This free NCEES PS practice test has 50 original, unofficial questions with worked solutions across all five knowledge areas on the Principles and Practice of Surveying exam specification used before July 2027, and there's no signup. Every question is also tagged to the specification that takes effect in July 2027, so you can see where it maps if your exam falls after the change.

Practice questions

Question 1

Legal Principles · Monuments vs. distances · Select one · PS-L01
July 2027 area: Legal Principles

Applying the traditional priority-of-calls rule reflected in the cited sources, a 1958 deed's third call reads "North 210.00 feet to an iron pipe." You find an undisturbed iron pipe that matches the deed's description. Title records and a 1958 survey show it was set for this conveyance. It sits 213.40 ft from the previous corner along the called bearing, and no other evidence conflicts. Where is the corner?

Your response, Question 1
Answer and explanation, Question 1

Answer: A. At the pipe, 213.40 ft along the line.

When an original, undisturbed monument that the deed calls for disagrees with the deed's distance, the monument controls. The distance was the original surveyor's attempt to describe where the pipe went; the pipe is where the parties actually put the corner. That only works because the facts prove this is the called-for, original pipe.

Why the other choices miss: B: Treats the measurement as more important than the monument it describes. C: No rule splits the difference between a monument and a distance. D: This is a question about where the title line is, not about possession or encroachment.

If the pipe couldn't be tied to the original conveyance, it wouldn't carry this weight. Courts in each state apply this rule through their own case law.

Source: California Code of Civil Procedure § 2077 (rules for construing descriptions), Rules One–Three; BLM, The Basics of Boundary Law Study Guide, pp. 17–18 (monuments prevail over measurements)

Jump to answer key

How to use this test: Work each question before you open its answer. For exam pace, give yourself 180 minutes for all 50. The real exam gives you 6 hours of testing time for 100 questions, or 3.6 minutes a question (NCEES Examinee Guide, May 2026, p. 16). Untimed is fine for a first pass. Keep the free NCEES PS Reference Handbook open as you work, since that's what you'll have on screen on exam day. Scoring rules and the answer key follow Question 50.


Question 2

Legal Principles · Area call vs. bearings and distances · Select one · PS-L02
July 2027 area: Legal Principles

Applying the traditional priority-of-calls rule reflected in the cited sources, a description's bearings and distances close mathematically and enclose 1.87 acres. It ends "containing 2.00 acres, more or less." No monuments are called for or found. What controls the boundary?

Your response, Question 2
Answer and explanation, Question 2

Answer: B. The bearings and distances.

Area is the weakest element in a description. It's a result calculated from the lines, not something the parties laid out on the ground, and "more or less" signals it's an estimate. With no monuments in play, the lines and angles control and the 1.87-acre result stands.

Why the other choices miss: A: Puts area above lines, which reverses the usual order. C: There's no general rule favoring whichever reading gives more land. D: A description that closes and can be located on the ground isn't void just because its acreage call is off.

Source: California Code of Civil Procedure § 2077 (rules for construing descriptions), Rule Three; BLM, The Basics of Boundary Law Study Guide, p. 12 (priority of calls)

Jump to answer key

Question 3

Legal Principles · Accretion along a river · Select one · PS-L03
July 2027 area: Legal Principles

Under the common-law accretion rule described in Nebraska v. Iowa, a river slowly and imperceptibly deposits sediment over 25 years along a riverfront lot, building a 30-ft strip of new dry land. Who generally owns the new strip?

Your response, Question 3
Answer and explanation, Question 3

Answer: B. The owner of the riverfront lot.

Slow, imperceptible buildup is accretion. Under the accretion rule, the riparian owner's boundary keeps following the water, so the new land belongs to the riverfront lot.

Why the other choices miss: A: The riverbed owner keeps land exposed by a sudden change (avulsion), not by gradual accretion. C: The opposite owner loses land to erosion in this situation; they don't gain the deposit. D: Under the cited common-law rule, a decree is not what creates the gradual-accretion change described here.

Navigability and state law affect details such as who owns the bed. The gradual-versus-sudden distinction is the core rule.

Source: Nebraska v. Iowa, 143 U.S. 359 (1892), accretion vs. avulsion rule

Jump to answer key

Question 4

Legal Principles · Accretion, reliction, and avulsion · Select two · PS-L04
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

Which two statements match the common-law water-boundary rules described by the U.S. Supreme Court in Stop the Beach Renourishment (2010)?

Your response, Question 4 (select two)

Select two. Both, and only both, must be chosen to score.

Answer and explanation, Question 4

Answer: A and C.

Gradual changes (accretion, where material is deposited, and reliction, where water slowly recedes) move the boundary and give the upland owner the new land. A sudden change (avulsion) doesn't move the boundary; it stays at the pre-event line.

Why the other choices miss: B: Reverses the avulsion rule. Land suddenly exposed seaward of the old line belongs to the owner of the submerged land, usually the state. D: Ignores avulsion.

Source: Stop the Beach Renourishment, Inc. v. Florida Dept. of Environmental Protection, 560 U.S. 702 (2010), opinion Part I (summarized in the syllabus); Nebraska v. Iowa, 143 U.S. 359 (1892), accretion vs. avulsion rule

Jump to answer key

Question 5

Legal Principles · Adverse possession against federal land · Select one · PS-L05
July 2027 area: Legal Principles

Your client's fence has enclosed a 12-ft strip of adjoining U.S. Forest Service land openly and continuously for 31 years. The client asks whether title to the strip has passed by adverse possession. What's the best answer?

Your response, Question 5
Answer and explanation, Question 5

Answer: C. No; adverse possession can't be the basis of a quiet-title suit against the United States.

The federal Quiet Title Act says nothing in it permits suits against the United States based on adverse possession. However long the fence has stood, adverse possession cannot be the basis of the quiet-title claim described here.

Why the other choices miss: A, B, D: All apply private-land adverse possession thinking to land owned by the federal government.

Many states also bar adverse possession of state or public land. California, for example, says possession of land owned by the state or any public entity never ripens into title.

Source: 28 U.S.C. § 2409a (Quiet Title Act), § 2409a(n); California Civil Code § 1007

Jump to answer key

Question 6

Legal Principles · Senior rights in sequential conveyances · Enter a number · PS-L06
July 2027 area: Legal Principles

For this practice item, apply the traditional junior/senior-rights principle reflected in the cited source. A parent tract's south line is recorded as 520.00 ft. Between the undisputed original corners, you measure 516.48 ft. The common owner first deeded "the East 260.00 feet" to Parker. A year later, the owner deeded "the West 260.00 feet" to Quinn. Nothing else bears on the line. How wide is Quinn's parcel along the south line, in feet? Round to two decimal places.

Answer and explanation, Question 6

Answer: 256.48 ft. Any entry that rounds to 256.48 counts.

Parker's deed came first, so it's senior and gets its full 260.00 ft. Quinn's later (junior) deed can only convey what the owner still had: 516.48 − 260.00 = 256.48 ft. The junior parcel absorbs the 3.52-ft shortage.

Common wrong answers: 258.24: Splits the shortage equally, which is the approach for parcels created at the same time, not one after another. 260.00: Ignores the shortage and creates a 3.52-ft overlap on paper.

Recording statutes, possession, and other evidence can change who is senior in a real case. This question removes those complications on purpose.

Source: BLM, The Basics of Boundary Law Study Guide, pp. 7, 10, 15 (senior and junior rights)

Jump to answer key

Question 7

Legal Principles · Proration in a platted block · Enter a number · PS-L07
July 2027 area: Legal Principles

For this practice item, apply the simultaneous-conveyance proration rule reflected in the cited cases. A recorded plat shows Block 4 with Lots 1 through 4, each 50.00 ft wide, for a 200.00-ft block. Lot 1 is westmost. You find the original block-corner monuments 201.20 ft apart. Every lot is dimensioned on the plat, and no original lot corners or other evidence survive. How far from the west block monument is the line between Lots 3 and 4, in feet? Round to two decimal places.

Answer and explanation, Question 7

Answer: 150.90 ft. Any entry that rounds to 150.90 counts.

Lots created by one plat are created at the same moment, so none is senior to another. The 1.20-ft excess is shared in proportion to the record widths: each lot gets 50.00 × 201.20 / 200.00 = 50.30 ft. The Lot 3–4 line is 3 × 50.30 = 150.90 ft from the west monument.

Common wrong answers: 150.00: Uses record distances from one end and dumps all the excess into Lot 4. 151.20: Gives all the excess to the first three lots.

The answer changes if a lot is shown without a dimension (that remainder lot usually takes the excess or shortage) or if original lot corners are found. Courts reach these results through state case law.

Source: Illinois Supreme Court, 56 Ill. 399 (pro rata division of a block deficiency); Tolson v. Southwestern Improvement Ass'n (Ark. 1911)

Jump to answer key

Question 8

Legal Principles · Easement classification · Select one · PS-L08
July 2027 area: Legal Principles

A natural-gas utility holds a 30-ft pipeline easement across a farm, granted by a recorded deed. The utility owns no land that the easement serves. How is this easement best classified?

Your response, Question 8
Answer and explanation, Question 8

Answer: B. In gross.

An easement in gross benefits a person or company, not a neighboring parcel. An appurtenant easement needs a dominant parcel that it serves. Here the utility holds the right for its business and owns no benefited land, so it's in gross.

Why the other choices miss: A: There's no dominant parcel. C: Prescriptive easements arise from long use, not a recorded grant. D: A covenant restricts how land is used; it doesn't grant a right to put a pipeline across it.

Source: California Civil Code § 802 (servitudes held "not attached to land"); Moylan v. Dykes, 181 Cal. App. 3d 561 (1986) (easement in gross is not attached to particular land)

Jump to answer key

Question 9

Legal Principles · Original corners control · Select one · PS-L09
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

Retracing a section line, you recover the original, undisturbed quarter-section stone with its bearing trees. It's 41 ft north of the midpoint between the two existing original section corners. What controls?

Your response, Question 9
Answer and explanation, Question 9

Answer: A. The original stone.

Federal law says the corners marked in the returned original surveys are the proper corners. A recovered original corner stays where it is, even if the original surveyor didn't place it exactly at the midpoint. The "equidistant" rule applies to corners that weren't marked in the original survey.

Why the other choices miss: B, C, D: Each replaces a proven original corner with a computed position, which moves the land everyone has relied on since the original survey.

Source: 43 U.S.C. § 752 (boundaries and contents of public lands), paragraph First

Jump to answer key

Question 10

Legal Principles · Obliterated vs. lost corners · Select one · PS-L10
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

The original wood post and bearing trees for a section corner are gone. A 1962 county surveyor's record ties a stone set at the corner. Two long-time landowners show you a fence corner built on that stone, and the record ties and their testimony agree. How should you treat the corner?

Your response, Question 10
Answer and explanation, Question 10

Answer: B. Obliterated; restore it at the position the evidence proves.

Under the 2009 BLM Manual, an obliterated corner is one where the original monument and accessories are gone, but the position was perpetuated or can be recovered by substantial evidence, such as reliable records and testimony. That's this case. Proportioning is only for lost corners, where no such evidence exists.

Why the other choices miss: A, C: Proportioning a corner whose position can be proven moves it away from where it belongs. D: Nothing of the original monument remains, so the original isn't in place.

Source: Florida DEP, Certified Corner Record Instruction Manual (quotes the 2009 BLM Manual definitions), Existent, Obliterated, Lost corner definitions; BLM, 1973-to-2009 Manual of Surveying Instructions crosswalk, §§ 6-17, 7-2, 7-16

Jump to answer key

Question 11

Legal Principles · Contents of quarter sections · Enter a number · PS-L11
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

The official plat returns Section 14 as containing 643.20 acres and gives no separate contents for its quarter sections. Under 43 U.S.C. § 752, how many acres does the NE¼ contain? Round to two decimal places.

Answer and explanation, Question 11

Answer: 160.80 acres. Any entry that rounds to 160.80 counts.

When a quarter section's contents weren't returned, the statute holds it to contain one-fourth of the section's returned contents: 643.20 ÷ 4 = 160.80 acres.

Common wrong answers: 160.00: Uses the nominal quarter section instead of one-fourth of the returned contents.

Source: 43 U.S.C. § 752 (boundaries and contents of public lands), paragraph Third

Jump to answer key

Professional Survey Practices (Questions 12–24)

Question 12

Professional Survey Practices · Traverse precision · Enter a number · PS-P01
July 2027 area: Professional Survey Practices

A closed traverse has a perimeter of 2,450.36 ft. The misclosure in latitude is −0.12 ft and in departure is +0.09 ft. What is the relative precision? Enter the denominator of 1:x, rounded to the nearest 100.

Answer and explanation, Question 12

Answer: 1:16,300. Any entry that rounds to 16,300 counts.

Linear misclosure = √(0.12² + 0.09²) = 0.15 ft. Precision = 2,450.36 ÷ 0.15 = 16,336, or 1:16,300.

Common wrong answers: 11,700: Adds the two misclosures (0.21 ft) instead of combining them as a vector. 20,400: Uses only the latitude misclosure.

Source: Worked from the stated inputs

Jump to answer key

Question 13

Professional Survey Practices · Area by coordinates · Enter a number · PS-P02
July 2027 area: Professional Survey Practices

A parcel's corners, in order around the boundary, have these coordinates (N, E): (1000.00, 1000.00), (1000.00, 1420.00), (1310.00, 1500.00), (1350.00, 1060.00). What is the area in acres? Round to three decimal places.

Answer and explanation, Question 13

Answer: 3.290 acres. Any entry that rounds to 3.290 counts.

Use the coordinate (cross-multiplication) method: area = ½ |Σ (Eᵢ × Nᵢ₊₁ − Eᵢ₊₁ × Nᵢ)|. The sum comes to 286,600, so the area is 143,300 sq ft. Divide by 43,560: 3.290 acres.

Common wrong answers: 6.580: Forgets to halve the cross-product sum. A negative result: Lists the points the other way around; take the absolute value.

Source: Worked from the stated inputs

Jump to answer key

Question 14

Professional Survey Practices · Inverse between coordinates · Select one · PS-P03
July 2027 area: Professional Survey Practices

Point 1 is at N 5000.00, E 5000.00. Point 2 is at N 4612.40, E 5298.65. What are the bearing and distance from Point 1 to Point 2?

Your response, Question 14
Answer and explanation, Question 14

Answer: A. S 37°36′53″ E, 489.31 ft.

ΔN = −387.60 (south) and ΔE = +298.65 (east). Bearing angle = arctan(298.65 ÷ 387.60) = 37°36′53″, so S 37°36′53″ E. Distance = √(387.60² + 298.65²) = 489.31 ft.

Why the other choices miss: B: Inverts the ratio (ΔN over ΔE). C: The back bearing, from Point 2 to Point 1. D: Adds the coordinate differences instead of using the Pythagorean theorem.

Source: Worked from the stated inputs

Jump to answer key

Question 15

Professional Survey Practices · Ground to grid distance · Enter a number · PS-P04
July 2027 area: Areas of Practice/Types of Surveys

A measured horizontal ground distance is 1,500.00 ft. The mean ellipsoid height of the line is 1,200 ft, the grid scale factor is 0.99994, and you use R = 20,906,000 ft for the earth's radius. What is the grid distance in feet? Round to two decimal places.

Answer and explanation, Question 15

Answer: 1,499.82 ft. Any entry that rounds to 1,499.82 counts.

Elevation factor = R ÷ (R + h) = 20,906,000 ÷ 20,907,200 = 0.9999426. Combined factor = 0.99994 × 0.9999426 = 0.9998826. Grid distance = 1,500.00 × 0.9998826 = 1,499.82 ft.

Common wrong answers: 1,499.91: Applies only the grid scale factor. 1,500.18: Divides by the combined factor, which is the grid-to-ground direction.

Use ellipsoid height in the elevation factor, not orthometric height (elevation).

Source: Penn State GEOG 862, Lesson 6: Elevation Factor, R/(R + h) and combined factor

Jump to answer key

Question 16

Professional Survey Practices · Orthometric height from GNSS · Enter a number · PS-P05
July 2027 area: Areas of Practice/Types of Surveys

A static GNSS session gives an ellipsoid height h = 182.413 m. The geoid model gives a geoid height N = −31.207 m at the point. What is the orthometric height H in meters? Round to three decimal places.

Answer and explanation, Question 16

Answer: 213.620 m. Any entry that rounds to 213.620 counts.

H = h − N = 182.413 − (−31.207) = 213.620 m. In the conterminous U.S., the geoid lies below the ellipsoid, so N is negative and the orthometric height is larger than the ellipsoid height.

Common wrong answers: 151.206: Adds N instead of subtracting it. That's the most common sign error in GNSS heights.

This question uses meters because NGS publishes geoid heights in meters; convert at the end if your project is in feet.

Source: Roman & Weston (NGS), "Beyond GEOID12," FIG Working Week 2011, Figure 1, H = h − N; NGS, About OPUS, sample solution report (ORTHO HGT computed using GEOID18)

Jump to answer key

Question 17

Professional Survey Practices · OPUS processing · Select one · PS-P06
July 2027 area: Standards and Specifications

You upload a 3-hour dual-frequency static GPS file to NGS's Online Positioning User Service (OPUS). How will it be processed?

Your response, Question 17
Answer and explanation, Question 17

Answer: B. As a static (OPUS-S) solution.

OPUS accepts static files from 15 minutes to 48 hours. Files of 2 to 48 hours are processed with static software; files from 15 minutes to 2 hours use rapid-static. A 3-hour file goes to static processing.

Why the other choices miss: A: Rapid-static handles files under 2 hours. C: Four hours is the minimum for publicly sharing a solution (OPUS Share), not for processing. D: OPUS processes static data, not real-time corrections.

Source: NGS, About OPUS, Upload requirements; How does OPUS processing work?

Jump to answer key

Question 18

Professional Survey Practices · Federal land records · Select one · PS-P07
July 2027 area: Professional Survey Practices

For a PLSS retracement, you want images of the original federal land patents for the township. Where should you look first?

Your response, Question 18
Answer and explanation, Question 18

Answer: B. The BLM General Land Office Records website.

BLM's General Land Office Records site provides access to federal land conveyance records for the public land states, including images of land title records.

Why the other choices miss: A: Assessor data is for taxation and isn't a federal title record. C: FEMA's center publishes flood maps. D: NGS datasheets describe geodetic control marks.

Source: BLM General Land Office Records

Jump to answer key

Question 19

Professional Survey Practices · Reference monuments (ALTA Table A item 1) · Select one · PS-P08
July 2027 area: Standards and Specifications

A client selected Table A item 1 on an ALTA/NSPS survey under the 2021 standards. One corner falls in a busy traffic lane, where a monument would be destroyed. Which approach complies?

Your response, Question 19
Answer and explanation, Question 19

Answer: B. Set a reference monument or witness to the corner.

Table A item 1 asks for monuments at all major corners, and it expressly allows "a reference monument or witness to the corner" instead. That covers corners where a monument at the true position wouldn't survive.

Why the other choices miss: A, C: Item 1 doesn't exempt corners just because they're hard to mark. D: An unexplained offset monument misleads anyone who later finds it.

Edition check: The exam supplies and scores against the 2021 ALTA/NSPS standards.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), Table A, item 1

Jump to answer key

Question 20

Professional Survey Practices · U.S. survey foot vs. international foot · Enter a number · PS-P09
July 2027 area: Professional Survey Practices

A legacy State Plane (SPCS 83) easting is 2,000,000.00 U.S. survey feet. What is it in international feet? Round to two decimal places.

Answer and explanation, Question 20

Answer: 2,000,004.00 international ft. Any entry that rounds to 2,000,004.00 counts.

One U.S. survey foot = 1200/3937 m; one international foot = 0.3048 m exactly. Multiply: 2,000,000.00 × (1200/3937) ÷ 0.3048 = 2,000,004.00. The two feet differ by about 2 parts per million. That's trivial over a short line but about 4 ft on a coordinate this large.

Common wrong answers: 2,000,000.00: Treats the two feet as identical, which is how GIS layers end up shifted by several feet.

NIST and NOAA deprecated the U.S. survey foot after December 31, 2022. It remains in use for legacy coordinate systems such as SPCS 83 in states that adopted it.

Source: NIST/NOAA, Deprecation of the U.S. Survey Foot, 85 FR 62698 (Oct. 5, 2020), Summary; Table 1

Jump to answer key

Question 21

Professional Survey Practices · Record vs. measured on an ALTA plat · Select two · PS-P10
July 2027 area: Standards and Specifications

Under Section 6.B of the 2021 ALTA/NSPS standards, which two must the plat show?

Your response, Question 21 (select two)

Select two. Both, and only both, must be chosen to score.

Answer and explanation, Question 21

Answer: A and C.

Section 6.B.iii requires showing a significantly different measured dimension alongside the record dimension, clearly distinguished from it. Section 6.B.iv requires the basis of bearings and any difference from the record basis.

Why the other choices miss: B: Dropping record dimensions hides the comparison a title company needs. D: The standard reverses this. Dimensions must be horizontal ground dimensions unless otherwise noted.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), § 6.B.iii–iv

Jump to answer key

Question 22

Professional Survey Practices · Slope distance reduction · Enter a number · PS-P11
July 2027 area: Professional Survey Practices

A total station measures a slope distance of 412.36 ft at a zenith angle of 86°14′20″. What is the horizontal distance in feet? Round to two decimal places.

Answer and explanation, Question 22

Answer: 411.47 ft. Any entry that rounds to 411.47 counts.

With a zenith angle, horizontal distance = slope distance × sin(zenith) = 412.36 × sin(86°14′20″) = 411.47 ft.

Common wrong answers: 27.05: Uses cosine, which gives the vertical difference. 412.36: Skips the reduction.

Source: Worked from the stated inputs

Jump to answer key

Question 23

Professional Survey Practices · Lot yield · Enter a number · PS-P12
July 2027 area: Professional Survey Practices

A 12.50-acre tract is being subdivided. Assume 15% of the gross area goes to right-of-way and open space, and the minimum lot size is 9,000 sq ft. Ignoring lot shape, what is the maximum number of whole lots?

Answer and explanation, Question 23

Answer: 51 lots. Whole number only.

Gross area = 12.50 × 43,560 = 544,500 sq ft. Net = 544,500 × 0.85 = 462,825 sq ft. 462,825 ÷ 9,000 = 51.4, so 51 whole lots.

Common wrong answers: 60: Skips the 15% deduction. 52: Rounds 51.4 up, which would leave a lot under the minimum size.

The 15% deduction and lot size are made up for practice. Real numbers come from the local zoning and subdivision ordinances.

Source: Worked from the stated inputs

Jump to answer key

Question 24

Professional Survey Practices · Random error propagation · Enter a number · PS-P13
July 2027 area: Professional Survey Practices

Each full 100-ft tape length has an independent random error of ±0.010 ft. What random error do you expect in a 1,600-ft line made of 16 full tape lengths? Round to three decimal places.

Answer and explanation, Question 24

Answer: ±0.040 ft. Any entry that rounds to 0.040 counts.

Independent random errors add as the square root of the sum of squares: 0.010 × √16 = ±0.040 ft.

Common wrong answers: 0.160: Adds the errors directly, which is how systematic errors accumulate, not random ones.

Source: Worked from the stated inputs

Jump to answer key

Standards and Specifications (Questions 25–29)

Question 25

Standards and Specifications · Relative positional precision · Enter a number · PS-S01
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

Using the feet value printed in Section 3.E.v of the 2021 ALTA/NSPS standards, what is the maximum allowable relative positional precision between two adjacent corners 400.00 ft apart? Round to two decimal places.

Answer and explanation, Question 25

Answer: 0.09 ft. Any entry that rounds to 0.09 counts.

The standard allows 2 cm (0.07 ft) plus 50 parts per million of the direct distance between the two corners: 0.07 + 0.000050 × 400.00 = 0.07 + 0.02 = 0.09 ft. That's at the 95% confidence level.

Common wrong answers: 0.07: Leaves out the 50 ppm part. 0.02: Uses only the 50 ppm part.

2 cm is actually 0.066 ft, so a fully metric computation gives about 0.086 ft. The question specifies the printed 0.07 ft. Section 3.E.iii also stresses that a small relative positional precision doesn't make a corner correct if the boundary law behind it is wrong.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), § 3.E.i–v

Jump to answer key

Question 26

Standards and Specifications · Table A item 3, flood zone · Select one · PS-S02
July 2027 area: Standards and Specifications

A client selects Table A item 3 on a 2021 ALTA/NSPS survey. How is the flood zone determined?

Your response, Question 26
Answer and explanation, Question 26

Answer: B. By scaled map location and graphic plotting only.

Table A item 3 calls for the flood zone classification "depicted by scaled map location and graphic plotting only," with proper annotation from the federal flood insurance rate map or state or local equivalent. It's a map reading, not an elevation survey.

Why the other choices miss: A, C: Elevation work is a separate service, such as an Elevation Certificate. D: Item 3 applies whether or not a map amendment exists.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), Table A, item 3

Jump to answer key

Question 27

Standards and Specifications · New descriptions · Select two · PS-S03
July 2027 area: Standards and Specifications

Under Section 6.B.ii of the 2021 ALTA/NSPS standards, which two statements are correct?

Your response, Question 27 (select two)

Select two. Both, and only both, must be chosen to score.

Answer and explanation, Question 27

Answer: A and C.

Section 6.B.ii discourages new descriptions except when the surveyor and insurer think one is necessary, and especially discourages them for platted lots. When one is prepared (other than for an original survey), the plat must note whether it describes the same real estate as the record description and, if not, how it differs.

Why the other choices miss: B: New descriptions are the exception, not the rule. D: Section 6.B.i still requires the current record description on the plat.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), § 6.B.i–ii

Jump to answer key

Question 28

Standards and Specifications · Elevation Certificate Section E · Select one · PS-S04
July 2027 area: Standards and Specifications

A house is in Zone A with no base flood elevation (BFE). The owner wants an Elevation Certificate to document floodplain-management compliance, not to support a Letter of Map Amendment. Under the 2023 instructions, who may provide the compliance information in Section E?

Your response, Question 28
Answer and explanation, Question 28

Answer: B. A local floodplain official, the owner, or the owner's authorized representative.

For Zones AO, AR/AO, and A without a BFE, the instructions let a local floodplain management official, the owner, or the owner's authorized representative provide compliance information in Section E. Certified elevations are required if the certificate will support a LOMA, CLOMA, LOMR-F, or CLOMR-F request.

Why the other choices miss: A: That's the rule for Section C elevations, not Section E in these zones. C: FEMA doesn't complete Elevation Certificates. D: Section E exists specifically for Zone AO and Zone A compliance.

Source: FEMA Elevation Certificate and Instructions, 2023 edition (FF-206-FY-22-152, 8/23), Instructions p. 1

Jump to answer key

Question 29

Standards and Specifications · Elevation Certificate validity · Select one · PS-S05
July 2027 area: Standards and Specifications

An Elevation Certificate was completed using construction drawings before the building was built. Under the 2023 form, what happens when construction is finished?

Your response, Question 29
Answer and explanation, Question 29

Answer: B. A new Elevation Certificate is required.

Section C of the form says a new Elevation Certificate will be required when construction of the building is complete. A certificate based on drawings describes a plan, not the finished building.

Why the other choices miss: A: The no-expiration rule applies to certificates completed for the finished building, and even those need redoing after physical changes that affect key items. C: Only an authorized certifier can complete the survey sections. D: The printed expiration date applies to the blank form, not to completed certificates.

A completed certificate doesn't expire unless a physical change to the building invalidates information in Items A8 or A9 or Sections C, E, or H.

Source: FEMA Elevation Certificate and Instructions, 2023 edition (FF-206-FY-22-152, 8/23), Form p. 1 and Section C

Jump to answer key

Business Practices (Questions 30–36)

Question 30

Business Practices · Sealing documents · Select one · PS-B01
July 2027 area: Business Practices

A developer asks you to seal a boundary plat prepared by an unlicensed technician you never supervised. You review it closely, and it looks right. Under the professional-conduct rules cited below, what should you do?

Your response, Question 30
Answer and explanation, Question 30

Answer: B. Decline; you may seal only work prepared under your responsible charge.

The cited professional-conduct rules bar licensees from sealing documents not prepared under their responsible charge, meaning direct control and personal supervision of the work. Reviewing finished work afterward isn't responsible charge.

Why the other choices miss: A, C, D: A review, a disclaimer, or an indemnity agreement doesn't create responsible charge.

Your own board's rules govern. Check the version your board has adopted.

Source: New Mexico Admin. Code 16.39.8.9, Rules of Professional Conduct; 21 NCAC 56 .0701, Rules of Professional Conduct (North Carolina), (d)

Jump to answer key

Question 31

Business Practices · Conflicts of interest · Select one · PS-B02
July 2027 area: Business Practices

Under the cited New Mexico professional-conduct rule, a client hires you to survey a disputed line and you learn your brother-in-law owns the adjoining parcel. What should you do first?

Your response, Question 31
Answer and explanation, Question 31

Answer: A. Disclose the relationship to the client before going further.

The cited rule requires licensees to disclose known or potential conflicts of interest, including circumstances that could appear to influence their judgment. A relative owning the adjoining parcel in a dispute is exactly that.

Why the other choices miss: B: Personal confidence in your objectivity doesn't replace disclosure. C: The rules require disclosure, not a blanket refusal. D: Hiding information makes the conflict worse.

Source: New Mexico Admin. Code 16.39.8.9, Rules of Professional Conduct

Jump to answer key

Question 32

Business Practices · Fee estimate · Enter a number · PS-B03
July 2027 area: Business Practices

A survey crew costs $185 per hour and its equipment $45 per hour. The job takes 26 hours. Add 30% overhead to the direct cost, then add 12% profit to that total. What is the fee to the nearest dollar?

Answer and explanation, Question 32

Answer: $8,707. Any entry that rounds to 8,707 counts.

Direct cost = ($185 + $45) × 26 = $5,980. With overhead: $5,980 × 1.30 = $7,774. With profit: $7,774 × 1.12 = $8,706.88, or $8,707.

Common wrong answers: $8,492: Adds 42% in one step instead of applying profit on top of overhead. $6,698: Skips overhead.

The rates are made up for practice.

Source: Worked from the stated inputs

Jump to answer key

Question 33

Business Practices · Setting scope for an unusual ALTA survey · Select one · PS-B04
July 2027 area: Business Practices

A lender orders an ALTA/NSPS survey of a marina with leased boat slips. Under Section 2 of the 2021 standards, what should happen before work starts?

Your response, Question 33
Answer and explanation, Question 33

Answer: B. The request specifies the survey and Table A items, and the unusual scope is agreed in writing first.

Section 2 requires the request to say an ALTA/NSPS survey is required and which Table A items are included. It names marinas and leases as examples of properties whose scope should be discussed with the client, lender, and insurer and agreed in writing before work begins.

Why the other choices miss: A: Scope belongs before fieldwork. C: The insurer isn't responsible for survey costs unless it agrees in writing. D: The standards flag these properties precisely because they fall outside the normal scope.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), § 2

Jump to answer key

Question 34

Business Practices · Underground utilities and liability · Select one · PS-B05
July 2027 area: Business Practices

Table A item 11(b) is selected on a 2021 ALTA/NSPS survey. You submit an 811 locate request, but the utilities don't respond. What does the Table A note to item 11 require?

Your response, Question 34
Answer and explanation, Question 34

Answer: B. Note on the plat how the incomplete response affected your assessment.

The note to item 11 recognizes that 811 requests from surveyors may be ignored or answered incompletely, and says the surveyor must note on the plat how that affected the utility assessment. It also says that without excavation, underground features can't be depicted accurately, completely, and reliably.

Why the other choices miss: A: Guessing creates exactly the liability the note is meant to avoid. C: Observed evidence of utilities is still required under Section 5.E.iv. D: The standard itself says exact underground locations can't be guaranteed without excavation.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), Table A, item 11 and note

Jump to answer key

Question 35

Business Practices · Professional competence · Select one · PS-B06
July 2027 area: Business Practices

Under the cited New Mexico professional-conduct rule, your firm is asked to perform a hydrographic survey, but you have never performed hydrographic work and no one on staff is qualified for that work. What is the best response?

Your response, Question 35
Answer and explanation, Question 35

Answer: B. Limit your services to phases you are qualified to perform and have a properly qualified licensee perform the other phases.

The cited rule says a licensee should undertake assignments only when qualified by education or experience in the specific technical fields involved. It also allows an assignment that reaches beyond the licensee's own qualifications when the licensee limits personal services to qualified phases and the other phases are performed by qualified licensees.

Why the other choices miss: A: Learning on the client's project does not satisfy the cited qualification rule. C: Later review does not turn unqualified work into qualified professional service. D: A client waiver does not remove the licensee's professional duty.

Your own licensing board's rules govern your practice. This item tests the cited rule, not a claim that every jurisdiction uses identical wording.

Source: New Mexico Admin. Code 16.39.8.9, Rules of Professional Conduct, §16.39.8.9(B)(1), (3)

Jump to answer key

Question 36

Business Practices · Table A item 19, insurance · Select one · PS-B07
July 2027 area: Business Practices

Table A item 19, professional liability insurance, is selected on a 2021 ALTA/NSPS survey. How is it handled?

Your response, Question 36
Answer and explanation, Question 36

Answer: B. A certificate is furnished on request; it isn't addressed on the face of the plat.

Item 19 covers a minimum professional liability policy in effect during the contract. The certificate of insurance is furnished on request, and the item "shall not be addressed on the face of the plat or map."

Why the other choices miss: A, C: The item expressly keeps insurance off the plat. D: Table A items are optional and negotiated.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), Table A, item 19

Jump to answer key

Areas of Practice (Questions 37–50)

Question 37

Areas of Practice · Improvements near boundary lines · Select one · PS-A01
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

Unless physical access is restricted, Section 5.C.ii of the 2021 ALTA/NSPS standards requires locating walls, buildings, fences, and other improvements within what distance of each side of the boundary lines?

Your response, Question 37
Answer and explanation, Question 37

Answer: B. 5 ft.

Section 5.C.ii sets five feet on each side of the boundary lines. Where access within five feet is restricted, Section 6.B.xi requires a note identifying those areas.

Why the other choices miss: C: Ten feet is the distance for utility poles in Section 5.E.iv. A, D: Not distances used in this section.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), §§ 5.C.ii, 5.E.iv, 6.B.xi

Jump to answer key

Question 38

Areas of Practice · Water boundary notes · Select two · PS-A02
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

The surveyed property's title line follows a river. Under Section 6.B.vi of the 2021 ALTA/NSPS standards, which two items must the plat note include?

Your response, Question 38 (select two)

Select two. Both, and only both, must be chosen to score.

Answer and explanation, Question 38

Answer: A and C.

Section 6.B.vi requires a note with the date the boundary was measured, which attribute of the water feature was located, and a caveat that the boundary may change due to natural causes and may or may not be the actual limit of title.

Why the other choices miss: B: The required caveat says the opposite. D: Flood flow isn't part of the boundary note.

Source: ALTA/NSPS Minimum Standard Detail Requirements, 2021 (NSPS copy), § 6.B.vi

Jump to answer key

Question 39

Areas of Practice · Leveling section misclosure · Enter a number · PS-A03
July 2027 area: Standards and Specifications

You run a Second-Order, Class II leveling section. The shortest one-way length of the section is 2.25 km. What is the maximum allowable section misclosure in millimeters? Round to one decimal place.

Answer and explanation, Question 39

Answer: 12.0 mm. Any entry that rounds to 12.0 counts.

FGCS allows 8 mm × √D for Second-Order, Class II, where D is the shortest one-way length of the section in kilometers: 8 × √2.25 = 8 × 1.5 = 12.0 mm.

Common wrong answers: 9.0: Uses the Second-Order, Class I constant (6 mm). 18.0: Uses the Third-Order constant (12 mm). 18.0 is also what you get by forgetting the square root (8 × 2.25).

Source: FGCS Specifications and Procedures to Incorporate Electronic Digital/Bar-Code Leveling Systems, ver. 4.1 (2004), § 3.5, Field Procedures and Office Procedures tables, pp. 4–6

Jump to answer key

Question 40

Areas of Practice · Maximum sight length · Select one · PS-A04
July 2027 area: Standards and Specifications

Under the FGCS geodetic leveling specification, what is the maximum sight length for Second-Order, Class II leveling, unless the instrument maker recommends less?

Your response, Question 40
Answer and explanation, Question 40

Answer: C. 70 m.

The Field Procedures table lists maximum sight lengths of 50, 60, 60, 70, and 90 m for First-Order Class I through Third-Order. Second-Order, Class II is 70 m.

Why the other choices miss: A: First-Order, Class I. B: First-Order, Class II and Second-Order, Class I. D: Third-Order.

Source: FGCS Specifications and Procedures to Incorporate Electronic Digital/Bar-Code Leveling Systems, ver. 4.1 (2004), § 3.5, Field Procedures table, p. 4

Jump to answer key

Question 41

Areas of Practice · NMAS horizontal test · Enter a number · PS-A05
July 2027 area: Standards and Specifications

A map published at 1:1,200 is tested under the U.S. National Map Accuracy Standards. No more than 10% of tested well-defined points may be in error by more than what ground distance, in feet? Round to two decimal places.

Answer and explanation, Question 41

Answer: 3.33 ft. Any entry that rounds to 3.33 counts.

For publication scales larger than 1:20,000, the limit is 1/30 inch at map scale. 1/30 inch × 1,200 = 40 inches = 3.33 ft on the ground.

Common wrong answers: 2.00: Uses 1/50 inch, which applies to scales of 1:20,000 or smaller.

Source: USGS, Map Accuracy Standards (Fact Sheet 171-99), reprinting the U.S. National Map Accuracy Standards (1947)

Jump to answer key

Question 42

Areas of Practice · NMAS vertical test · Select one · PS-A06
July 2027 area: Standards and Specifications

A contour map with a 2-ft contour interval claims to meet the U.S. National Map Accuracy Standards. What is the vertical requirement?

Your response, Question 42
Answer and explanation, Question 42

Answer: B. No more than 10% of tested elevations may be in error by more than 1 ft.

NMAS says no more than 10% of the elevations tested may be in error by more than one-half the contour interval. Half of 2 ft is 1 ft.

Why the other choices miss: A: NMAS allows up to 10% to exceed the limit. C: Uses the full interval. D: NMAS isn't stated as an RMSE; that's the approach of newer standards.

Source: USGS, Map Accuracy Standards (Fact Sheet 171-99), reprinting the U.S. National Map Accuracy Standards (1947)

Jump to answer key

Question 43

Areas of Practice · NSSDA horizontal accuracy · Enter a number · PS-A07
July 2027 area: Standards and Specifications

An orthoimage is tested against 25 well-distributed checkpoints. RMSEx = RMSEy = 0.20 ft. Under the FGDC National Standard for Spatial Data Accuracy (NSSDA), what is the horizontal accuracy at the 95% confidence level, in feet? Round to two decimal places.

Answer and explanation, Question 43

Answer: 0.49 ft. Any entry that rounds to 0.49 counts.

RMSEr = √(0.20² + 0.20²) = 0.283 ft. When RMSEx = RMSEy, NSSDA horizontal accuracy = 1.7308 × RMSEr = 1.7308 × 0.283 = 0.49 ft. (Equivalently, 2.4477 × 0.20 = 0.49 ft.)

Common wrong answers: 0.39: Uses the vertical factor 1.9600 on a single component. 0.28: Stops at RMSEr without converting to 95% confidence.

Report it as "Tested 0.49 ft horizontal accuracy at 95% confidence level."

Source: ASPRS Positional Accuracy Standards for Digital Geospatial Data, Edition 1 (2014), Annex B, Examples 5–6, pp. A17–A18 (NSSDA relationships)

Jump to answer key

Question 44

Areas of Practice · Cut/fill on a grade stake · Select one · PS-A08
July 2027 area: Areas of Practice/Types of Surveys

From a benchmark at elevation 742.18, you take a backsight of 4.62. The rod reading on the ground at a stake is 6.95. Design subgrade at the stake is 733.40. What goes on the stake?

Your response, Question 44
Answer and explanation, Question 44

Answer: A. C 6.45.

Height of instrument = 742.18 + 4.62 = 746.80. Ground = 746.80 − 6.95 = 739.85. Ground is 739.85 − 733.40 = 6.45 ft above design, so it's a cut of 6.45.

Why the other choices miss: B: Right number, wrong direction. Ground above design means cut. C: Compares design with the benchmark elevation instead of the ground. D: Compares design with the height of instrument and forgets to subtract the ground rod reading.

Source: Worked from the stated inputs

Jump to answer key

Question 45

Areas of Practice · Horizontal curve stationing · Enter a number · PS-A09
July 2027 area: Areas of Practice/Types of Surveys

A circular curve has its PI at station 41+18.37, a deflection angle Δ = 32°30′00″, and radius R = 950.00 ft. Stations run along the curve. What is the station of the PT? Enter it in feet (for 41+18.37, enter 4118.37), rounded to two decimal places.

Answer and explanation, Question 45

Answer: 43+80.34. Any entry that rounds to 4,380.34 counts.

Tangent T = R tan(Δ/2) = 950.00 × tan 16°15′ = 276.90 ft. PC = 4,118.37 − 276.90 = 38+41.47. Curve length L = πRΔ/180 = 538.87 ft. PT = 3,841.47 + 538.87 = 43+80.34.

Common wrong answers: 4,395.27: Adds the tangent to the PI. 4,373.15: Adds the long chord (531.68 ft) instead of the arc length. 4,657.24: Adds the curve length to the PI instead of the PC.

Source: Worked from the stated inputs

Jump to answer key

Question 46

Areas of Practice · Sag vertical curve low point · Enter a number · PS-A10
July 2027 area: Areas of Practice/Types of Surveys

An equal-tangent sag vertical curve has g₁ = −2.00%, g₂ = +3.00%, and L = 400 ft. The PVI is at station 20+00, elevation 512.40. What is the elevation of the low point? Round to two decimal places.

Answer and explanation, Question 46

Answer: 514.80 ft (at station 19+60). Any entry that rounds to 514.80 counts.

BVC is at 18+00, elevation 512.40 + 0.02 × 200 = 516.40. The rate of grade change r = (3.00 − (−2.00))% ÷ 400 ft. The low point is where the grade is zero: x = 2.00 × 400 ÷ 5.00 = 160 ft from the BVC, at 19+60. Elevation = 516.40 − 0.02 × 160 + (0.05 ÷ 400) × 160² ÷ 2 = 516.40 − 3.20 + 1.60 = 514.80.

Common wrong answers: 516.40: The BVC elevation. 512.40: The PVI elevation, which lies on the tangents, not on the curve.

Source: Worked from the stated inputs

Jump to answer key

Question 47

Areas of Practice · Average end area volume · Enter a number · PS-A11
July 2027 area: Areas of Practice/Types of Surveys

Two cross sections 50 ft apart have cut areas of 168 sq ft and 244 sq ft. Using the average end area method, what is the volume in cubic yards? Round to one decimal place.

Answer and explanation, Question 47

Answer: 381.5 CY. Any entry that rounds to 381.5 counts.

Volume = (168 + 244) ÷ 2 × 50 = 10,300 cu ft. Divide by 27: 381.5 CY.

Common wrong answers: 763.0: Forgets to average the two areas. 10,300: Leaves the answer in cubic feet.

Source: Worked from the stated inputs

Jump to answer key

Question 48

Areas of Practice · Restoring a lost quarter corner · Enter a number · PS-A12
July 2027 area: Areas of Practice/Types of Surveys (Boundary Division)

An interior north-south section line (not in the north or west tier of sections) has a record distance of 40.00 chains to the quarter corner and 40.00 chains beyond. Both section corners are existent and measure 5,283.10 ft apart. The quarter corner is lost. How far from the south section corner should it be restored, in feet? Round to two decimal places.

Answer and explanation, Question 48

Answer: 2,641.55 ft. Any entry that rounds to 2,641.55 counts.

A lost quarter corner on an interior section line is restored by single proportionate measurement between the two section corners. With equal record halves, it goes at the proportional midpoint: 5,283.10 ÷ 2 = 2,641.55 ft.

Common wrong answers: 2,640.00: Uses the record 40 chains from the south corner and pushes all of the excess north.

Single proportion applies here only because the corner is truly lost and the record distances are equal. Lines in the north and west tiers are handled differently.

Source: BLM, 1973-to-2009 Manual of Surveying Instructions crosswalk, § 7-16, single proportionate measurement; 43 U.S.C. § 752 (boundaries and contents of public lands)

Jump to answer key

Question 49

Areas of Practice · Contour interpolation · Enter a number · PS-A13
July 2027 area: Areas of Practice/Types of Surveys

Two spot elevations, 101.6 and 104.2, are 80.0 ft apart on a uniform slope. How far from the 101.6 shot does the 103-ft contour cross the line? Round to one decimal place.

Answer and explanation, Question 49

Answer: 43.1 ft. Any entry that rounds to 43.1 counts.

Distance = (103.0 − 101.6) ÷ (104.2 − 101.6) × 80.0 = 1.4 ÷ 2.6 × 80.0 = 43.1 ft.

Common wrong answers: 36.9: Measures from the 104.2 shot instead. 40.0: Assumes the contour falls halfway.

Source: Worked from the stated inputs

Jump to answer key

Question 50

Areas of Practice · As-built pipe grade · Enter a number · PS-A14
July 2027 area: Areas of Practice/Types of Surveys

You measure the upstream invert of a newly laid storm pipe at elevation 512.34 ft and the downstream invert at 509.88 ft. The horizontal run between them is 246.0 ft. What is the pipe's as-built fall in percent? Enter the percent, rounded to two decimal places.

Answer and explanation, Question 50

Answer: 1.00%. Any entry that rounds to 1.00 counts.

The elevation drop is 512.34 − 509.88 = 2.46 ft. Divide by the horizontal run and convert to percent: 2.46 ÷ 246.0 × 100 = 1.00%.

Common wrong answer: 0.01: That's the decimal slope before multiplying by 100 to express it as a percent.

Source: Worked from the stated inputs.

Jump to answer key

Score your attempt

Give yourself one point for each question you got right before reading its explanation.

  • Select two questions are all-or-nothing, the way NCEES scores every question. One wrong or missing choice scores zero.
  • Enter a number questions count if your answer rounds to the key at the precision the question asks for.
  • Your score is correct answers ÷ 50. Count unanswered questions separately, so you can tell "didn't know" from "ran out of time."

Answer key

Answer key
QuestionCurrent areaJuly 2027 areaFormatAnswer
1Legal PrinciplesLegal PrinciplesSelect oneA
2Legal PrinciplesLegal PrinciplesSelect oneB
3Legal PrinciplesLegal PrinciplesSelect oneB
4Legal PrinciplesAreas of Practice/Types of Surveys (Boundary Division)Select twoA and C
5Legal PrinciplesLegal PrinciplesSelect oneC
6Legal PrinciplesLegal PrinciplesEnter a number256.48 ft
7Legal PrinciplesLegal PrinciplesEnter a number150.90 ft
8Legal PrinciplesLegal PrinciplesSelect oneB
9Legal PrinciplesAreas of Practice/Types of Surveys (Boundary Division)Select oneA
10Legal PrinciplesAreas of Practice/Types of Surveys (Boundary Division)Select oneB
11Legal PrinciplesAreas of Practice/Types of Surveys (Boundary Division)Enter a number160.80 acres
12Professional Survey PracticesProfessional Survey PracticesEnter a number1:16,300
13Professional Survey PracticesProfessional Survey PracticesEnter a number3.290 acres
14Professional Survey PracticesProfessional Survey PracticesSelect oneA
15Professional Survey PracticesAreas of Practice/Types of SurveysEnter a number1,499.82 ft
16Professional Survey PracticesAreas of Practice/Types of SurveysEnter a number213.620 m
17Professional Survey PracticesStandards and SpecificationsSelect oneB
18Professional Survey PracticesProfessional Survey PracticesSelect oneB
19Professional Survey PracticesStandards and SpecificationsSelect oneB
20Professional Survey PracticesProfessional Survey PracticesEnter a number2,000,004.00 international ft
21Professional Survey PracticesStandards and SpecificationsSelect twoA and C
22Professional Survey PracticesProfessional Survey PracticesEnter a number411.47 ft
23Professional Survey PracticesProfessional Survey PracticesEnter a number51 lots
24Professional Survey PracticesProfessional Survey PracticesEnter a number±0.040 ft
25Standards and SpecificationsAreas of Practice/Types of Surveys (Boundary Division)Enter a number0.09 ft
26Standards and SpecificationsStandards and SpecificationsSelect oneB
27Standards and SpecificationsStandards and SpecificationsSelect twoA and C
28Standards and SpecificationsStandards and SpecificationsSelect oneB
29Standards and SpecificationsStandards and SpecificationsSelect oneB
30Business PracticesBusiness PracticesSelect oneB
31Business PracticesBusiness PracticesSelect oneA
32Business PracticesBusiness PracticesEnter a number$8,707
33Business PracticesBusiness PracticesSelect oneB
34Business PracticesBusiness PracticesSelect oneB
35Business PracticesBusiness PracticesSelect oneB
36Business PracticesBusiness PracticesSelect oneB
37Areas of PracticeAreas of Practice/Types of Surveys (Boundary Division)Select oneB
38Areas of PracticeAreas of Practice/Types of Surveys (Boundary Division)Select twoA and C
39Areas of PracticeStandards and SpecificationsEnter a number12.0 mm
40Areas of PracticeStandards and SpecificationsSelect oneC
41Areas of PracticeStandards and SpecificationsEnter a number3.33 ft
42Areas of PracticeStandards and SpecificationsSelect oneB
43Areas of PracticeStandards and SpecificationsEnter a number0.49 ft
44Areas of PracticeAreas of Practice/Types of SurveysSelect oneA
45Areas of PracticeAreas of Practice/Types of SurveysEnter a number43+80.34
46Areas of PracticeAreas of Practice/Types of SurveysEnter a number514.80 ft (at station 19+60)
47Areas of PracticeAreas of Practice/Types of SurveysEnter a number381.5 CY
48Areas of PracticeAreas of Practice/Types of Surveys (Boundary Division)Enter a number2,641.55 ft
49Areas of PracticeAreas of Practice/Types of SurveysEnter a number43.1 ft
50Areas of PracticeAreas of Practice/Types of SurveysEnter a number1.00%

Tally by knowledge area (exams before July 2027)

Tally by knowledge area (exams before July 2027)
AreaQuestionsYour correct
Legal Principles1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11___ of 11
Professional Survey Practices12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24___ of 13
Standards and Specifications25, 26, 27, 28, 29___ of 5
Business Practices30, 31, 32, 33, 34, 35, 36___ of 7
Areas of Practice37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50___ of 14

Tally for exams in July 2027 or later

If your appointment is in July 2027 or later, use this table instead. It sorts the same 50 questions into the six new areas.

Tally for exams in July 2027 or later
AreaQuestionsYour correct
Professional Survey Practices12, 13, 14, 18, 20, 22, 23, 24___ of 8
Standards and Specifications17, 19, 21, 26, 27, 28, 29, 35, 39, 40, 41, 42, 43___ of 13
Business Practices30, 31, 32, 33, 34, 36___ of 6
Areas of Practice/Types of Surveys15, 16, 44, 45, 46, 47, 49, 50___ of 8
Legal Principles1, 2, 3, 5, 6, 7, 8___ of 7
Areas of Practice/Types of Surveys (Boundary Division)4, 9, 10, 11, 25, 37, 38, 48___ of 8

Read it with one caution. These 50 questions were allocated to the current specification, so under the July 2027 ranges they over-sample Standards and Specifications and under-sample Legal Principles. If you're testing after the change, give legal principles extra practice beyond this set.

What your score means

Your percentage describes how you did on these 50 questions. It isn't an NCEES score, and it doesn't predict a pass. NCEES counts your correct answers, converts the count to a scaled score to adjust for differences between exam forms, and doesn't publish the passing score. There's no deduction for wrong answers, and some questions on the real exam are unscored pretest items you can't identify (NCEES Examinee Guide, May 2026, pp. 11 and 14).

Each area here has 5 to 14 questions, so a miss points to a skill worth checking, not a measured weakness in the whole area. One rule carries straight to exam day: since wrong answers cost nothing, never leave a question blank.

Turn each miss into a fix

For every miss, and every lucky guess, write down the first step that went wrong. Fix that step, not the whole topic.

Turn each miss into a fix
What went wrongWhat to do nextYou've fixed it when
Picked the wrong evidence or ruleSay in one sentence which kind of evidence controls and why (monument, record, possession, proportion)You can explain why the rule you first chose doesn't apply to these facts
Used the wrong edition or documentCheck which standard and edition NCEES lists for your exam date, then find the provision in itYou can find it again in the supplied document in under two minutes
Sign, datum, or unit errorWrite every input with its unit and reference surface (ground, ellipsoid, grid; survey foot or international foot) before you calculateThe units cancel to exactly what the question asks for
Missed a condition in the stemUnderline the detail that controls: "original," "undisturbed," "first deeded," "no BFE," "unless"You can name the condition that changes the answer
Answered with a state-law habitSeparate the general principle from your state's statutes and casesYou can say what the general rule is and where your state differs
Too slowNote where the time went, then repeat the same method on a fresh problemThe same setup takes noticeably less time

A day later, rework each missed question cold. Then change one input and solve it again to check that you learned the method, not the answer.

What this practice test covers

NCEES publishes a question range for each knowledge area. We gave each area roughly half of its range. That's our editorial allocation, not an official weighting, and 50 questions can only sample each area.

What this practice test covers
Current NCEES knowledge areaNCEES questions (of 100)This test (of 50)Question numbers
Legal Principles18–27111–11
Professional Survey Practices22–331312–24
Standards and Specifications8–12525–29
Business Practices13–19730–36
Areas of Practice24–361437–50
Total10050

Source: NCEES PS CBT exam specifications, effective January 1, 2019, pp. 1–3.

The set has 24 single-answer questions, 22 numeric-entry questions, and 4 select-two questions. Numeric entry is heavy on purpose: it's the alternative item type candidates practice least. Standards questions are keyed to the editions NCEES supplies on the exam. Legal questions teach general common-law and federal principles. Where a principle depends on state law, the explanation says so.

Which specification matches your test date?

Your appointment date decides which specification applies. If you test before July 2027, use the current specification. If you test in July 2027 or later, use the new one.

Which specification matches your test date?
Exams before July 2027 (effective Jan. 1, 2019)Exams beginning July 2027
Legal Principles: 18–27Professional Survey Practices: 20–30
Professional Survey Practices: 22–33Standards and Specifications: 11–17
Standards and Specifications: 8–12Business Practices: 6–9
Business Practices: 13–19Areas of Practice/Types of Surveys: 10–15
Areas of Practice: 24–36Legal Principles: 23–35
—Areas of Practice/Types of Surveys (Boundary Division): 15–23

Sources: current specification and July 2027 specification.

Some things don't change. Both specifications describe a 100-question, computer-based exam with 7 hours of total time, closed book with an electronic reference, in U.S. Customary units. Both list the same supplied standards. What changes is the content organization. Boundary work becomes its own large division, legal principles grow, and business practices shrink.

Which ALTA/NSPS standards does the exam use?

The 2021 edition. Both the current and July 2027 PS specifications list the 2021 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys. NCEES scores standards-based questions against the editions on that list, and solutions based on other editions don't receive credit.

That matters because the 2026 ALTA/NSPS standards took effect February 23, 2026 for real-world surveys (ALTA, 2026 Minimum Standard Detail Requirements). If you do ALTA work, you may be using 2026 at the office and 2021 on the exam. Every ALTA question on this page is keyed to 2021.

The full supplied-standards list, the same in both specifications:

Which ALTA/NSPS standards does the exam use?
Supplied on the examEdition
ALTA/NSPS Minimum Standard Detail Requirements for Land Title Surveys2021
FEMA Elevation Certificate and Instructions2023
FGCS § 3.5, Geodetic Leveling (Specifications and Procedures to Incorporate Electronic Digital/Bar-Code Leveling Systems)2004
FGDC Geospatial Positioning Accuracy StandardsParts 1–3: 1998; Part 4: 2002; Part 5: 2005
United States National Map Accuracy Standards1947

Source: last page of each specification linked above. The NCEES PS Reference Handbook is also supplied.

Are these real NCEES questions?

No. Every question on this page is original and unofficial. We wrote each one from the published NCEES specifications and the source cited under it. None is a recalled, leaked, or reworded NCEES exam item. NCEES exams are confidential, and examinees agree not to disclose exam content (NCEES Examinee Guide, pp. 13 and 19).

How close is this to the real exam?

How close is this to the real exam?
Row labelNCEES PS examThis practice test
Questions10050
Time7-hour appointment: 2-minute nondisclosure agreement, 8-minute tutorial, 6 hours of exam time, and an optional 50-minute scheduled breakUntimed, or 180 minutes at exam pace
StructureTwo sections. After you submit the first half, you can't go back to itOne set; revisit anything
Question formatsMultiple choice plus alternative item types: multiple correct, point-and-click, drag-and-drop, and fill-in-the-blankSingle answer, numeric entry, select two, and ordering; no point-and-click
ReferencesNCEES PS Reference Handbook and the listed standards, on screen onlyWhatever you have; practicing with the handbook is better
UnitsU.S. CustomaryU.S. Customary, plus one question with metric geodetic inputs
ScoringCorrect answers converted to a scaled score; pass or fail; no partial credit; unscored pretest questionsOne point per question; a percentage
ResultsTypically 7–10 daysImmediately, with the answer key

The 50 questions in this set use three formats: 24 select-one, 22 enter-a-number, and 4 select-two. Ordering is not a separate exercise in this set.

Sources: NCEES PS exam page; NCEES Examinee Guide, May 2026, pp. 10–12, 14, 16; NCEES computer-based testing.

Practice with what you'll get on exam day

  • The handbook. Download the current NCEES PS Reference Handbook from your MyNCEES account. It's free, and it's the version you'll see on screen.
  • The standards. Get the five supplied documents above and practice finding provisions in them. On exam day the references open in a viewer with its own search box on the left. Ctrl+F doesn't work, and only one standard opens at a time.
  • The calculator. For 2026 exams, NCEES allows Casio fx-115 and fx-991 models, the HP 33s and 35s, and TI-30X and TI-36X models (NCEES calculator policy). A TI-30XS is also available on screen. NCEES reviews the list every year.
  • The screen. You'll test on a 24-inch monitor with the question and reference side by side, with reusable booklets and markers for scratch work.

Sources: NCEES Examinee Guide, May 2026, pp. 8–10; specifications linked above.

Where to go next

Sources and verification

The linked Penn State Elevation Factor lesson is currently unavailable. The complete ground-to-grid calculation remains shown in Question 15.

Last verified: October 12, 2026. We checked the exam format, timing, fee, scoring rules, both specifications, and the supplied-standards list against the NCEES documents below. We re-solved every numeric question in code and checked each standards question against the edition NCEES supplies. These questions haven't been statistically tested or reviewed by NCEES or a licensed surveyor, and source checking isn't professional surveying review.

NCEES

Standards supplied on the exam and used in the questions

Law and federal guidance used in the questions

The legal questions teach general principles. Your state's statutes and case law control actual boundary decisions.

By Castleport Test Prep Editorial Team. This page was developed with AI-assisted research, drafting, question development, and editing. See how Castleport uses sources and AI assistance and our editorial standards.

Castleport Test Prep is an independent exam prep publisher. It is not affiliated with, endorsed by, or approved by the National Council of Examiners for Engineering and Surveying (NCEES). Exam and credential names are used for identification, and trademarks belong to their respective owners. These practice questions are original and unofficial, and nothing on this page guarantees a passing result or a license.

Free NCEES PS Practice Test: 50 Questions With Solutions