Georgia licenses electrical contractors, not individual electricians. A Class I (restricted) license covers smaller residential work and a Class II (unrestricted) license covers everything else. Georgia rewrote these rules in a law that took effect July 1, 2026, so check the date on any guide you read.
| Row label | Class I (Restricted) | Class II (Unrestricted) |
|---|---|---|
| Work you can contract | Single-family homes up to 3 levels and multifamily buildings up to 2 levels, on single-phase service up to 400 amps | Any electrical contracting, including commercial, industrial, and three-phase work |
| Standard experience | 3 years full-time (2,000 hours = 1 year) | 4 years full-time, at least 2 of them on three-phase systems |
| Other ways to qualify | 2-year electrical contracting diploma or certificate + 2 years' experience, or a completed U.S. Department of Labor (DOL) accredited or approved electrical apprenticeship | 2-year program + 4 years' experience, or a completed DOL apprenticeship + 1 year of three-phase experience |
| Proof of experience | Sworn affidavit from each supervising licensed contractor (or a licensed architect, professional engineer, or electrical engineer) | Same |
| Exam | PSI, 140 scored questions (+15 unscored), 8 hours, listed references permitted, passing scaled score 70 | PSI, 140 scored questions (+22 unscored), 8 hours, listed references permitted, passing scaled score 70 |
| Apply | Online in GOALS, $110 application fee, PSI exam fee paid separately | Same |
| Keep it active | Renew every 2 years by June 30 of even years; 8 CE hours per cycle | Same |
Heads-up: The Board's written rules and some of its web pages still show pre-July 2026 standards (200 amps, 4 years, three references). This page reports the enacted 2026 statute for the current qualification rules and separately shows the Board's still-published application instructions. Follow the live GOALS checklist and confirm any conflict with the Division before you file. See what changed below.
Last verified October 1, 2026, against Georgia's licensing statute, the Board's rules, FAQ, and how-to guide, and PSI's candidate handbook.
What changed on July 1, 2026
Georgia's legislature repealed and rewrote the licensing law for electrical, plumbing, HVAC, low-voltage, and utility contractors (SB 553, signed bill; now O.C.G.A. Title 43, Chapter 14). The official 2026 statutory summary lists July 1, 2026 as Act 472's effective date. As of October 1, 2026, the Board's administrative rules and application pages still contained older requirements, so the current statute and current filing instructions do not line up in every detail.
| Topic | State law since July 1, 2026 | Board rules and pages (as of Oct 1, 2026) | What to do |
|---|---|---|---|
| Class I scope | Residential only: single-family up to 3 levels, multifamily up to 2 levels; single-phase up to 400 A (§ 43-14-2(10)) | Single-phase up to 200 A, no building-type limit (Rule 121-3-.01(1)) | Planning small commercial work on a Class I? Ask the Division first. |
| Class I experience | 3 years full-time, or a 2-year program + 2 years, or a completed DOL apprenticeship (§ 43-14-8(e)) | 4 years of primary experience, with up to 1 year credited from secondary work or education (Rule 121-3-.01(4)–(5)) | Document your experience to the law's standard; ask which standard your file will be reviewed under. |
| Class II experience | 4 years including at least 2 on three-phase, or a program + 4 years, or a DOL apprenticeship + 1 year three-phase (§ 43-14-8(f)) | 4 years, including work above single-phase 200 A (Rule 121-3-.01(6)) | Keep three-phase hours on their own log. |
| Experience proof | Sworn affidavit from each qualifying supervisor, with statutory professional alternatives | Three references, at least one from a licensed electrical contractor, are still listed by the how-to guide and FAQ | Follow the live GOALS upload fields and Board instructions; the published checklist has not yet been reconciled with the affidavit language in the 2026 statute. |
| Minimum age | The reenacted § 43-14-8 reviewed for this page does not state a minimum age | 21 is still printed in Rule 121-3-.01(2) | Confirm the live Board/GOALS requirement before filing; the public sources are not yet reconciled. |
| Background check | Applying authorizes a criminal background check; fingerprints may be required; you pay the cost (§ 43-14-8(g)) | The current how-to guide and FAQ still ask for a local-law-enforcement background check | Follow the live application instructions; the statute also authorizes fingerprint-based checks. |
| Late renewal | Up to 31 days after expiration (§ 43-14-20(c)) | July 1–31 of even years | Same result. |
| Extra CE hours | Can't be carried forward (§ 43-14-20(k)) | — | Finish 8 hours inside each cycle. |
| Reciprocity | The Division may grant it when statutory conditions are met (§ 43-14-23) | The current Board FAQ says reciprocity is not offered, effective May 2026 | Unless the Board confirms a reciprocal route for your application, use Georgia's examination path. |
The practical problem is the transition, not a lack of sources: the enacted statute and still-published Board material say different things on several application details. Use the current statute to understand the qualification paths, use the live GOALS checklist for the files the portal actually requests, and ask the Division to resolve any conflict that affects your application. You can reach it through the Board's contact form.
Class I or Class II: which license do you need?
Choose Class II if you'll contract for anything commercial or industrial, any three-phase work, residential service above 400 amps, or buildings taller than Class I allows. Class I fits contractors who stay in single-family homes up to three levels and multifamily buildings up to two levels, on single-phase service up to 400 amps at the service drop or lateral (§ 43-14-2(10)–(11)).
That's a real change. The old rule let a Class I contractor take any single-phase job up to 200 amps, including a small shop or office. The new definition is residential only, but with twice the amperage. If you already hold a Class I and do light commercial work, ask the Division how your license is being treated now.
Two related points:
- Low-voltage work is a different license. Alarm, telecom, and other low-voltage systems are licensed by the Division of Low Voltage Contractors, and the law excludes low-voltage contracting from "electrical contracting" (§ 43-14-2(8)).
- There's no state journeyman or master license. The Board's FAQ says it licenses electrical contractors, not electricians. Electricians work under a licensed contractor.
Experience requirements
What counts as a year
Georgia defines one year of full-time experience as at least 2,000 hours of documented qualifying work in a calendar year (§ 43-14-2(13)). For your own records, keep enough detail to identify when you worked, the projects involved, and who supervised you. The law doesn't spell out how the Division credits a year with fewer hours, so if your history is part-time or seasonal, ask before you apply.
Three ways to qualify
| Path | Class I | Class II |
|---|---|---|
| Field experience | 3 years full-time in direct installation | 4 years full-time, at least 2 on three-phase systems |
| 2-year program (diploma or certificate in electrical contracting from an accredited technical college, university, or other institution the Division recognizes) | Program + 2 years full-time | Program + 4 years full-time, at least 2 on three-phase |
| Apprenticeship (completed program accredited or approved by the U.S. Department of Labor) | Listed as a qualifying route | Apprenticeship + 1 year full-time on three-phase systems |
Sources: § 43-14-8(e)(2) and (f)(2); signed SB 553.
Two things surprise people here. First, the 2-year program doesn't shorten the Class II path at all. It's still four years of experience. Second, the Class I program and apprenticeship routes sit in a single sentence of the statute. As written, a completed DOL apprenticeship is its own route to the Class I exam, but confirm with the Division how it's reading that sentence before you rely on it.
Experience areas you need to show
The law lists the kinds of work your experience has to cover:
- Raceways: pull boxes, junction boxes, conduit bodies, and connections to cabinets, panelboards, and switchboards
- Conductors: cords, cables, splices, taps, terminations, bonding jumpers, overcurrent devices, and metering devices, sized for ampacity and voltage
- Services: service entrances, meters, cabinets, switchboards, service risers, disconnects, grounding electrodes, main bonding jumpers, and ground-fault protection
- Motors and generators: feeders, branch circuits, overcurrent protection, disconnects, and controllers
- Switches and controls: for lighting, appliances, HVAC equipment, and other utilization equipment
- Special occupancies
- Grounding and bonding: metal piping, equipment grounding conductors, exposed metal parts, and protection of grounding conductors
- Calculations: general lighting loads, minimum branch circuits, conductor ampacity, raceway fill, and net loads using the Code's demand and derating factors
- Class I: projects in at least 5 of areas 1–7, plus competency in area 8 (§ 43-14-8(e)(2)(A)).
- Class II: all 8 areas, plus work on installations larger than single-phase 200 amps (§ 43-14-8(f)(2)(A)).
Who signs for your experience
Each supervising licensed contractor signs a sworn affidavit covering the time they supervised you. A licensed architect, professional engineer, or electrical engineer can sign instead. Worked under three contractors? You'll need three affidavits (§ 43-14-8(e)(3), (f)(3)).
The 2026 statute makes the supervising licensed contractor's affidavit the normal proof route and also names licensed architects, professional engineers, and electrical engineers as alternatives in the situations it describes. If your supervision history does not fit those categories, ask the Division how it wants that experience documented before you file.
What to submit
The law requires the experience affidavit(s), at least one secure and verifiable ID document, an affidavit of lawful presence (plus immigration documents if you're not a U.S. citizen), and consent to a criminal background check (§ 43-14-8). The Board's GOALS checklist, as published on October 1, 2026, still asks for items from the older process too. Don't skip a field the portal requires.
Application checklist
Checklist sources: Board how-to guide; Board FAQ; § 43-14-8.
How to apply
- Pick your class and path using the tables above.
- Open an account in GOALS and choose Electrical Contractor – Restricted (Class I) or Non-Restricted (Class II).
- Upload your documents and pay the $110 fee.
- Wait for review. The Board says applications are generally processed within 20 business days. A deficiency letter restarts that count, and an application can be withdrawn if deficiencies aren't fixed within 60 days. Complete files go to a Board meeting and must be complete at least 15 days before it to make that agenda (how-to guide).
- Get your Exam Approval Letter. It's valid for one year. PSI then sends registration and payment instructions (Board FAQ).
- Schedule and pass the exam with a scaled score of 70 or higher.
- Wait for the license. PSI's official score can take up to 6 weeks to reach the Board, and Board staff contact you about your results (PSI handbook, p. 9).
- Don't contract until the license is active. You can check status in GOALS.
Veterans who served during a period of conflict may qualify for 5 or 10 points added to their exam score. Military spouses and transitioning service members can get expedited processing (PSI handbook, p. 1; Rule 121-2-.12).
The Georgia electrical contractor exam
Both classes take a multiple-choice, computer-based exam at PSI test centers. It runs in two parts of four hours each, with a break between. Each class has 140 scored questions, plus unscored pretest questions mixed in: 15 on Class I and 22 on Class II. You won't know which questions are pretest, so answer everything. There's no penalty for guessing.
| Content area | Class I | Class II |
|---|---|---|
| Regulations, laws, and administrative functions | 30 | 30 |
| Comply with laws (workers' comp, unemployment insurance, IRS Circular E, the Georgia licensing board, sales and use tax, business licenses) | 10 | 10 |
| Comply with regulations (OSHA 1926, NEC, NFPA, UL listing, permits and inspections) | 9 | 9 |
| Administrative requirements (bonding, insurance, cash flow, bookkeeping, incident reports, estimating, contracts) | 6 | 6 |
| Plan and organize work | 5 | 5 |
| Technical functions | 110 | 110 |
| Basic electrical circuits | 21 | 14 |
| Electrical controls and devices | 22 | 15 |
| DC and AC rotating equipment (motors and generators) | 9 | 16 |
| Transformers | 7 | 21 |
| Interior electrical systems | 30 | 23 |
| Special equipment, conditions, and locations | 21 | 21 |
| Scored questions | 140 | 140 |
| Unscored pretest questions | 15 | 22 |
| Total on screen | 155 | 162 |
The biggest difference between the classes: the Class II exam moves 21 questions off basic circuits, controls, and interior wiring (7 each) and onto motors and transformers. Those two areas carry 37 questions on Class II versus 16 on Class I. If you're sitting for Class II, three-phase transformer connections and motor work deserve real study time.
Books you can bring (exams through December 31, 2026)
Only these references are allowed in the room:
- American Electricians' Handbook, 17th edition (2021)
- Contractors Guide to Business, Law, and Project Management – Georgia Construction Industry Licensing Board, 5th edition (NASCLA)
- IRS Employer's Tax Guide (Circular E), 2025 or 2026
- Code of Federal Regulations, Title 29, Part 1926 (OSHA), latest edition
- Georgia State Electrical 2023 National Electrical Code or the NEC Handbook
- Printreading Based on the 2020 NEC
- Ugly's Electrical References, 2023
You can highlight, underline, and add permanent tabs. You can't add notes or loose pages, and anything extra gets confiscated. This list applies to exams through December 31, 2026; PSI says to get an updated list for later dates (PSI handbook, p. 11).
Scoring, retakes, and exam day
- Scoring: Scores are scaled, not a raw percentage. You need a final scaled score of 70 to pass. If you don't pass, your score report shows subscores by content area (PSI handbook, p. 9).
- Retakes: After two failed attempts, you must finish a Board-approved review course before a third try. If you fail again after that, no more courses are required (Rule 121-2-.06; Board FAQ).
- Arrival and ID: Arrive 20 minutes early. More than 15 minutes late means you're turned away and lose the fee. Bring two IDs: one current government photo ID with your signature, and one more with your name and signature.
- Calculator: A silent, non-programmable calculator without alpha keys or printing is allowed.
- Rescheduling: You can reschedule once for free if you do it at least 2 business days ahead. A no-show forfeits the fee.
Exam-day sources: PSI handbook, pp. 2–4.
For the calculation-heavy technical sections, the free Castleport practice sets on load calculations, motor calculations, and conduit fill are useful next steps.
Running an electrical contracting business
Georgia doesn't issue a separate company license, and the Board says it doesn't register electrical contracting companies (Board FAQ). The license belongs to a person, and the company works under that person. The rules that come with that:
- A licensee must be connected to the business full time. A partnership, LLC, or corporation can't do electrical contracting unless a licensed person is regularly connected to it and working in the business full time (§ 43-14-8(d)).
- One company at a time. A licensee can qualify only one business at once. They also can't supervise that company's work during hours they're working for another employer (Rule 121-6-.01).
- 7 days to report a departure. If the qualifying licensee leaves, the company must notify the Division within 7 days. If the licensee dies, partners and employees can keep working under that license for 90 days, and the Division may grant one more 90-day period (§ 43-14-8(d)).
- No lending a license. The 2026 law expressly makes knowingly letting an unlicensed person or entity use your license — including lending, leasing, renting, or assigning it — grounds for discipline (§ 43-14-6(a)(4)(D)).
- No advertising without a license. An unlicensed person can't advertise electrical contracting unless a licensed electrical contractor does the work (§ 43-14-8(b)(2)).
The current electrical-contractor statute, Rule 121-3, and SOS initial-application checklist reviewed for this page do not list a statewide insurance or surety-bond document as an initial electrical-contractor application requirement. Local permitting and code-enforcement requirements can still apply, so check the jurisdiction where the work will be performed.
Local licenses, permits, and who's exempt
One state license works statewide. A Georgia license lets you contract anywhere in the state within your class. Cities and counties can't add their own contractor-licensing requirement, except as the law allows for local code enforcement, bonds, and fees or taxes (§ 43-14-19(b); § 43-14-16). Local permits and inspections still apply, so check with the permitting office where the job is.
You don't need your own contractor license if you are (§ 43-14-19):
- an electrician working for a licensed electrical contractor;
- an individual working on a home you own or live in (the work still has to meet applicable code, ordinance, permit, and inspection requirements);
- a regular full-time employee of a business or institution working on your employer's own premises;
- a utility worker working on the utility's own system up to and including the meter;
- maintenance staff at a state, county, or city facility doing the facility's maintenance work; or
- working on a farm or ranch building, or farm irrigation wiring, located more than 30 feet from any dwelling or animal-husbandry building.
Licensed in another state?
The Board's FAQ says Georgia does not currently offer licensure by reciprocity, effective May 2026 (Board FAQ). The Board's how-to guide still contains an older reciprocity section naming five states, so don't rely on that older list without confirmation.
The 2026 law does authorize the Division to grant a license without an exam when the statutory reciprocity conditions are met, including substantially equal requirements, at least two years of immediately preceding practice, and reciprocal treatment for Georgia licensees (§ 43-14-23). Unless the Board confirms that route for your application, plan on Georgia's examination path.
Keeping your license
Renewal. Licenses last two years and expire June 30 of even-numbered years, so the next deadline is June 30, 2028. You renew online in GOALS. Late renewal runs July 1–31 with a late fee. After that, the license lapses, and you can't contract until it's renewed or reinstated (how-to guide; § 43-14-20).
Continuing education.
- Hours: 4 CE hours per year, which is 8 per renewal cycle.
- First renewal: if you were licensed for one year or less before your first renewal, you don't need any CE. If you were licensed more than one year but less than two, you need 4 hours (Rule 121-4-.05).
- Carry-forward: hours don't carry forward to the next cycle.
- Records and audits: keep certificates for 5 years, because the Board audits at random.
- Reporting: for the 2026 renewal cycle, the Board directed licensees to report CE through CE Broker (Board FAQ).
Reinstatement. If your license lapsed less than three years ago, you file a reinstatement application, pay the reinstatement fee, and show your CE. The how-to guide lists $310 for Class II. After three years, expect to retake the exam and document your experience again (§ 43-14-20(e)–(f); Rule 121-4-.02). Current renewal and late fees are on the GOALS fee schedule.
Practice: 8 questions on Georgia licensing law
The exam's Comply with laws section has 10 questions, and the Georgia licensing board is one of its listed topics. These are original, unofficial practice questions written from the statute and rules, not PSI items. Your score reflects these eight questions only, not how you'll do on the real exam.
GA-LAW-01. Under the definition that took effect July 1, 2026, a Class I electrical contractor may work on single-phase installations up to what size at the service drop or service lateral?
- A. 100 amperes
- B. 200 amperes
- C. 400 amperes
- D. 600 amperes
Reveal answer
C. 400 amperes. § 43-14-2(10) sets the Class I limit at 400 amps single-phase and limits Class I to single-family homes up to three levels and multifamily buildings up to two. 200 amps is the older limit still printed in Rule 121-3-.01(1). Neither 100 nor 600 amps appears in either source.
GA-LAW-02. Under Georgia's 2026 law, one year of "full-time experience" means documented qualifying work of at least:
- A. 1,500 hours in a calendar year
- B. 2,000 hours in a calendar year
- C. 2,080 hours in a calendar year
- D. 4,000 hours in a calendar year
Reveal answer
B. 2,000 hours. § 43-14-2(13) defines full-time experience as at least 2,000 hours of documented qualifying work in a calendar year. 2,080 hours is a common 40-hour payroll year, but it isn't the statutory threshold for one year.
GA-LAW-03. An LLC's only qualifying electrical contractor resigns. How soon must the LLC notify the Division of Electrical Contractors?
- A. Within 5 days
- B. Within 7 days
- C. Within 30 days
- D. Within 90 days
Reveal answer
B. Within 7 days. § 43-14-8(d) requires notice within seven days after the qualifying licensee leaves. The 90-day period in that subsection applies after a qualifying licensee's death, so D describes a different event.
GA-LAW-04. Which situation does O.C.G.A. § 43-14-19(d)(1) expressly allow without the individual holding an electrical contractor license?
- A. A paid handyman wiring a customer's kitchen
- B. A homeowner installing wiring in a residential dwelling they own or occupy, subject to applicable code, ordinance, and inspection requirements
- C. A general contractor's employee wiring a client's new house
- D. An out-of-state electrical contractor beginning Georgia work before receiving Georgia authorization
Reveal answer
B. § 43-14-19(d)(1) expressly says the chapter does not prohibit an individual from installing, altering, or repairing electrical wiring in a residential dwelling owned or occupied by that individual, subject to the chapter, Board rules, and applicable local resolutions, ordinances, codes, and inspection requirements. The cited subsection does not create that homeowner exemption for A, C, or D.
GA-LAW-05. A license expired on June 30 without being renewed. Under the 2026 law, how long is the late-renewal window?
- A. 14 days
- B. 31 days
- C. 60 days
- D. 6 months
Reveal answer
B. 31 days. § 43-14-20(c) allows late renewal for up to 31 days after expiration, and the Board's guide lists July 1–31. After that the license lapses and needs reinstatement (§ 43-14-20(d)).
GA-LAW-06. An electrical contractor completed 12 CE hours during the last renewal cycle. How many can be carried into the next cycle?
- A. None
- B. 4
- C. 8
- D. All 12
Reveal answer
A. None. § 43-14-20(k) says continuing education hours can't be carried forward to a later renewal period. Electrical contractors need 4 hours per year, 8 per cycle (Board FAQ), so the 4 extra hours simply don't count again.
GA-LAW-07. A candidate has failed the Georgia electrical contractor exam twice. What's required before a third attempt?
- A. A six-month waiting period
- B. New experience affidavits
- C. Proof of completing a Board-approved review course
- D. Switching to the other license class
Reveal answer
C. Rule 121-2-.06(1) requires a Board-approved review course after two failed exams. If the candidate fails a third time, no further course is required. The rule doesn't impose a waiting period, new affidavits, or a class change.
GA-LAW-08. Using the apprenticeship route to a Class II license, a candidate who completed a U.S. Department of Labor accredited or approved electrical apprenticeship also needs how much full-time experience on three-phase systems?
- A. 1 year
- B. 2 years
- C. 3 years
- D. 4 years
Reveal answer
A. 1 year. § 43-14-8(f)(2)(C) pairs a completed apprenticeship with one year of full-time three-phase experience. Two years of three-phase work (B) is the minimum within the standard four-year route, and four years (D) is that route's total.
Quick answers
Do I need a high school diploma or GED? Neither the licensing statute (§ 43-14-8) nor the Board's rule (121-3-.01) lists one.
Do I still need three references? The 2026 law asks for sworn experience affidavits, but the Board's published checklist still lists three reference forms. Provide what GOALS asks for when you file.
Is there a minimum age? The still-published Board rule says 21, while the reenacted 2026 licensing statute reviewed for this page does not state a minimum age. Because those public sources are not yet reconciled, confirm the live Board/GOALS requirement before filing.
Which NEC edition is on the exam? For exams through December 31, 2026, PSI's permitted-reference list includes the Georgia State Electrical 2023 National Electrical Code or the NEC Handbook (PSI handbook, p. 11). See NEC adoption by state for Georgia's amendment dates.
Official sources
- Signed SB 553 (2026)
- Georgia General Statutes Summary 2026 — Act 472 / SB 553
- O.C.G.A. Title 43, Chapter 14 as re-enacted, effective July 1, 2026:
- § 43-14-2
- § 43-14-8
- § 43-14-19
- § 43-14-20
- § 43-14-23
- The Board directs readers to the free official annotated code on LexisNexis.
- Georgia Board Rules, Department 121:
- Georgia State Board of Electrical Contractors:
- GOALS licensing portal and fee schedule
- PSI Candidate Information Handbook, Division of Electrical Contractors (Rev. 11/2024; reference list effective through Dec. 31, 2026)
Last verified: October 1, 2026. On that date we checked:
- the re-enacted statute sections listed above;
- Board Rules 121-2, 121-3, 121-4, and 121-6;
- the Board's FAQ and how-to guide;
- the PSI candidate handbook.
Castleport Test Prep is an independent exam prep publisher. We're not affiliated with, endorsed by, or approved by the Georgia Secretary of State, the State Construction Industry Licensing Board or its Division of Electrical Contractors, or PSI. Exam and credential names identify their subjects, and trademarks belong to their owners. The practice questions on this page are original and aren't official exam items. This page explains published law and rules; the Board decides every application.