-E, is the critical path and sets the project at 14 days, so C and D have zero float. B can slip 14 − 12 = 2 days without delaying E.
Look it up: Calculation (critical path method: forward and backward pass).
Reference status: Calculation: every number you need is in the question.
Content area: General Requirements · Critical path
Question 47
NASCLA-F047
How long must an employer keep the OSHA 300 Log, the annual summary, and the 301 incident reports?
Show answer
Answer: D. 5 years after the end of the calendar year they cover
These records must be kept for five years following the end of the calendar year they cover. During that time the 300 Log must be updated for newly discovered cases or changes in classification. The other periods don't match the rule.
Look it up: 29 CFR 1904.33(a) and (b)(1).
Reference status: Not on PSI's reference list: federal rule (29 CFR Part 1904).
Source: 29 CFR Part 1904, Subpart D (eCFR)
Content area: Procurement and Contracting Requirements · Injury and illness record retention
Question 48
NASCLA-F048
A floor plan is drawn at ¼ inch = 1 foot-0 inches. A wall measures 3½ inches on the drawing. How long is the wall?
Show answer
Answer: C. 14 feet
At ¼ inch per foot, each inch on the drawing is 4 feet. 3.5 × 4 = 14 feet. 28 feet would be the answer at ⅛-inch scale. 7 feet would be ½-inch scale. 3.5 feet reads drawing inches as feet. PSI's current bulletin says a physical diagram/blueprint packet is handed out onsite; this item practices basic plan-scale reading.
Look it up: Calculation. Real length = drawing length ÷ scale (inches per foot).
Reference status: Calculation: every number you need is in the question.
Content area: General Requirements · Reading scale
Question 49
NASCLA-F049
Your cost for a job is $80,000. You want a 20% gross margin, meaning profit is 20% of the selling price. What price do you bid?
Show answer
Answer: D. $100,000
Margin is figured on price, not cost: price = cost ÷ (1 − margin) = $80,000 ÷ 0.80 = $100,000. Check: $20,000 profit ÷ $100,000 = 20%. $96,000 is a 20% markup on cost, which yields only about a 16.7% margin ($16,000 ÷ $96,000). $84,000 and $88,000 don't follow either method.
Look it up: Calculation. The SEC guide defines gross profit (gross margin) as net revenues minus cost of sales.
Reference status: Calculation: every number you need is in the question.
Source: SEC, Beginners' Guide to Financial Statements
Content area: Procurement and Contracting Requirements · Pricing for a gross margin
Question 50
NASCLA-F050
A building pad requires excavating an area 60 feet by 40 feet to a depth of 3 feet. How many bank cubic yards is that, before any swell factor?
Show answer
Answer: B. 267 cubic yards
Volume = 60 × 40 × 3 = 7,200 cubic feet. 7,200 ÷ 27 = 266.7, about 267 cubic yards. 7,200 stops at cubic feet. 800 divides by 9 (the square feet in a square yard) instead of 27. 80 divides by 90. Loose (hauled) yards would be higher once a swell factor is applied.
Look it up: Calculation. Cubic yards = cubic feet ÷ 27 (a yard is 3 feet).
Reference status: Calculation: every number you need is in the question.
Source: NIST SP 811, Appendix B.8
Content area: Site Construction · Excavation quantity
Answer key
| Question | Answer | Content area |
|---|---|---|
| 1 | A | General Requirements |
| 2 | B | Procurement and Contracting Requirements |
| 3 | D | Site Construction |
| 4 | C | Metals |
| 5 | B | Concrete |
| 6 | C | General Requirements |
| 7 | B | Procurement and Contracting Requirements |
| 8 | C | Site Construction |
| 9 | B | Masonry |
| 10 | D | General Requirements |
| 11 | C | Wood |
| 12 | A | Procurement and Contracting Requirements |
| 13 | A | Electrical Systems |
| 14 | C | Thermal and Moisture Protection |
| 15 | A | General Requirements |
| 16 | B | Mechanical and Plumbing Systems |
| 17 | D | Procurement and Contracting Requirements |
| 18 | B | Site Construction |
| 19 | D | Concrete |
| 20 | A | Doors, Windows, and Glazing |
| 21 | A | General Requirements |
| 22 | A | Procurement and Contracting Requirements |
| 23 | D | Metals |
| 24 | D | Site Construction |
| 25 | C | Finishes |
| 26 | A | General Requirements |
| 27 | D | Procurement and Contracting Requirements |
| 28 | D | Concrete |
| 29 | C | Mechanical and Plumbing Systems |
| 30 | B | General Requirements |
| 31 | C | Site Construction |
| 32 | C | Procurement and Contracting Requirements |
| 33 | D | Wood |
| 34 | C | General Requirements |
| 35 | B | Procurement and Contracting Requirements |
| 36 | A | Masonry |
| 37 | B | Doors, Windows, and Glazing |
| 38 | B | Procurement and Contracting Requirements |
| 39 | D | General Requirements |
| 40 | D | Finishes |
| 41 | A | Procurement and Contracting Requirements |
| 42 | B | Metals |
| 43 | C | Mechanical and Plumbing Systems |
| 44 | B | Thermal and Moisture Protection |
| 45 | B | Procurement and Contracting Requirements |
| 46 | A | General Requirements |
| 47 | D | Procurement and Contracting Requirements |
| 48 | C | General Requirements |
| 49 | D | Procurement and Contracting Requirements |
| 50 | B | Site Construction |
Score your attempt
As you check each answer, mark it one of three ways:
- Knew it: you got it right without opening a book.
- Looked it up: you got it right by finding it in a reference.
- Guessed: you weren't sure, whether you got it right or not.
"Knew it" and "Looked it up" both count, because the real exam is open book. A pile of "Guessed" marks in one content area tells you where to study, even if some of those guesses were right.
Then count your correct answers by content area:
| Content area | Questions in this set | Question numbers | Your correct |
|---|---|---|---|
| General Requirements | 11 | 1, 6, 10, 15, 21, 26, 30, 34, 39, 46, 48 | ___ of 11 |
| Site Construction | 6 | 3, 8, 18, 24, 31, 50 | ___ of 6 |
| Concrete | 3 | 5, 19, 28 | ___ of 3 |
| Masonry | 2 | 9, 36 | ___ of 2 |
| Metals | 3 | 4, 23, 42 | ___ of 3 |
| Wood | 2 | 11, 33 | ___ of 2 |
| Thermal and Moisture Protection | 2 | 14, 44 | ___ of 2 |
| Doors, Windows, and Glazing | 2 | 20, 37 | ___ of 2 |
| Finishes | 2 | 25, 40 | ___ of 2 |
| Mechanical and Plumbing Systems | 3 | 16, 29, 43 | ___ of 3 |
| Electrical Systems | 1 | 13 | ___ of 1 |
| Procurement and Contracting Requirements | 13 | 2, 7, 12, 17, 22, 27, 32, 35, 38, 41, 45, 47, 49 | ___ of 13 |
| Total | 50 | ___ of 50 |
Your percent correct is feedback on these 50 original questions. It isn't a PSI score, and it doesn't predict whether you'll pass. On the real exam you need 81 correct out of 115 scored questions, which is about 70.4%. Some areas here have only one to three questions, so a single miss swings that area a lot. Treat area results as a hint about where to look, not a precise measure.
NASCLA commercial exam at a glance
| Item | Detail |
|---|---|
| Exam | NASCLA Accredited Examination for Commercial General Building Contractors |
| Owner and test vendor | NASCLA owns the exam; PSI Services LLC delivers it |
| Scored questions | 115 |
| Needed to pass | 81 correct (about 70.4%) |
| Time | 330 minutes (5½ hours) |
| Unscored questions | 10 additional pretest questions; their time is already included in the 330 minutes |
| Format | Computer-based at a PSI test center, one question per screen; you can change answers until time runs out |
| Open book | Yes, but you bring your own references |
| Fees | $65 NASCLA application; $130 PSI exam fee; $45 per transcript sent to a state agency |
| Eligibility window | 1 year from approval, up to 3 attempts |
Sources: PSI Candidate Information Bulletin 1458 (updated July 7, 2026); NASCLA: Apply for NASCLA Exams; NASCLA Accredited Examinations FAQ.
Where the 115 scored questions come from
PSI's bulletin splits the exam into 12 content areas. We gave each area a share of our 50 questions in proportion to its share of the 115, rounding so the total stays at 50.
| Content area | Scored questions on the exam | Questions in this set |
|---|---|---|
| General Requirements | 25 | 11 |
| Site Construction | 15 | 6 |
| Concrete | 6 | 3 |
| Masonry | 4 | 2 |
| Metals | 6 | 3 |
| Wood | 5 | 2 |
| Thermal and Moisture Protection | 5 | 2 |
| Doors, Windows, and Glazing | 4 | 2 |
| Finishes | 5 | 2 |
| Mechanical and Plumbing Systems | 6 | 3 |
| Electrical Systems | 3 | 1 |
| Procurement and Contracting Requirements | 31 | 13 |
| Total | 115 | 50 |
Three areas make up 71 of the 115 questions: Procurement and Contracting Requirements (31), General Requirements (25), and Site Construction (15). The first two alone are 56 questions, almost half the exam. That's why a big share of this set is business math, labor and contract rules, and jobsite safety. Source: PSI Candidate Information Bulletin 1458 (updated July 7, 2026).
Is the NASCLA exam open book?
Yes. You may use the approved references during the exam, but PSI doesn't provide them. You bring your own copies. The bulletin lists the permitted references, including codes, OSHA's construction rules, construction-management texts, and the NASCLA contractor business guide.
The rules for your books:
- You may highlight, underline, and use the book's index.
- Tabs must be permanent. Post-it notes and other removable tabs have to come off.
- You can't write notes in the books, and no loose or attached papers are allowed.
Code editions are fixed. The building code must be the 2021 or 2024 International Building Code. The concrete code must be ACI 318-14 or ACI 318-19. The accessibility standard must be ICC A117.1-2017. For the other, non-code references, you may bring a different edition than the one listed, but at your own risk, since the questions are written from the listed editions.
You may bring a calculator if it is silent, battery-powered, and non-programmable, with no paper tape and no alphabet keyboard. At the test center you'll also get a printed packet of diagrams and plans for the questions that use drawings.
Source: PSI Candidate Information Bulletin 1458 (updated July 7, 2026). Check the current bulletin for the full reference list before you buy books.
How much time you get per question
You have 330 minutes for 115 scored questions plus 10 additional unscored pretest questions. Because PSI says the pretest-question time is already included in the 330 minutes, the overall on-screen pace works out to about 2.64 minutes per question. Counting only the 115 scored questions gives about 2.87 minutes each.
For a simple scaled timing drill, give yourself about 132 minutes for these 50 questions (50 × 2.64). That is a practice pacing calculation, not an official 50-question time limit.
How to use this practice test
- Take it cold first. Answer all 50 without books to see what you already know. Mark each one "Knew it" or "Guessed."
- Take it again open book. Use the Look it up line to find each answer in the regulation, code, or formula. Time how long each lookup takes. Speed of finding things is a big part of this exam.
- Study the misses by area. Use the score table above. If one area keeps showing up, spend your next study block there.
- Practice under time. Once your lookups are faster, try a 132-minute run as a scaled pacing drill.
- Tab your books as you go. Every time you hunt for a section, add a permanent tab so you find it faster next time.
Does passing the NASCLA exam give you a contractor license?
No. NASCLA isn't a license. It's an exam that participating states accept in place of their own trade exam for the matching commercial classification. You still apply for a license with each state and meet its other requirements. Many states also require their own business and law exam.
NASCLA lists these 20 participating agencies across 17 states and the U.S. Virgin Islands:
- Alabama Home Builders Licensure Board
- Alabama Licensing Board for General Contractors
- Arizona Registrar of Contractors
- Arkansas Contractors Licensing Board
- California Contractors State License Board
- Florida Construction Industry Licensing Board
- Georgia State Licensing Board for Residential and General Contractors
- Louisiana State Licensing Board for Contractors
- Mississippi State Board of Contractors
- Nevada State Contractors Board
- New Mexico Construction Industries Division
- North Carolina Licensing Board for General Contractors
- Oregon Construction Contractors Board
- South Carolina Contractors' Licensing Board
- South Carolina Residential Builders Commission
- Tennessee Board for Licensing Contractors
- Utah Division of Occupational and Professional Licensing
- U.S. Virgin Islands Department of Licensing and Consumer Affairs
- Virginia Board for Contractors
- West Virginia Contractor Licensing Board
Each agency decides which of its license classifications the NASCLA exam covers, so check with the agency where you plan to work before you apply. Sources: NASCLA Commercial Exam Participating State Agencies; NASCLA: State Business and Law Exams.
Applying, fees, and attempts
- Apply to NASCLA. The application costs $65 and is filed through NASCLA's online system. NASCLA says applications are typically processed within 7 business days. There are no eligibility requirements to apply, and you don't have to live in a participating state.
- Schedule with PSI. Once you're approved, you have 1 year to test and up to 3 attempts. If you don't pass within that year, you can reapply after it ends.
- Pay the exam fee. PSI's fee is $130 and is good for 1 year from payment. To cancel or reschedule, PSI must receive your notice at least 2 days before your exam.
- Send your results. After you pass, you order a transcript for each state agency, at $45 each. Transcripts stay available to view for 2 years. A passing score report doesn't show a numerical score.
Sources: NASCLA: Apply for NASCLA Exams; NASCLA Accredited Examinations FAQ; PSI Candidate Information Bulletin 1458 (updated July 7, 2026); PSI: NASCLA scheduling.
What this test doesn't cover
- Questions whose answers could not be independently checked in an accessible authoritative source. We kept this set to rules, conversions, calculations, and construction concepts we could verify. The real exam also draws on listed books and codes that are not all freely readable online, so this set does not reproduce every subtopic inside PSI's 12 broad content areas.
- Building code values. We left out questions that depend on specific numbers in the International Building Code because we couldn't verify the code text from a free public source.
- The plan packet. Question 48 covers reading scale, but the exam's diagram and plan questions go further than any web page can.
- NASCLA's electrical exams. These are separate exams with their own outlines.
- State business and law exams. Those are separate, state-specific tests.
Sources
Exam and application
- PSI Candidate Information Bulletin 1458 (updated July 7, 2026)
- NASCLA: Apply for NASCLA Exams
- NASCLA Accredited Examinations FAQ
- NASCLA Commercial Exam Participating State Agencies
- NASCLA Commercial Exam
- NASCLA: State Business and Law Exams
- PSI: NASCLA scheduling
Federal rules and laws used in the questions
- 29 CFR 1926.451 (eCFR)
- 29 CFR 1926.501 (eCFR)
- 29 CFR 1926.502 (eCFR)
- 29 CFR 1926.404 (eCFR)
- 29 CFR 1926.651 (eCFR)
- 29 CFR 1926.652 (eCFR)
- 29 CFR 1926 Subpart P, Appendix B (eCFR)
- 29 CFR 1926.701 (eCFR)
- 29 CFR 1926.706 (eCFR)
- 29 CFR 1926.760 (eCFR)
- 29 CFR 1926.1053 (eCFR)
- 29 CFR Part 1904, Subpart D (eCFR)
- 29 CFR 778.101 (eCFR)
- 29 CFR 778.107 (eCFR)
- 8 CFR 274a.2 (eCFR)
- 40 CFR 122.26 (eCFR)
- 40 U.S.C. 3131 (Cornell LII)
- FAR 11.501 (Acquisition.gov)
Conversions and financial terms
Last verified
We last checked these facts on October 4, 2026: exam details, pass line, time, and content outline in PSI's bulletin (updated July 7, 2026); NASCLA's fees, application rules, and participating agency list; and the federal-rule, NIST, SEC, FAR, and U.S. Code sources used in the questions. Fees, agency lists, and code editions change, so confirm them with NASCLA, PSI, or your state before you apply.
About this page
By the Castleport Test Prep Editorial Team.
We wrote these questions and checked each answer against the regulation, bulletin, or calculation cited with it. They have not been reviewed by a licensed contractor.
Castleport Test Prep is an independent exam prep publisher. We are not affiliated with, endorsed by, or approved by NASCLA, PSI Services LLC, the International Code Council, or any state licensing agency. Exam and credential names are used only to identify their subjects, and trademarks belong to their owners. These are original practice questions, not real exam questions. Practice results don't predict your exam score or licensing outcome.