These 85 original, unofficial practice questions match the NCEES PE Industrial and Systems exam's question count and cover all five current content areas, with multiple-choice and practice versions of several alternative item types. Each question has a worked explanation; source links are included when an answer depends on an external rule, standard, or technical reference.

Systems Engineering (Questions 1–17)

1. Lead time and process cycle efficiency on a value stream map

PEIS-T01 · Systems Engineering · 1A System analysis and design tools · Multiple choice

A three-step process has value-added times of 2, 5, and 3 minutes per unit. A value stream map shows 600 units waiting before step 2 and 300 units waiting before step 3. Customer demand is 150 units per working day, and the plant works 2 shifts × 8 hours. Convert each inventory to days of demand and express lead time in working minutes. What are the production lead time and the process cycle efficiency (value-added time ÷ production lead time)?

Show answer and solution

Answer: A. 6.0 days; 0.17%

Inventory in days of demand: 600 ÷ 150 = 4.0 days and 300 ÷ 150 = 2.0 days, so 6.0 working days of waiting.

One working day = 2 × 8 × 60 = 960 minutes. Lead time = 6.0 × 960 + 10 = 5,770 minutes (the 10 is the value-added time: 2 + 5 + 3).

Process cycle efficiency = 10 ÷ 5,770 = 0.17%.

Why the others miss:

  • B: Uses 24-hour calendar days (6 × 1,440 + 10 = 8,650 min). The stem asks for working minutes.
  • C: Counts only the 600-unit queue (4 × 960 + 10 = 3,850 min).
  • D: Uses one 8-hour shift per day (6 × 480 + 10 = 2,890 min).

If you missed it: Write the time basis next to every number before you divide. Most lead-time errors are a days-versus-minutes slip.

Source: Derived calculation; method and arithmetic shown above

2. Pareto analysis

PEIS-T02 · Systems Engineering · 1A System analysis and design tools · Multiple choice

A packaging line logged 300 defects last month: loose cap 12, scratches 120, other 8, dents 80, wrong color 30, misaligned label 50. Using a Pareto analysis, what is the fewest number of categories that together account for at least 80% of defects?

Show answer and solution

Answer: B. 3

Sort largest to smallest: scratches 120, dents 80, misaligned label 50, wrong color 30, loose cap 12, other 8.

Cumulative share: 120 ÷ 300 = 40.0%, then 200 ÷ 300 = 66.7%, then 250 ÷ 300 = 83.3% after three categories.

Why the others miss:

  • A: Two categories reach only 66.7%.
  • C: Adds wrong color after 80% is already reached (93.3%). The question asks for the fewest.
  • D: Accumulates in the order the categories were listed, without sorting first. That takes five categories to pass 80%.

If you missed it: A Pareto chart only works after you sort. Rank first, then accumulate.

Source: Derived calculation; method and arithmetic shown above

3. Name the group technique

PEIS-T03 · Systems Engineering · 1A System analysis and design tools · Multiple choice

A team leader asks eight people to write ideas silently for 10 minutes. Each person then shares one idea at a time in turn while the leader records them, with no discussion. The group clarifies each idea, removes duplicates, and then votes to rank the top ideas. Which technique is this?

Show answer and solution

Answer: A. Nominal group technique

Silent idea generation, round-robin sharing without discussion, clarification, and then voting to prioritize are the steps of the nominal group technique.

Why the others miss:

  • B: An affinity diagram organizes a large number of ideas into their natural groupings. It sorts ideas; it doesn't rank them by vote.
  • C: A Pareto analysis ranks categories by frequency or cost from data, not by a group vote.
  • D: Value stream mapping traces material and information flow through a process.

If you missed it: The silent-writing step plus a ranking vote is the signature of nominal group technique.

Source: NIATx, Nominal Group Technique Instructions (steps 1–4); ASQ, What is an affinity diagram?

4. House of quality technical importance

PEIS-T04 · Systems Engineering · 1B Requirements analysis (QFD) · Multiple choice

In a house of quality, customer requirements carry importance weights: short changeover 5, accurate picks 4, short operator training 2. Relationship scores (9 strong, 3 moderate, 1 weak, 0 none) for three technical characteristics are:

4. House of quality technical importance
Technical characteristicChangeoverAccuracyTraining
Quick-release fixtures903
Barcode verification193
Visual work instructions339

Technical importance = Σ (customer weight × relationship score). Which characteristic should get first priority?

Show answer and solution

Answer: A. Quick-release fixtures, 51

Quick-release fixtures: 5(9) + 4(0) + 2(3) = 45 + 0 + 6 = 51.

Barcode verification: 5(1) + 4(9) + 2(3) = 5 + 36 + 6 = 47.

Visual work instructions: 5(3) + 4(3) + 2(9) = 15 + 12 + 18 = 45.

Why the others miss:

  • B: Barcode verification's 47 is correct, but it is second.
  • C: 15 is the unweighted sum of relationship scores (3 + 3 + 9). Unweighted sums ignore what customers care about most.
  • D: Fixtures lead by 4 points. There is no tie.

If you missed it: Multiply each relationship by its row weight before adding down the column.

Source: Derived calculation; method and arithmetic shown above; ASQ, What is quality function deployment?

5. Functional requirements versus constraints

PEIS-T05 · Systems Engineering · 1B Requirements analysis · Select all that apply

For a new order-picking system, a functional requirement says what the system must do; a constraint limits how it can be done (space, budget, interfaces, regulations). Select all that are constraints.

Show answer and solution

Answer: A, C, and E

A (space), C (budget), and E (an interface the design must use) limit the solution space. They are constraints.

B and D describe what the system must do. They are functional requirements.

Why the other choices are wrong:

  • B: Scanning each pick is a function the system performs.
  • D: Printing a packing list is a function the system performs.

If you missed it: Ask whether the statement describes an action the system takes (functional) or a boundary on any design you could choose (constraint). All-or-nothing scoring: you need A, C, and E, and nothing else.

Source: Definitions supplied in the stem; classification follows directly from them

6. Overall equipment effectiveness

PEIS-T06 · Systems Engineering · 1C Performance measures and applications · Multiple choice

A 480-minute shift includes 30 minutes of scheduled breaks, so planned production time is 450 minutes. Unplanned downtime was 45 minutes. The ideal cycle time is 0.5 minute per unit. The line made 720 units, of which 684 were good. Using OEE = availability × performance × quality, what is the OEE?

Show answer and solution

Answer: A. 76.0%

Availability = run time ÷ planned time = (450 − 45) ÷ 450 = 405 ÷ 450 = 0.900.

Performance = (ideal cycle × total count) ÷ run time = (0.5 × 720) ÷ 405 = 0.889.

Quality = good ÷ total = 684 ÷ 720 = 0.950.

OEE = 0.900 × 0.889 × 0.950 = 0.760. Check: good units × ideal cycle ÷ planned time = 684 × 0.5 ÷ 450 = 0.760.

Why the others miss:

  • B: Averages the three factors instead of multiplying them.
  • C: Multiplies availability and performance but leaves out quality.
  • D: Uses the full 480-minute shift as planned time. Scheduled breaks aren't planned production time.

If you missed it: The shortcut check (good units × ideal cycle ÷ planned time) catches most OEE slips in seconds.

Source: Derived calculation; method and arithmetic shown above

7. Using a shadow price

PEIS-T07 · Systems Engineering · 1D Modeling techniques (linear programming) · Multiple choice

A product-mix LP maximizes profit. The sensitivity report shows the machine-hours constraint (≤ 400 hours) is binding with a shadow price of $12 per hour, an allowable increase of 50 hours, and an allowable decrease of 80 hours. Shadow prices here are based on the existing hourly cost already included in the model. Overtime would add 30 machine hours at an extra $8 per hour not in the model. What happens to total profit?

Show answer and solution

Answer: A. It rises by $120

30 extra hours is within the allowable increase of 50, so the $12 shadow price holds for every added hour.

Gain from the hours = 30 × $12 = $360. Extra overtime cost = 30 × $8 = $240.

Net change = $360 − $240 = +$120.

Why the others miss:

  • B: Counts the value of the hours but not the extra $8 per hour.
  • C: Counts the overtime cost but not the value the hours create.
  • D: Re-solving is needed only when the change goes past the allowable range. 30 hours is inside it.

If you missed it: A shadow price is valid only inside the allowable range, and it already reflects costs in the model. Subtract only the costs the model doesn't include.

Source: Derived calculation; method and arithmetic shown above

8. Two-server queue

PEIS-T08 · Systems Engineering · 1D Modeling techniques (queuing) · Fill in the blank

A tool crib has 2 attendants. Requests arrive as a Poisson process at 10 per hour, and each attendant serves exponentially at 6 per hour. Treat it as an M/M/2 queue. What is Lq, the average number of requests waiting? Enter to two decimals.

Show answer and solution

Answer: 3.79 requests (accepted: 3.77 to 3.8)

Offered load a = λ/μ = 10/6 = 1.667. Utilization ρ = λ/(2μ) = 10/12 = 0.833.

P₀ = [1 + a + a²/(2(1 − ρ))]⁻¹ = [1 + 1.667 + 2.778/0.333]⁻¹ = [1 + 1.667 + 8.333]⁻¹ = 1/11 = 0.0909.

Lq = P₀ a² ρ / [2! (1 − ρ)²] = 0.0909 × 2.778 × 0.833 ÷ (2 × 0.0278) = 3.79.

Wq = Lq/λ = 0.379 h, about 22.7 minutes.

Common wrong answers:

  • 4.17: Treats the crib as one fast server (M/M/1 with μ = 12/h). Two servers at 6/h aren't the same as one at 12/h, because one can sit idle while the other is busy.
  • 0.83: Reports utilization, not the queue length.

If you missed it: For multi-server queues, compute P₀ first; everything else follows from it.

Source: Derived calculation; method and arithmetic shown above

9. Shortest route through a network

PEIS-T09 · Systems Engineering · 1D Modeling techniques (graph theory and networks) · Multiple choice

A delivery network has these one-way links (minutes): S→A 4, S→B 2, A→C 3, B→C 6, B→D 1, D→C 6, C→T 2, D→T 9. What is the shortest time from S to T, and which route gives it?

Show answer and solution

Answer: A. 9 minutes via S–A–C–T

Label nodes from S (Dijkstra): B = 2, D = 2 + 1 = 3, A = 4, C = min(4 + 3, 2 + 6, 3 + 6) = 7, T = min(7 + 2, 3 + 9) = 9.

Trace back: T from C, C from A, A from S, so the route is S–A–C–T.

Why the others miss:

  • B: Follows the cheapest next link at every step (S→B, B→D, D→C, C→T). Greedy choices don't guarantee the shortest total.
  • C: A feasible route, but 1 minute longer.
  • D: A feasible route, but 3 minutes longer.

If you missed it: Keep a permanent label for each node and update neighbors before moving on. Don't commit to the cheapest single link.

Source: Derived calculation; method and arithmetic shown above

10. How many simulation replications?

PEIS-T10 · Systems Engineering · 1D Modeling techniques (simulation) · Multiple choice

Ten pilot replications of a clinic simulation give a standard deviation of 12 minutes for average patient wait. You want a 95% confidence interval with a half-width of ±3 minutes. Using z = 1.96 as a planning approximation, how many replications do you need?

Show answer and solution

Answer: A. 62

n = (z s / e)² = (1.96 × 12 / 3)² = (7.84)² = 61.5.

Round up to 62 so the half-width doesn't exceed ±3 minutes.

Why the others miss:

  • B: Rounds 61.5 down, which falls just short of the precision you asked for.
  • C: Forgets to square (7.84 rounded up).
  • D: Uses (s/e)² without the z value.

If you missed it: Sample-size results always round up.

Source: Derived calculation; method and arithmetic shown above

11. Continuous processes

PEIS-T11 · Systems Engineering · 1E Process types · Select all that apply

Here, a continuous process moves material without interruption, and output is measured by volume or weight rather than counted as separate units. Select all that are continuous processes.

Show answer and solution

Answer: A, C, and E

A, C, and E move material without interruption and measure output by volume or weight. They are continuous.

Why the other choices are wrong:

  • B: Discrete: separate, countable vehicles.
  • D: Batch: a fixed quantity is processed together, then the next load starts.
  • F: A service process. Patients are discrete arrivals, not a continuous flow of material.

If you missed it: Ask how output is counted. Units counted one by one means discrete; separate loads means batch.

Source: Definition supplied in the stem

12. Reading a tornado diagram

PEIS-T12 · Systems Engineering · 1F Model assessment (sensitivity analysis) · Multiple choice

A make-versus-buy model says Make beats Buy by $50,000 NPV at base values. A tornado diagram shows the range of that advantage as each input swings across its plausible range, one at a time:

12. Reading a tornado diagram
InputAdvantage of Make (low end to high end)
Material price+$2,000 to +$140,000
Demand volume−$20,000 to +$110,000
Labor rate+$30,000 to +$70,000
Scrap rate+$35,000 to +$62,000

Which single input could flip the decision to Buy within its plausible range?

Show answer and solution

Answer: A. Demand volume

The decision flips only if the Make advantage can fall below $0.

Only demand volume's range crosses zero (−$20,000 at its low end). So demand volume can flip the decision.

Why the others miss:

  • B: Material price has the widest bar, but its whole range stays positive. Width shows sensitivity, not whether the decision changes.
  • C: Labor rate's range stays well above zero.
  • D: Demand volume's range crosses zero.

If you missed it: On a tornado diagram, look for the bar that crosses the decision threshold, not just the longest bar.

Source: Derived calculation; method and arithmetic shown above

13. The five focusing steps

PEIS-T13 · Systems Engineering · 1G Bottleneck analysis (theory of constraints) · Drag and drop: order

Put the theory of constraints five focusing steps in order, first to last.

P. Elevate the constraint

Q. Identify the system's constraint

R. Prevent inertia from becoming the constraint (start again)

S. Subordinate everything else to the constraint

T. Exploit the constraint

Choose the item for each position, first to last

Show answer and solution

Answer: Q → T → S → P → R

Identify → Exploit → Subordinate → Elevate → Prevent inertia, then repeat.

Exploit (get the most from the constraint you already have) comes before Elevate (adding capacity), because the cheapest improvement is usually using the constraint better.

If you missed it: Exploit and subordinate cost little; elevate usually costs money. That's why elevate comes fourth. Drag-and-drop ordering is scored all-or-nothing.

Source: TOC Institute, The Five Focusing Steps

14. Effective bottleneck with scrap

PEIS-T14 · Systems Engineering · 1G Bottleneck analysis · Multiple choice

A three-station line has capacities of 60, 50, and 55 units per hour. Inspection right after Station 1 scraps 20% of the units Station 1 processes. Station 1 always runs at full capacity. What is the line's maximum output of good units per hour?

Show answer and solution

Answer: A. 48

Good units leaving Station 1 = 60 × 0.80 = 48 per hour.

Station 2 could handle 50 but only receives 48, and Station 3 can handle 55. Output = 48 good units per hour. Station 1 plus its scrap loss is the real constraint.

Why the others miss:

  • B: Station 2's nominal capacity. It never gets 50 units an hour to work on.
  • C: Applies the 20% scrap to Station 2's capacity instead of to Station 1's output.
  • D: Station 3 is the second-fastest station, not the limit.

If you missed it: Convert every station to good-unit capacity at the same point in the flow before you pick the bottleneck.

Source: Derived calculation; method and arithmetic shown above

15. Value index

PEIS-T15 · Systems Engineering · 1H Value analysis and engineering · Multiple choice

A value engineering team lists component cost and worth (the lowest cost that would reliably perform the component's function). The team ranks opportunities by value index = worth ÷ cost, lowest first.

15. Value index
ComponentCostWorth
Motor$40$32
Housing$18$13
Gasket$9$3
Fastener kit$6$5

Which component should the team study first?

Show answer and solution

Answer: A. Gasket

Value indexes: motor 0.80, housing 0.72, gasket 0.33, fastener kit 0.83.

The gasket costs three times what its function is worth, so it ranks first.

Why the others miss:

  • B: The motor has the largest dollar gap ($8) but a value index of 0.80. The team ranks by index, not by dollars.
  • C: 0.72 is the second-lowest index.
  • D: 0.83 is the highest index, closest to good value.

If you missed it: Value engineering targets cost that buys no essential function. A low worth-to-cost ratio flags that waste.

Source: Derived calculation; method and arithmetic shown above; FAR 48.101(a), value engineering

16. Crash the schedule by 2 days

PEIS-T16 · Systems Engineering · 1I Project management and planning (CPM) · Multiple choice

Activities (normal duration; crash cost per day; maximum days of crashing): A 4 d, $500/d, 1 d; B 5 d, $300/d, 2 d; C 5 d, $200/d, 1 d, follows A; D 3 d, $400/d, 1 d, follows B; E 2 d, $600/d, 1 d, follows C and D. What is the minimum crash cost to cut the project by 2 days?

Show answer and solution

Answer: A. $800

Paths: A–C–E = 11 days (critical) and B–D–E = 10 days. Target 9 days.

Day 1: crash C, the cheapest critical activity ($200). Now both paths are 10 days.

Day 2: both paths must drop. E is on both, at $600; the cheapest pair is A + B at $800. Crash E.

Total = $200 + $600 = $800.

Why the others miss:

  • B: Crashes C twice. C can only be crashed 1 day.
  • C: Crashes C and then A. That shortens A–C–E to 9 days, but B–D–E is still 10, so the project only drops 1 day.
  • D: Crashes E and A. That works, but costs $300 more than crashing C and E.

If you missed it: After every day of crashing, recheck which paths are critical. A second path often joins the critical set.

Source: Derived calculation; method and arithmetic shown above

17. Earned value

PEIS-T17 · Systems Engineering · 1I Project management and planning (cost and time) · Multiple choice

At week 10, a project shows planned value (PV) $160,000, earned value (EV) $140,000, and actual cost (AC) $175,000. What are the cost performance index (CPI) and schedule performance index (SPI), and what do they say?

Show answer and solution

Answer: A. CPI 0.80, SPI 0.875: over budget and behind schedule

CPI = EV ÷ AC = 140,000 ÷ 175,000 = 0.80. Below 1.0 means the work done cost more than planned.

SPI = EV ÷ PV = 140,000 ÷ 160,000 = 0.875. Below 1.0 means less work was done than planned.

Why the others miss:

  • B: Inverts both ratios (AC ÷ EV and PV ÷ EV).
  • C: Swaps the two indices.
  • D: Computes 'CPI' as PV ÷ AC. Earned value, not planned value, goes in both numerators.

If you missed it: EV is in the numerator of both indices. Cost compares to actual cost; schedule compares to planned value.

Source: CDC Unified Process, Earned Value Practices Guide, p. 2 (CPI = EV/AC, SPI = EV/PV) (source link unavailable)

Facilities Engineering and Planning (Questions 18–34)

18. Flow-distance for two layouts

PEIS-T18 · Facilities Engineering and Planning · 2A Process flow (from-to analysis) · Multiple choice

Daily loads between three departments: A→B 30, A→C 10, B→C 25, C→A 5. Distances (ft):

18. Flow-distance for two layouts
PairLayout 1Layout 2
A–B50100
A–C10050
B–C5050

Which layout has the lower total load-distance, and what is it?

Show answer and solution

Answer: A. Layout 1, 4,250 load-ft per day

Layout 1: 30(50) + 10(100) + 25(50) + 5(100) = 1,500 + 1,000 + 1,250 + 500 = 4,250.

Layout 2: 30(100) + 10(50) + 25(50) + 5(50) = 3,000 + 500 + 1,250 + 250 = 5,000.

Why the others miss:

  • B: Layout 2's total is correct, but it is higher.
  • C: Adds distances without weighting them by flow.
  • D: Leaves out the C→A backflow of 5 loads.

If you missed it: Every flow, in both directions, gets multiplied by its distance.

Source: Derived calculation; method and arithmetic shown above

The cited CDC earned-value guide is currently unavailable at its original address. The equations and calculations are shown in the worked solution above.

19. Match costs to life-cycle phases

PEIS-T19 · Facilities Engineering and Planning · 2H Facility life cycle cost analysis · Drag and drop: match

Match each cost for a new automated storage system to the life-cycle phase it belongs to.

  1. Purchase price of the storage and retrieval equipment
  2. Installation, commissioning, and initial operator training
  3. Annual maintenance contract and spare parts
  4. Decommissioning and removal at end of service

Options:

  • a. Acquisition
  • b. Implementation
  • c. Sustainment
  • d. Retirement
Match each numbered item to a lettered option

Show answer and solution

Answer: 1 → a, 2 → b, 3 → c, 4 → d

Buying the equipment is acquisition; getting it running and staff trained is implementation; keeping it running year after year is sustainment; taking it out of service is retirement.

If you missed it: Life-cycle cost analysis exists because the purchase price is only one of the four phases. Matching items are scored all-or-nothing.

Source: Phase names from the NCEES specification, item 2H

20. Score a block layout

PEIS-T20 · Facilities Engineering and Planning · 2B Layout design techniques (relationship diagrams) · Multiple choice

Four equal-size departments go in a 2 × 2 block layout. Departments that share a side are adjacent; diagonal departments are not. Closeness ratings are scored A = 16, E = 8, I = 4, O = 2, U = 0, X = −32. Ratings: Receiving–Stores A; Stores–Machining E; Stores–Office I; Receiving–Machining O; Receiving–Office U; Machining–Office X. Score each layout by adding the scores of adjacent pairs. Which layout scores highest?

20. Score a block layout
LayoutTop rowBottom row
1Receiving, StoresMachining, Office
2Machining, StoresReceiving, Office
3Stores, MachiningReceiving, Office

Show answer and solution

Answer: B. Layout 2, score 14

Layout 1 adjacencies: Receiving–Stores 16, Machining–Office −32, Receiving–Machining 2, Stores–Office 4 → −10.

Layout 2 adjacencies: Machining–Stores 8, Receiving–Office 0, Machining–Receiving 2, Stores–Office 4 → 14.

Layout 3 adjacencies: Stores–Machining 8, Receiving–Office 0, Stores–Receiving 16, Machining–Office −32 → −8.

In a 2 × 2 block, keeping Machining and Office apart forces them onto a diagonal, which puts Receiving and Stores on the other diagonal. Giving up the A pair beats paying the X penalty.

Why the others miss:

  • A: Layout 1 gets the A pair but also puts the X pair side by side.
  • C: Layout 3 also puts the X pair side by side.
  • D: Layout 3 also puts the A pair side by side, so the premise is false. And an A adjacency earns 16 points while an X adjacency costs 32; the total score decides, not the single best pair.

If you missed it: Check the X pairs first. An undesirable adjacency usually costs more than any single good one earns.

Source: Derived calculation; method and arithmetic shown above

21. Rectilinear location

PEIS-T21 · Facilities Engineering and Planning · 2B Layout design techniques (single-facility location) · Multiple choice

A tool crib will serve four work centers. Travel follows rectilinear aisles. Locations (x, y in hundreds of feet) and daily trips: W1 (1, 5) 4 trips; W2 (4, 1) 5 trips; W3 (7, 6) 2 trips; W4 (9, 3) 3 trips. Where should the crib go to minimize total weighted rectilinear distance?

Show answer and solution

Answer: A. (4, 3)

For rectilinear distance, use the weighted median of each coordinate. Total weight = 14, so the median is where cumulative weight first reaches more than 7.

x sorted: 1 (4), 4 (cumulative 9) → x = 4.

y sorted: 1 (5), 3 (cumulative 8) → y = 3.

Optimal location: (4, 3).

Why the others miss:

  • B: The weighted center of gravity. It is a reasonable start for straight-line travel, but it doesn't minimize rectilinear distance.
  • C: The unweighted average of the coordinates.
  • D: Swaps x and y.

If you missed it: Rectilinear plus weights means weighted median, solved separately for x and y.

Source: Derived calculation; method and arithmetic shown above

22. Rack positions with a utilization allowance

PEIS-T22 · Facilities Engineering and Planning · 2C Space analysis (warehousing) · Fill in the blank

A randomized-storage warehouse must hold a peak of 1,800 pallets at once. Because of honeycombing and slotting losses, you plan for 85% of rack positions to be filled at peak. How many rack positions are needed? Enter a whole number.

Show answer and solution

Answer: 2,118 positions

Positions = 1,800 ÷ 0.85 = 2,117.6.

Round up: 2,118 positions.

Common wrong answers:

  • 1530: Multiplies by 0.85 instead of dividing. Planning for partial fill needs more positions than pallets, not fewer.
  • 2117: Rounds down and leaves the plan short by a fraction of a position.

If you missed it: A utilization factor below 1 always increases the space you need.

Source: Derived calculation; method and arithmetic shown above

23. Size a buffer with Little's law

PEIS-T23 · Facilities Engineering and Planning · 2C Space analysis (WIP sizing) · Multiple choice

Parts leave a paint line at 90 per hour and must sit in a cure buffer for an average of 40 minutes. Each cure rack holds 12 parts and takes 18 ft² of floor. How much floor space does the buffer need?

Show answer and solution

Answer: A. 90 ft²

Little's law: WIP = throughput × time in system = 90 parts/h × (40/60) h = 60 parts.

Racks = 60 ÷ 12 = 5. Floor space = 5 × 18 = 90 ft².

Why the others miss:

  • B: Multiplies 90 parts per hour by 40 minutes without converting minutes to hours.
  • C: Gives every part its own 18 ft² instead of 12 parts per rack.
  • D: Reports the WIP count (60 parts) as square feet.

If you missed it: Match the time units in Little's law before multiplying.

Source: Derived calculation; method and arithmetic shown above

24. Operators needed

PEIS-T24 · Facilities Engineering and Planning · 2D Capacity analysis (personnel requirements) · Multiple choice

A cell must ship 4,200 good units per week. The process scraps 5% of units started. Standard time is 6 minutes per unit started. Operators work 40 hours per week at 90% efficiency, and absenteeism averages 8%. How many operators should be staffed?

Show answer and solution

Answer: A. 14

Units to start = 4,200 ÷ 0.95 = 4,421.1. Hours needed = 4,421.1 × 6 ÷ 60 = 442.1 h.

Effective hours per operator present = 40 × 0.90 = 36 h. Operators present = 442.1 ÷ 36 = 12.28.

Staff for absenteeism: 12.28 ÷ (1 − 0.08) = 13.35. Round up to 14.

Why the others miss:

  • B: Rounds up 12.28 but forgets absenteeism.
  • C: Rounds 12.28 down and forgets absenteeism.
  • D: Multiplies by the 90% efficiency instead of dividing by it.

If you missed it: Scrap, efficiency, and absenteeism all push the requirement up. If an adjustment lowers your answer, its direction is wrong.

Source: Derived calculation; method and arithmetic shown above

25. Machines needed with setups

PEIS-T25 · Facilities Engineering and Planning · 2D Capacity analysis (machine requirements) · Multiple choice

A part family runs in 50 batches per week of 120 units each. Each batch needs a 45-minute setup, and run time is 2.5 minutes per unit. Each machine is scheduled 80 hours per week and is available 85% of that time. How many machines are required?

Show answer and solution

Answer: A. 5

Load = 50 × (45 + 120 × 2.5) = 50 × 345 = 17,250 min = 287.5 h.

Capacity per machine = 80 × 0.85 = 68 h. Machines = 287.5 ÷ 68 = 4.23. Round up: 5.

Why the others miss:

  • B: Either ignores setups (250 h ÷ 68 = 3.68 → 4) or rounds 4.23 down.
  • C: Ignores setups and availability (250 ÷ 80 = 3.1) and rounds down.
  • D: Uses 40 available hours instead of 80 (287.5 ÷ 34 = 8.46 → 9).

If you missed it: Setup time is real machine time. Add it per batch, not per unit.

Source: Derived calculation; method and arithmetic shown above

26. Benefit-cost ratio with disbenefits

PEIS-T26 · Facilities Engineering and Planning · 2E Cost-benefit analysis · Multiple choice

A plant road improvement has equivalent annual benefits of $180,000, annual disbenefits (lost parking during peak hours) of $30,000, and an equivalent annual cost of $100,000. Using the conventional B/C ratio, which subtracts disbenefits from benefits, what is the ratio and is the project justified?

Show answer and solution

Answer: A. 1.50; justified

Conventional B/C = (benefits − disbenefits) ÷ costs = (180,000 − 30,000) ÷ 100,000 = 1.50.

B/C > 1.0, so the project is justified.

Why the others miss:

  • B: Adds disbenefits to costs (180 ÷ 130). That's a different ratio from the one asked for, even though the decision happens to match here.
  • C: Ignores the disbenefits.
  • D: Inverts the ratio (cost ÷ net benefit).

If you missed it: Read which convention the question names. The decision often matches across conventions, but the number doesn't.

Source: Derived calculation; method and arithmetic shown above

27. Factor rating with a must-have

PEIS-T27 · Facilities Engineering and Planning · 2F Site selection factors and methods · Multiple choice

Three sites are scored 0–100 on labor (weight 0.5), operating cost (0.3), and highway access (0.2). Rail access is a must-have; Site R has no rail. Scores: P (80, 70, 85); Q (70, 80, 75); R (90, 85, 75). Which site should be selected?

Show answer and solution

Answer: B. Site P, 78

Screen first: R fails the rail must-have and is out.

P: 0.5(80) + 0.3(70) + 0.2(85) = 40 + 21 + 17 = 78. Q: 35 + 24 + 15 = 74.

Choose Site P.

Why the others miss:

  • A: R scores highest (85.5) but fails a must-have, so its score doesn't matter.
  • C: Q's 74 is correct but lower than P's 78.
  • D: Adds R's unweighted scores, and R is still disqualified.

If you missed it: Apply knockout criteria before you weight and score anything.

Source: Derived calculation; method and arithmetic shown above

28. Least-cost shipping plan

PEIS-T28 · Facilities Engineering and Planning · 2F Site selection (network optimization) · Multiple choice

DC1 can ship 60 units per week and DC2 can ship 40. Customers need C1 30, C2 45, and C3 25. Shipping cost per unit:

28. Least-cost shipping plan
FromC1C2C3
DC1$4$6$3
DC2$3$5$7

What is the minimum total weekly shipping cost that meets all demand within DC capacities?

Show answer and solution

Answer: A. $425

Optimal plan: DC1 → C2 35 and C3 25; DC2 → C1 30 and C2 10.

Cost = 35(6) + 25(3) + 30(3) + 10(5) = 210 + 75 + 90 + 50 = $425.

Why it's optimal: each customer's cheaper source is used up to that DC's capacity. DC2 is $1 cheaper than DC1 for both C1 and C2, but $4 more expensive for C3, so DC2's 40 units go to C1 and C2.

Why the others miss:

  • B: The northwest-corner starting plan (DC1 → C1 30, C2 30; DC2 → C2 15, C3 25). It's feasible but not optimized.
  • C: Sends each customer's full demand from its cheapest DC, which needs 75 units from DC2. DC2 can only ship 40.
  • D: A feasible plan (DC1 → C2 45, C3 15; DC2 → C1 30, C3 10) that sends 10 units on the expensive DC2→C3 lane.

If you missed it: A starting solution isn't an optimal one. Check whether shifting units between lanes lowers cost.

Source: Derived calculation; method and arithmetic shown above

29. Pallets per trailer

PEIS-T29 · Facilities Engineering and Planning · 2G Unit load analysis · Fill in the blank

A trailer is 52 ft long inside and 100 in wide. Pallets are 48 in × 40 in, floor-loaded single-high in any orientation, and each loaded pallet weighs 1,750 lb. The legal payload is 44,000 lb. How many pallets can one trailer carry? Enter a whole number.

Show answer and solution

Answer: 25 pallets

Floor space: turn the 48 in side across the width (48 + 48 = 96 in ≤ 100 in), so 2 pallets per row. Rows = 624 in ÷ 40 in = 15.6 → 15 rows → 30 pallets.

Weight: 44,000 ÷ 1,750 = 25.1 → 25 pallets.

Weight governs: 25 pallets.

Common wrong answers:

  • 30: Checks floor space only. Weight runs out first.
  • 26: Uses the other orientation for floor space and ignores weight.

If you missed it: A unit-load plan checks both cube and weight. The smaller limit wins.

Source: Derived calculation; method and arithmetic shown above

30. Present worth of life-cycle cost

PEIS-T30 · Facilities Engineering and Planning · 2H Facility life cycle cost analysis · Multiple choice

Two conveyor systems each serve 8 years; interest is 10% per year. System X: acquisition $220,000 and implementation $30,000 now, sustainment $18,000 per year, retirement cost $40,000 at year 8. System Y: acquisition $180,000 and implementation $25,000 now, sustainment $28,000 per year, retirement cost $5,000 at year 8. Which has the lower present worth of cost? Use (P/A, 10%, 8) = 5.3349 and (P/F, 10%, 8) = 0.4665.

Show answer and solution

Answer: A. Y, about $356,700

X: 250,000 + 18,000(5.3349) + 40,000(0.4665) = 250,000 + 96,028 + 18,660 = $364,700.

Y: 205,000 + 28,000(5.3349) + 5,000(0.4665) = 205,000 + 149,377 + 2,333 = $356,700.

Y costs about $8,000 less in present worth.

Why the others miss:

  • B: Leaves out X's retirement cost. Dropping that one phase reverses the decision.
  • C: X's present worth is correct, but it is the higher of the two.
  • D: Adds the cash flows without discounting. They happen to tie undiscounted, which shows why timing matters.

If you missed it: Include all four life-cycle phases, and discount each to the same point in time.

Source: Derived calculation; method and arithmetic shown above

31. Screen handling equipment

PEIS-T31 · Facilities Engineering and Planning · 2I Material handling techniques and equipment · Select all that apply

A new rack area needs a truck that can lift a 3,000 lb load to 20 ft in 10 ft aisles. Rated specifications at the required load center:

31. Screen handling equipment
TruckRated capacityMaximum lift heightMinimum aisle
A. Counterbalanced forklift4,000 lb18 ft12 ft
B. Reach truck3,500 lb30 ft9 ft
C. Powered pallet jack5,000 lb0.5 ft6 ft
D. Turret truck3,000 lb40 ft6 ft
E. Walkie stacker2,500 lb16 ft7 ft

Select all trucks that meet every requirement.

Show answer and solution

Answer: B and D

Each truck must pass three checks: capacity ≥ 3,000 lb, lift ≥ 20 ft, aisle ≤ 10 ft.

B passes all three. D passes all three (3,000 lb meets 3,000 lb exactly).

Why the other choices are wrong:

  • A: Lifts only 18 ft and needs a 12 ft aisle.
  • C: Doesn't lift to rack height.
  • E: Capacity 2,500 lb and lift 16 ft are both short.

If you missed it: Screen every option against every requirement. One failure is enough to drop it.

Source: Derived calculation; method and arithmetic shown above

32. How many AGVs?

PEIS-T32 · Facilities Engineering and Planning · 2I Material handling (fleet sizing) · Multiple choice

An AGV system must make 120 deliveries per hour. Each delivery travels 300 ft loaded and 300 ft empty back, at 200 ft/min, and needs 1.0 minute for load and unload. Traffic, charging, and blocking leave each vehicle 85% of each hour for work. How many AGVs are needed?

Show answer and solution

Answer: A. 10

Time per delivery = 300/200 + 300/200 + 1.0 = 1.5 + 1.5 + 1.0 = 4.0 min.

Vehicle-minutes needed per hour = 120 × 4.0 = 480. Each AGV supplies 60 × 0.85 = 51.

480 ÷ 51 = 9.41. Round up: 10 AGVs.

Why the others miss:

  • B: Leaves out the empty return trip (2.5 min per delivery).
  • C: Ignores the 85% factor (480 ÷ 60).
  • D: Rounds 9.41 down.

If you missed it: Every loaded trip has an empty trip back unless the stem says vehicles chain jobs.

Source: Derived calculation; method and arithmetic shown above

33. Inspection time with a rework loop

PEIS-T33 · Facilities Engineering and Planning · 2A Process flow (rework loops) · Multiple choice

Each unit is inspected for 3 minutes. 20% of inspections fail; a failed unit is reworked and inspected again, and each inspection is independent with the same 20% failure rate. What is the expected inspection time per good unit?

Show answer and solution

Answer: A. 3.75 min

Expected inspections per good unit = 1 ÷ (1 − 0.20) = 1.25 (a geometric series: 1 + 0.2 + 0.2² + …).

Expected inspection time = 1.25 × 3 = 3.75 min.

Why the others miss:

  • B: Adds one round of rework (1.2 inspections) but ignores units that fail a second time.
  • C: Ignores rework entirely.
  • D: Divides by the failure rate instead of the pass rate.

If you missed it: With repeated independent trials until success, expected trials = 1 ÷ (probability of success).

Source: Derived calculation; method and arithmetic shown above

34. Locational break-even

PEIS-T34 · Facilities Engineering and Planning · 2F Site selection (cost-volume analysis) · Multiple choice

Site 1 has fixed costs of $300,000 per year and variable cost of $12 per unit. Site 2 has fixed costs of $500,000 per year and $8 per unit. Expected volume is 40,000 units per year. Which site is cheaper at that volume, and at what volume do the two cost the same?

Show answer and solution

Answer: A. Site 1; 50,000 units

At 40,000 units: Site 1 = 300,000 + 12(40,000) = $780,000; Site 2 = 500,000 + 8(40,000) = $820,000. Site 1 is cheaper.

Break-even: 300,000 + 12Q = 500,000 + 8Q → 4Q = 200,000 → Q = 50,000 units. Above that, Site 2's lower variable cost wins.

Why the others miss:

  • B: Correct crossover, but Site 2 is cheaper only above 50,000 units.
  • C: Divides the fixed-cost difference by Site 2's variable cost ($8) instead of the variable-cost difference ($4).
  • D: Divides the fixed-cost difference by Site 1's variable cost ($12).

If you missed it: Crossover volume = difference in fixed cost ÷ difference in variable cost.

Source: Derived calculation; method and arithmetic shown above

Operations Engineering (Questions 35–51)

35. Tracking signal

PEIS-T35 · Operations Engineering · 3A Forecasting methods (forecast control) · Multiple choice

Over six periods, forecast errors (actual − forecast) were +12, +8, −4, +10, +6, +9. The planner investigates when the tracking signal (running sum of forecast errors ÷ MAD) falls outside ±4. What does the tracking signal show?

Show answer and solution

Answer: A. About 5.0; outside the limits, and the forecast runs too low

Running sum of errors = 12 + 8 − 4 + 10 + 6 + 9 = 41.

MAD = (12 + 8 + 4 + 10 + 6 + 9) ÷ 6 = 49 ÷ 6 = 8.17.

Tracking signal = 41 ÷ 8.17 = 5.0, outside ±4.

Errors are actual − forecast and mostly positive, so actual demand keeps beating the forecast: the forecast runs too low.

Why the others miss:

  • B: Right value, wrong direction. Positive actual − forecast errors mean the forecast is too low.
  • C: Divides by the sum of absolute errors (49) instead of their average.
  • D: Reports the running sum as the tracking signal.

If you missed it: Check how the error is defined before reading the sign.

Source: Derived calculation; method and arithmetic shown above

36. Least-squares trend

PEIS-T36 · Operations Engineering · 3A Forecasting methods (time series) · Multiple choice

Demand for periods 1 through 5 was 20, 24, 27, 33, and 36 units. Fit a least-squares linear trend and forecast period 6.

Show answer and solution

Answer: A. 40.3

t̄ = 3, ȳ = 28. Deviations of t: −2, −1, 0, 1, 2. Deviations of y: −8, −4, −1, 5, 8.

Slope b = Σ(t − t̄)(y − ȳ) ÷ Σ(t − t̄)² = (16 + 4 + 0 + 5 + 16) ÷ 10 = 4.1.

Intercept a = 28 − 4.1(3) = 15.7. Forecast for period 6 = 15.7 + 4.1(6) = 40.3.

Why the others miss:

  • B: Extends the average change from first to last period ((36 − 20) ÷ 4 = 4 per period). That isn't least squares.
  • C: The mean of the data, with no trend.
  • D: Forecasts period 7 instead of period 6.

If you missed it: Center the time index first; the arithmetic gets much shorter.

Source: Derived calculation; method and arithmetic shown above

37. Apply a seasonal index

PEIS-T37 · Operations Engineering · 3A Forecasting methods (seasonality) · Fill in the blank

A trend model forecasts deseasonalized demand of 1,250 units for next year's third quarter. The third-quarter seasonal index is 1.16. What is the seasonalized forecast? Enter a whole number of units.

Show answer and solution

Answer: 1,450 units

Seasonalized forecast = deseasonalized forecast × seasonal index = 1,250 × 1.16 = 1,450 units.

Common wrong answers:

  • 1078: Divides by the index. You divide to remove seasonality from data, and multiply to put it back into a forecast.

If you missed it: An index above 1 means a stronger-than-average season, so the forecast should rise.

Source: Derived calculation; method and arithmetic shown above

38. Level versus chase

PEIS-T38 · Operations Engineering · 3B Production planning methods (aggregate planning) · Multiple choice

Demand for the next four months is 600, 1,000, 1,400, and 1,000 units. Each worker makes 20 units per month. The plant starts with 50 workers and zero inventory and must end with zero inventory; no shortages are allowed. Hiring costs $1,000 per worker, a layoff costs $1,500 per worker, and holding costs $5 per unit on each month's ending inventory. Compare a level plan (constant 50 workers) with a chase plan (workforce matches each month's demand). Which is cheaper, and what are the two plans' costs?

Show answer and solution

Answer: A. Level; $4,000 vs. chase $100,000

Level: 50 workers make 1,000 units each month. Ending inventory: 400, 400, 0, 0. Holding = (400 + 400) × $5 = $4,000. No hires or layoffs.

Chase: workers needed 30, 50, 70, 50. Changes from 50: lay off 20, hire 20, hire 20, lay off 20. Cost = 40 × $1,000 + 40 × $1,500 = $100,000.

The level plan is cheaper by $96,000.

Why the others miss:

  • B: Counts the chase plan's zero inventory but leaves out its hiring and layoff costs.
  • C: Counts the chase plan's hiring but not its layoffs.
  • D: Counts the chase plan's layoffs but not its hiring.

If you missed it: List every cost the plan triggers each month before comparing totals.

Source: Derived calculation; method and arithmetic shown above

39. MRP planned order release

PEIS-T39 · Operations Engineering · 3B Production planning methods (materials planning) · Multiple choice

An item has a gross requirement of 300 units in week 5 and no other requirements before then. On hand now: 80 units. A scheduled receipt of 50 units arrives in week 4. Safety stock is zero, lot sizing is lot-for-lot, and lead time is 2 weeks. What planned order release does MRP produce?

Show answer and solution

Answer: A. 170 units in week 3

Net requirement in week 5 = 300 − 80 on hand − 50 scheduled receipt = 170.

Lot-for-lot orders exactly 170. Offset by the 2-week lead time: release 170 units in week 3.

Why the others miss:

  • B: Places the order in the week it's needed, with no lead-time offset.
  • C: Ignores the scheduled receipt.
  • D: Ignores the on-hand inventory.

If you missed it: Net first (subtract on hand and scheduled receipts), then size the lot, then offset by lead time.

Source: Derived calculation; method and arithmetic shown above

40. Economic production quantity

PEIS-T40 · Operations Engineering · 3B Production planning methods (lot sizing) · Multiple choice

A part is used at 24,000 units per year and produced in-house at a rate of 60,000 units per year. Setup costs $400 per run, and holding costs $6 per unit per year. What is the economic production quantity?

Show answer and solution

Answer: A. 2,309 units

EPQ = √[2DS ÷ (H(1 − D/P))] = √[2(24,000)(400) ÷ (6 × (1 − 0.4))] = √(19,200,000 ÷ 3.6) = √5,333,333 = 2,309 units.

Because inventory builds gradually while production runs, average inventory is lower than with instant delivery, so the lot is larger than the EOQ.

Why the others miss:

  • B: The basic EOQ, which assumes the whole lot arrives at once.
  • C: Multiplies by (1 − D/P) instead of dividing.
  • D: Drops the 2 under the square root.

If you missed it: When production feeds inventory at a finite rate, maximum inventory is Q(1 − D/P), not Q.

Source: Derived calculation; method and arithmetic shown above

41. Incremental rate of return

PEIS-T41 · Operations Engineering · 3C Engineering economics (rate of return) · Multiple choice

Two mutually exclusive projects last 5 years with no salvage value. X costs $100,000 and returns $30,000 per year. Y costs $160,000 and returns $46,500 per year. MARR is 10%. Which should you choose?

Show answer and solution

Answer: A. Y, because the incremental investment earns about 11.6%, above the MARR

Both projects beat 10% alone: IRR(X) ≈ 15.2%, IRR(Y) ≈ 13.9%.

Increment Y − X: $60,000 now for $16,500 per year. (P/A, i, 5) = 60,000 ÷ 16,500 = 3.636, so i ≈ 11.6%. That beats 10%, so the extra $60,000 is worth spending. Choose Y.

Check with present worth at 10%: X = 30,000(3.7908) − 100,000 = $13,724; Y = 46,500(3.7908) − 160,000 = $16,272. Y is higher.

Why the others miss:

  • B: Picking the higher IRR ignores scale. The question is whether the extra investment earns the MARR.
  • C: The incremental return (11.6%) is above the MARR, not below it.
  • D: There's no 20% hurdle; the MARR is 10%.

If you missed it: For mutually exclusive choices, compare by incremental ROR or by present worth, never by ranking IRRs.

Source: Derived calculation; method and arithmetic shown above

42. Equivalent annual cost with unequal lives

PEIS-T42 · Operations Engineering · 3C Engineering economics (unequal lives) · Multiple choice

Machine A costs $40,000, lasts 4 years, and costs $8,000 per year to run. Machine B costs $70,000, lasts 8 years, and costs $6,000 per year. Neither has salvage value; the service is needed indefinitely and each machine would be replaced in kind. At 8% interest, which is cheaper? Use (A/P, 8%, 4) = 0.30192 and (A/P, 8%, 8) = 0.17401.

Show answer and solution

Answer: A. B, about $18,180 per year

A: 40,000(0.30192) + 8,000 = $20,077 per year.

B: 70,000(0.17401) + 6,000 = $18,181 per year. B is cheaper by about $1,900 per year.

Why the others miss:

  • B: Compares present worths over different lives. A's present worth covers only 4 years of service; B's covers 8.
  • C: First cost alone ignores operating cost and how long each machine lasts.
  • D: Spreads B's first cost with no interest (70,000 ÷ 8 + 6,000).

If you missed it: With repeatable unequal lives, compare annual worth, or use a common multiple of the lives.

Source: Derived calculation; method and arithmetic shown above

43. ABC overhead per unit

PEIS-T43 · Operations Engineering · 3D Costing systems (activity-based costing) · Fill in the blank

A plant's overhead pools are setups $120,000 (300 setups), inspections $90,000 (1,500 inspections), and machining $200,000 (10,000 machine hours). Low-volume product L made 500 units using 30 setups, 200 inspections, and 400 machine hours. What is L's activity-based overhead per unit? Enter dollars to two decimals.

Show answer and solution

Answer: 64.0 $ per unit

Activity rates: $400 per setup, $60 per inspection, $20 per machine hour.

L's overhead = 30(400) + 200(60) + 400(20) = 12,000 + 12,000 + 8,000 = $32,000.

Per unit = 32,000 ÷ 500 = $64.00.

Common wrong answers:

  • 32.80: Spreads all $410,000 of overhead on machine hours alone ($41 per hour × 400 ÷ 500). That's the traditional allocation, not ABC.

If you missed it: ABC charges each product for the activities it actually uses. Low-volume products often use lots of setups per unit.

Source: Derived calculation; method and arithmetic shown above

44. Which product is undercosted?

PEIS-T44 · Operations Engineering · 3D Costing systems (overhead allocation) · Multiple choice

Overhead of $410,000 can be allocated two ways. Traditional: $41 per machine hour. Activity-based: setups $400 each, inspections $60 each, machining $20 per machine hour. Low-volume product L made 500 units using 30 setups, 200 inspections, and 400 machine hours. Compared with ABC, how does the traditional method cost L's overhead per unit?

Show answer and solution

Answer: A. It undercosts L by $31.20 per unit

Traditional: 400 MH × $41 ÷ 500 units = $32.80 per unit.

ABC: [30(400) + 200(60) + 400(20)] ÷ 500 = 32,000 ÷ 500 = $64.00 per unit.

Traditional is lower by 64.00 − 32.80 = $31.20 per unit, so it undercosts L.

Why the others miss:

  • B: Reverses the direction. The traditional figure is the lower one.
  • C: The total is the same, but the split between products changes. That shift is the point of ABC.
  • D: Reports the full ABC overhead as the difference.

If you missed it: Volume-based allocation shifts overhead from low-volume, setup-heavy products onto high-volume ones.

Source: Derived calculation; method and arithmetic shown above

45. Minimize the number of late jobs

PEIS-T45 · Operations Engineering · 3E Production scheduling methods · Multiple choice

Five jobs wait at one machine, all available now. Processing time and due date (hours): J1 4, 6; J2 3, 7; J3 5, 9; J4 2, 10; J5 6, 12. What is the minimum possible number of late jobs?

Show answer and solution

Answer: A. 2

Moore–Hodgson: start in due-date order and remove the longest job whenever one goes late.

J1 done 4 (on time), J2 done 7 (on time), J3 done 12 (late, due 9). Remove the longest so far, J3 (5 h); completion falls to 7.

J4 done 9 (on time), J5 done 15 (late, due 12). Remove the longest of J1, J2, J4, J5: J5 (6 h).

On-time sequence J1–J2–J4, then J3 and J5 late: 2 late jobs. Checking all 120 sequences confirms none does better.

Why the others miss:

  • B: Earliest-due-date order alone (J3, J4, and J5 late). EDD minimizes maximum lateness, not the count of late jobs.
  • C: Not achievable here: J1, J2, J3, and J4 can't all be on time, and adding J5 doesn't help.
  • D: Total work is 20 hours against a latest due date of 12.

If you missed it: Match the rule to the goal: SPT for mean flow time, EDD for maximum lateness, Moore–Hodgson for number of late jobs.

Source: Derived calculation; method and arithmetic shown above

46. Johnson's rule

PEIS-T46 · Operations Engineering · 3E Production scheduling methods (flow shop) · Multiple choice

Five jobs go through Machine 1 and then Machine 2. Times (hours, M1/M2): A 5/2, B 1/6, C 9/7, D 3/8, E 10/4. Using Johnson's rule, what sequence and makespan result?

Show answer and solution

Answer: A. B–D–C–E–A; 30 hours

Pick the smallest remaining time. If it's on M1, schedule that job as early as possible; if on M2, as late as possible.

B (1, M1) first; A (2, M2) last; D (3, M1) second; E (4, M2) second-to-last; C in the middle: B–D–C–E–A.

M1 finishes: 1, 4, 13, 23, 28. M2 finishes: 7, 15, 22, 27, 30. Makespan = 30 hours, the minimum.

Why the others miss:

  • B: Alphabetical order, with no rule applied.
  • C: Sorts by shortest M1 time. That ignores M2.
  • D: Applies the rule backward (short M1 times last).

If you missed it: Short on M1 goes early so M2 starts fast; short on M2 goes late so M2 finishes fast.

Source: Derived calculation; method and arithmetic shown above

47. EOQ with a quantity discount

PEIS-T47 · Operations Engineering · 3F Inventory management (deterministic) · Multiple choice

Annual demand is 10,000 units, ordering costs $50 per order, and holding cost is 20% of unit price per year. The supplier charges $10.00 per unit for orders under 1,000 units and $9.60 for 1,000 or more. What order quantity minimizes total annual cost?

Show answer and solution

Answer: A. 1,000 units; about $97,460 per year

EOQ at $9.60 (H = $1.92) = √(2 × 10,000 × 50 ÷ 1.92) = 722, below the 1,000 break, so it isn't valid at that price.

EOQ at $10.00 (H = $2.00) = √(1,000,000 ÷ 2) = 707. Total = 100,000 + 707 + 707 = $101,414.

At the break, 1,000 units: 96,000 + (10 × 50) + (500 × 1.92) = 96,000 + 500 + 960 = $97,460. Order 1,000.

Why the others miss:

  • B: The best plan without the discount, about $3,950 per year more expensive.
  • C: 722 is below 1,000, so it can't get the $9.60 price.
  • D: Ordering plus holding is lower at 707, but purchase cost dominates. Total cost decides.

If you missed it: With all-units discounts, compare total cost at each valid EOQ and at each price break.

Source: Derived calculation; method and arithmetic shown above

48. Single-period order quantity

PEIS-T48 · Operations Engineering · 3F Inventory management (stochastic) · Multiple choice

A seasonal item costs $30, sells for $75, and any leftovers sell for $10 after the season. Demand is normal with mean 800 and standard deviation 150. How many should you order? (z for 0.692 ≈ 0.50; z for 0.600 ≈ 0.25.)

Show answer and solution

Answer: A. About 875

Underage cost Cu = 75 − 30 = $45 (profit lost per unit short). Overage cost Co = 30 − 10 = $20 (loss per unit left over).

Critical ratio = Cu ÷ (Cu + Co) = 45 ÷ 65 = 0.692, so z ≈ 0.50.

Q = 800 + 0.50 × 150 = about 875.

Why the others miss:

  • B: Swaps Cu and Co (ratio 0.308, z ≈ −0.50).
  • C: Orders the mean, which is right only when Cu = Co.
  • D: Uses Cu ÷ price (45 ÷ 75 = 0.60) as the ratio.

If you missed it: Shortages here cost more than leftovers, so you should order above the mean.

Source: Derived calculation; method and arithmetic shown above

49. Direct ship or cross-dock?

PEIS-T49 · Operations Engineering · 3G Distribution models (direct ship and cross-docking) · Select all that apply

Three suppliers serve four stores. Direct shipping sends an LTL shipment from every supplier to every store each week at $520 per shipment. Cross-docking sends one truckload per supplier to a cross-dock at $900 each, handles 4,800 cartons per week at $0.25 per carton, and sends one truckload to each store at $350 each. Select all true statements.

Show answer and solution

Answer: A, B, and C

Direct: 3 × 4 = 12 shipments × $520 = $6,240 per week.

Cross-dock: 3 × 900 + 4,800 × 0.25 + 4 × 350 = 2,700 + 1,200 + 1,400 = $5,300. Shipments: 3 inbound + 4 outbound = 7. Savings = $940.

At $0.40 handling: 2,700 + 1,920 + 1,400 = $6,020, still below $6,240.

At $0.50 handling: 2,700 + 2,400 + 1,400 = $6,500, now above $6,240.

Why the other choices are wrong:

  • D: At $0.50 per carton, cross-docking costs $6,500, more than direct.
  • E: 12 shipments × $520 = $6,240, not $5,040.

If you missed it: Cross-docking trades many small shipments for fewer full ones plus handling. The handling rate decides the break-even.

Source: Derived calculation; method and arithmetic shown above

50. Dedicated versus randomized storage

PEIS-T50 · Operations Engineering · 3H Storage and warehousing methods · Multiple choice

Four SKUs have peak inventories of 400, 300, 500, and 200 pallets, but their peaks happen at different times. The most pallets ever on hand at once is 900. Before any utilization allowance, how many pallet positions do dedicated storage and randomized storage need?

Show answer and solution

Answer: A. Dedicated 1,400; randomized 900

Dedicated storage reserves positions for each SKU's own peak: 400 + 300 + 500 + 200 = 1,400.

Randomized storage lets any pallet use any open position, so it needs only the largest total on hand at once: 900.

Why the others miss:

  • B: Dedicated slots can't be shared, so they must cover each SKU's separate peak.
  • C: Randomized storage shares slots, so it never needs the sum of separate peaks.
  • D: 350 is the average of the peaks, not the largest total on hand.

If you missed it: Dedicated: sum of maximums. Randomized: maximum of the sum.

Source: Derived calculation; method and arithmetic shown above

51. Rank modes by total cost

PEIS-T51 · Operations Engineering · 3I Transportation modes · Drag and drop: order

A plant ships 20,000 units per year; each unit is worth $500, and inventory carrying cost is 25% per year. In-transit inventory cost = annual units × unit value × carrying rate × (transit days ÷ 365). Rank the modes from lowest to highest total annual cost (freight plus in-transit inventory).

P. Rail: $3 freight per unit, 12 days in transit

Q. Truck: $5 freight per unit, 4 days in transit

R. Air: $12 freight per unit, 1 day in transit

Choose the item for each position, first to last

Show answer and solution

Answer: Q → P → R

In-transit cost per day = 20,000 × 500 × 0.25 ÷ 365 = $6,849.

Truck: 100,000 + 4 × 6,849 = $127,397. Rail: 60,000 + 12 × 6,849 = $142,192. Air: 240,000 + 6,849 = $246,849.

Lowest to highest: truck, rail, air.

If you missed it: Ranking by freight alone puts rail first. Slow transit ties up high-value inventory, and that cost can outweigh cheaper freight.

Source: Derived calculation; method and arithmetic shown above

Work Design (Questions 52–68)

52. Read a multiple-activity chart

PEIS-T52 · Work Design · 4A Methods for analysis and improvement (man-machine charts) · Select all that apply

One operator tends one machine. Each cycle: the operator loads the machine (2.0 min, machine stopped), the machine runs automatically (6.0 min) while the operator deburrs the previous part (1.5 min) and then waits, and the operator unloads (1.0 min, machine stopped). Count the machine as productive only while it runs. Select all true statements.

Show answer and solution

Answer: A, B, and C

Cycle = 2.0 + 6.0 + 1.0 = 9.0 min.

Operator works 2.0 + 1.5 + 1.0 = 4.5 min, so idle 9.0 − 4.5 = 4.5 min (50% utilization).

Machine runs 6.0 of 9.0 min = 66.7%; it is stopped 3.0 min per cycle.

Why the other choices are wrong:

  • D: Operator utilization is 4.5 ÷ 9.0 = 50%.
  • E: The machine is stopped during loading and unloading, 3.0 min per cycle.

If you missed it: Draw the operator and machine columns side by side; idle time shows up as gaps.

Source: Derived calculation; method and arithmetic shown above

53. How many machines per operator?

PEIS-T53 · Work Design · 4A Methods for analysis and improvement (machine assignment) · Multiple choice

Identical machines need 1.5 min of operator load/unload each cycle (machine stopped), then run 10 min automatically. The operator needs 0.5 min to walk and inspect between machines. The operator costs $30 per hour and each machine $60 per hour. Which assignment gives the lowest cost per unit?

Show answer and solution

Answer: A. 5 machines, about $12.65 per unit

Ideal number n′ = (load + run) ÷ (load + walk) = (1.5 + 10) ÷ (1.5 + 0.5) = 5.75. Compare 5 and 6.

n = 5: machines set the pace, so cycle = 11.5 min for 5 units. Cost = ($30 + 5 × $60) ÷ 60 × 11.5 ÷ 5 = $5.50/min × 2.3 = $12.65.

n = 6: the operator sets the pace, so cycle = 6 × 2.0 = 12 min for 6 units. Cost = $6.50/min × 2.0 = $13.00.

Why the others miss:

  • B: The cost for 6 machines is right, but it's higher than 5.
  • C: Keeps the 11.5-minute cycle with 6 machines. With 6, the operator can't get around in 11.5 minutes, so the cycle stretches to 12.
  • D: Four machines leave the operator idle and cost more per unit.

If you missed it: Above n′ the operator is the bottleneck; below it the machines are. Check both integers next to n′.

Source: Derived calculation; method and arithmetic shown above

54. Balance with the largest-candidate rule

PEIS-T54 · Work Design · 4B Line balancing · Multiple choice

Task times (s) and immediate predecessors: A 20 (none); B 35 (A); C 15 (A); D 25 (B); E 30 (C); F 10 (D, E); G 15 (F). Cycle time is 50 s. Using the largest-candidate rule (assign the longest eligible task that fits), how many stations result, and what is the line efficiency?

Show answer and solution

Answer: A. 4 stations; 75%

Total work = 150 s. Theoretical minimum = ⌈150 ÷ 50⌉ = 3.

Station 1: A (20), then C (15) = 35; B (35) and E (30) won't fit. Station 2: B (35); D (25) and E (30) won't fit. Station 3: E (30); D (25) won't fit. Station 4: D, F, G = 50.

Efficiency = 150 ÷ (4 × 50) = 75%.

Three stations is impossible here: any station holding A can't also hold B or E, which leaves at least 130 s for two stations of 50 s.

Why the others miss:

  • B: The theoretical minimum, not what precedence and task sizes allow.
  • C: Divides 150 by 4 stations × 47 s (an average), not by the 50 s cycle.
  • D: Over-counts stations; the rule produces four.

If you missed it: Efficiency always uses the cycle time, even if no station is fully loaded.

Source: Derived calculation; method and arithmetic shown above

55. Maximum output from station times

PEIS-T55 · Work Design · 4B Line balancing (output) · Multiple choice

A balanced line has station times of 42, 48, 39, and 45 seconds. The shift has 7.5 productive hours. What is the maximum output per shift?

Show answer and solution

Answer: A. 562 units

The slowest station sets the pace: 48 s per unit.

Output = 7.5 × 3,600 ÷ 48 = 562.5 → 562 complete units.

Why the others miss:

  • B: Uses the average station time (43.5 s).
  • C: Uses the fastest station (39 s).
  • D: Treats the line as one station doing all 174 s of work.

If you missed it: A line can't move faster than its slowest station.

Source: Derived calculation; method and arithmetic shown above

56. Standard time from TMU

PEIS-T56 · Work Design · 4C Work measurement (predetermined time systems) · Fill in the blank

A predetermined time analysis totals 1,250 TMU per cycle. Use 1 TMU = 0.00001 hour. Predetermined time values are treated as normal times, so no performance rating applies. Allowances are 12% of normal time. What is the standard time in seconds? Enter to one decimal.

Show answer and solution

Answer: 50.4 seconds (accepted: 50.3 to 50.5)

1 TMU = 0.00001 h = 0.036 s. Normal time = 1,250 × 0.036 = 45.0 s.

Standard time = 45.0 × 1.12 = 50.4 s.

Common wrong answers:

  • 45.0: Leaves out the allowance.
  • 0.014: Reports hours (1,250 × 0.00001 × 1.12) when the question asks for seconds.

If you missed it: Convert TMU once, carefully: 100,000 TMU per hour, 0.036 s per TMU.

Source: MTM Association, MTM research publication (1 TMU = 0.036 seconds). The no-performance-rating condition used here is stated directly in the question.

57. Minimum cycles for a time study

PEIS-T57 · Work Design · 4C Work measurement (stopwatch time study) · Multiple choice

Preliminary data suggest a mean cycle time of 0.80 min and a standard deviation of 0.06 min. You want the estimated mean within ±5% of 0.80 min at 95% confidence (use z = 1.96 as a planning approximation). What minimum sample size should you plan?

Show answer and solution

Answer: A. 9

Allowed error = 5% of the mean = 0.05 × 0.80 = 0.040 min.

n = (z s ÷ e)² = (1.96 × 0.06 ÷ 0.040)² = (2.94)² = 8.64. Round up: 9.

Why the others miss:

  • B: Rounds 8.64 down.
  • C: Forgets to square 2.94.
  • D: Treats ±5% as ±0.05 min instead of 5% of the mean.

If you missed it: '±5%' is relative to the planning mean. Convert it to minutes before using the sample-size formula.

Source: Derived calculation; method and arithmetic shown above

58. Total hours for the first four units

PEIS-T58 · Work Design · 4D Learning curves · Multiple choice

The first unit of a new fixture took 200 hours. Production follows an 85% unit learning curve (each unit's time is Tₙ = T₁ × n^b). How many total hours should the first four units take?

Show answer and solution

Answer: A. About 669 hours

b = log(0.85) ÷ log(2) = −0.2345.

T₁ = 200, T₂ = 170, T₃ = 200 × 3^−0.2345 = 154.6, T₄ = 144.5.

Total = 200 + 170 + 154.6 + 144.5 = 669 hours.

Why the others miss:

  • B: Uses the cumulative-average model (4 × 200 × 0.85²). The stem specifies the unit model.
  • C: The time for the fourth unit alone.
  • D: Ignores learning.

If you missed it: Unit model: sum each unit's time. Cumulative-average model: average × count. Check which one the problem names.

Source: Derived calculation; method and arithmetic shown above

59. Sample size with a finite population

PEIS-T59 · Work Design · 4E Sample size calculations · Multiple choice

An audit will estimate the proportion of mislabeled cartons in a lot of 2,000. A pilot suggests about 10% are mislabeled. You want the estimate within ±0.03 (absolute) at 95% confidence (z = 1.96). Using the finite population correction, how many cartons should you sample?

Show answer and solution

Answer: A. 323

Infinite-population size: n₀ = z² p(1 − p) ÷ e² = 3.8416 × 0.09 ÷ 0.0009 = 384.2.

Correct for the finite lot: n = n₀ ÷ [1 + (n₀ − 1) ÷ N] = 384.2 ÷ 1.1916 = 322.4. Round up: 323.

Why the others miss:

  • B: Skips the finite population correction (384.2 rounded up).
  • C: Rounds 322.4 down.
  • D: Halves the uncorrected size, which has no basis.

If you missed it: When the sample is a noticeable share of the lot (here about 19%), apply the correction.

Source: Derived calculation; method and arithmetic shown above

60. Standard time from a work sampling study

PEIS-T60 · Work Design · 4F Work sampling analysis · Multiple choice

Over a 480-minute shift, 1,000 random observations found the operator working in 850. The operator's average performance rating was 110%, and 300 units were produced. Allowances are 15% of normal time. What is the standard time per unit?

Show answer and solution

Answer: A. 1.72 min

Working time = 480 × 0.85 = 408 min. Normal time per unit = 408 × 1.10 ÷ 300 = 1.496 min.

Standard time = 1.496 × 1.15 = 1.72 min.

Why the others miss:

  • B: Leaves out the 110% rating.
  • C: Normal time, with no allowance.
  • D: Rates the whole 480-minute shift instead of only the working time.

If you missed it: Work sampling first finds the share of time spent working, then rates only that time.

Source: Derived calculation; method and arithmetic shown above

61. Hearing conservation at 87 dBA

PEIS-T61 · Work Design · 4G Safety codes, standards, and voluntary guidelines (OSHA noise) · Select all that apply

General-industry employees have an 8-hour TWA noise exposure of 87 dBA. All have baseline audiograms, and none has a standard threshold shift. Under 29 CFR 1910.95, select all that the employer must do.

Show answer and solution

Answer: A, B, C, and E

87 dBA is at or above the 85 dBA 8-hour TWA that triggers a hearing conservation program, (c)(1). That program includes monitoring (d), audiometric testing (g), hearing protectors made available at no cost (i)(1), and training (k).

87 dBA is below the 90 dBA, 8-hour permissible exposure in Table G-16, so the controls in (b)(1) aren't triggered.

Why the other choices are wrong:

  • D: Table G-16 allows 90 dBA for 8 hours. At 87 dBA the PEL isn't exceeded.
  • F: Wearing protectors is mandatory at 85 dBA or more only for employees without a baseline audiogram or with a standard threshold shift, (i)(2). Neither applies here.

If you missed it: Keep the two numbers apart: 85 dBA triggers the hearing conservation program; 90 dBA is the 8-hour permissible exposure.

Source: 29 CFR 1910.95(b)(1), Table G-16, (c)(1), (d)(1), (g)(1), (i)(1)–(2), (k)(1)

62. Remaining allowable time

PEIS-T62 · Work Design · 4H Methods for quantifying risk factors (OSHA noise limits) · Multiple choice

A worker has already spent 2 hours at 97 dBA today. Using OSHA Table G-16 permissible durations and the rule that the sum of (time at each level ÷ permitted time at that level) may not exceed 1, how many more hours may the worker spend at 92 dBA?

Show answer and solution

Answer: A. 2 hours

Table G-16 permits 3 h at 97 dBA and 6 h at 92 dBA.

Used so far: 2 ÷ 3 = 0.667. Remaining fraction: 1 − 0.667 = 0.333.

Allowed time at 92 dBA = 0.333 × 6 = 2 hours.

Why the others miss:

  • B: Subtracts 2 hours from the 6-hour limit, mixing exposures at different levels as if they were the same.
  • C: Ignores the exposure already received.
  • D: Assumes 2 hours at 97 dBA used up the whole daily allowance. It used 2/3 of it.

If you missed it: Mixed exposures add as fractions of each level's permitted time.

Source: 29 CFR 1910.95(b)(1), Table G-16 and footnote

63. Match RULA grand scores to action levels

PEIS-T63 · Work Design · 4H Methods for quantifying risk factors (RULA) · Drag and drop: match

Match each RULA grand score to its action level.

  1. Grand score 2
  2. Grand score 4
  3. Grand score 6
  4. Grand score 7

Options:

  • a. Action level 1: no action is needed
  • b. Action level 2: measures should be taken, but not in the short term
  • c. Action level 3: measures should be taken in the short term
  • d. Action level 4: urgent action must be taken
Match each numbered item to a lettered option

Show answer and solution

Answer: 1 → a, 2 → b, 3 → c, 4 → d

RULA grand scores run from 1 to 7: 1–2 is action level 1, 3–4 is level 2, 5–6 is level 3, and 7 is level 4.

If you missed it: Two scores per level, except 7, which stands alone at the top.

Source: Gómez-Galán et al., Musculoskeletal Risks: RULA Bibliometric Review (2020), action levels; McAtamney, Notes for using RULA (grand score 1–7)

64. Shoulder moment

PEIS-T64 · Work Design · 4I Limits of human capacity (skeletal-joint force analysis) · Multiple choice

A worker holds an 8.0 kg tool with the arm straight out horizontally. The tool's center of mass is 0.60 m from the shoulder joint. The arm has a mass of 3.5 kg with its center of mass 0.30 m from the shoulder. Use g = 9.81 m/s². What static moment must the shoulder resist?

Show answer and solution

Answer: A. 57.4 N·m

Moment = Σ (mass × g × horizontal distance) = (8.0 × 0.60 + 3.5 × 0.30) × 9.81 = (4.80 + 1.05) × 9.81 = 57.4 N·m.

Why the others miss:

  • B: Leaves out the arm's own weight.
  • C: Forgets g, leaving kg·m instead of N·m.
  • D: Places the arm's mass at the tool's distance (0.60 m) instead of at its own center of mass.

If you missed it: Every mass gets its own moment arm, and the moment arm is the horizontal distance to the joint.

Source: Derived calculation; method and arithmetic shown above

65. What a positioner does to the lifting index

PEIS-T65 · Work Design · 4J Lifting aids (with the NIOSH lifting equation) · Multiple choice

A worker lifts a 25 lb part with the hands 20 in out from the midpoint between the ankles (H). For this task, the product of the other multipliers (VM × DM × AM × FM × CM) is 0.70. A part positioner would let the worker lift with H = 12 in, all else unchanged. Using the revised NIOSH lifting equation (load constant 51 lb, HM = 10/H in inches), how does the lifting index change?

Show answer and solution

Answer: A. From about 1.40 to about 0.84

Before: RWL = 51 × (10/20) × 0.70 = 17.9 lb. LI = 25 ÷ 17.9 = 1.40.

After: RWL = 51 × (10/12) × 0.70 = 29.8 lb. LI = 25 ÷ 29.8 = 0.84.

Bringing the load closer raises the horizontal multiplier, which raises the recommended weight limit and drops the index below 1.0.

Why the others miss:

  • B: Divides RWL by the load. The lifting index is load ÷ RWL.
  • C: Assumes only vertical height matters. Horizontal distance has its own multiplier.
  • D: Leaves out the other multipliers (the 0.70 product), which overstates the recommended weight limit both times.

If you missed it: A lifting index above 1.0 means the load is more than the recommended weight limit for those conditions.

Source: Cole & McGlothlin, Ergonomics Case Study: Revised NIOSH Lifting Equation (2009), p. D74, citing NIOSH Pub. 94-110

66. Which control goes in the primary zone?

PEIS-T66 · Work Design · 4K Link analysis and associated criteria · Multiple choice

A control panel layout gives the primary reach zone to the control with the highest link value, defined here as importance (1–5) × frequency of use (uses per hour). Controls: alarm acknowledge, importance 5, frequency 2; feed rate, importance 3, frequency 8; spindle speed, importance 4, frequency 5; coolant on/off, importance 2, frequency 9. Which control gets the primary zone?

Show answer and solution

Answer: A. Feed rate

Link values: alarm acknowledge 10, feed rate 24, spindle speed 20, coolant 18. Feed rate ranks first.

Why the others miss:

  • B: Highest importance alone, but used only twice an hour (link value 10).
  • C: Highest frequency alone, but low importance (link value 18).
  • D: Second-highest link value (20).

If you missed it: Combine the criteria the way the problem defines them before ranking.

Source: Ranking criterion supplied in the stem; arithmetic shown

67. Design clearance for the 95th percentile

PEIS-T67 · Work Design · 4L Workplace design (anthropometric data) · Multiple choice

Standing height in a plant's workforce is approximately normal with mean 70.0 in and standard deviation 2.8 in. An overhead guard must clear the 95th-percentile worker plus a 3.0 in allowance for footwear and headwear. Use z = 1.645. What minimum clearance should be specified?

Show answer and solution

Answer: A. 77.6 in

95th percentile = 70.0 + 1.645 × 2.8 = 74.6 in.

Clearance = 74.6 + 3.0 = 77.6 in.

Why the others miss:

  • B: Designs for the average worker plus allowance. Half the workforce would be taller.
  • C: Uses the 90th percentile (z ≈ 1.28).
  • D: Leaves out the allowance.

If you missed it: Clearances are set by the tall end of the distribution; reaches are set by the short end.

Source: Derived calculation; method and arithmetic shown above

68. Name the mistake-proofing method

PEIS-T68 · Work Design · 4N Manufacturing/service process planning (mistake proofing) · Multiple choice

Each bag of hardware should hold 12 identical screws. At packing, a scale weighs every bag. Because each screw weighs the same, the weight tells the packer how many screws are in the bag, and any bag that doesn't weigh exactly 12 screws' worth is rejected. Which mistake-proofing method is this?

Show answer and solution

Answer: A. Fixed-value (grouping and counting) method

The fixed-value method counts repetitions or parts, and it can weigh an item to confirm it's complete. Weighing the bag confirms the 12-screw count: fixed-value.

Why the others miss:

  • B: The contact method checks a physical characteristic of the part itself, such as diameter or temperature. Here the weight is only a stand-in for the screw count.
  • C: The motion-step method checks that process steps happen in the right order.
  • D: Successive inspection is a type of inspection, not one of the setting functions that detects the error.

If you missed it: Ask what the device is really verifying: a feature (contact), a count (fixed-value), or a sequence (motion-step).

Source: ASQ, What is mistake proofing?

Quality Engineering (Questions 69–85)

69. p chart limits

PEIS-T69 · Quality Engineering · 5A Statistical process control (attribute charts) · Multiple choice

A p chart for fraction nonconforming uses samples of n = 200. The average fraction nonconforming from preliminary samples is p̄ = 0.08. What are the 3-sigma control limits?

Show answer and solution

Answer: A. UCL 0.138, LCL 0.022

σp = √[p̄(1 − p̄) ÷ n] = √(0.08 × 0.92 ÷ 200) = 0.0192.

UCL = 0.08 + 3(0.0192) = 0.138. LCL = 0.08 − 3(0.0192) = 0.022.

Why the others miss:

  • B: Uses 2-sigma limits.
  • C: Uses √(p̄ ÷ n) and drops the (1 − p̄) term.
  • D: Uses 1-sigma limits.

If you missed it: The binomial standard error is √[p(1 − p)/n]. Don't drop the (1 − p).

Source: NIST/SEMATECH e-Handbook §6.3.3.2, p control charts

70. Find the first out-of-control signal

PEIS-T70 · Quality Engineering · 5A Statistical process control (chart interpretation) · Point and click

An X̄ chart has center line 50.0 and σ of the subgroup mean = 1.0, so the zones are at 51, 52, and 53. Apply these rules on the high side: (1) one point above 53; (2) two of three consecutive points above 52; (3) four of five consecutive points above 51; (4) eight consecutive points above 50. Subgroup means, in order:

70. Find the first out-of-control signal
Point123456789101112131415
X̄50.249.551.450.852.451.252.650.449.151.851.652.251.350.953.4

Click (or select) the point at which the chart first signals an out-of-control condition.

Select a point (or click its column in the table above)

Show answer and solution

Answer: Point 7

Point 5 (52.4) is the first point above 52, but it's alone.

At point 7 (52.6), two of the last three points (5 and 7) are above 52: rule 2 fires. Points 3–7 also have four of five above 51 (51.4, 52.4, 51.2, 52.6): rule 3 fires at the same point.

The first signal is point 7. Point 15 (53.4) later breaks rule 1, but by then the process had already signaled.

Common wrong answers:

  • 5: The first point beyond 2σ, but one point in that zone isn't a signal by itself.
  • 15: The most extreme point, but not the first signal.

If you missed it: Scan in order and test every rule at each new point. The most dramatic point is rarely the first signal.

Source: NIST/SEMATECH e-Handbook §6.3.2, Western Electric control chart rules

71. c chart for defects

PEIS-T71 · Quality Engineering · 5A Statistical process control (c chart) · Multiple choice

Painted panels of identical size average c̄ = 4.0 defects per panel. Using a 3-sigma c chart, what are the control limits, and is a panel with 9 defects in control?

Show answer and solution

Answer: A. UCL 10, LCL 0; 9 is in control

UCL = c̄ + 3√c̄ = 4 + 3(2) = 10. The raw lower limit is 4 − 6 = −2, so for a count chart it is set to 0.

9 ≤ 10, so the panel is in control.

Why the others miss:

  • B: Uses 1-sigma limits (4 ± 2).
  • C: Uses 2-sigma limits (4 + 4 = 8).
  • D: Uses 3c̄ instead of 3√c̄. Poisson standard deviation is √c̄.

If you missed it: For Poisson counts, the variance equals the mean, so σ = √c̄.

Source: NIST/SEMATECH e-Handbook §6.3.3.1, c control charts

72. Estimate σ from the average range

PEIS-T72 · Quality Engineering · 5A Statistical process control (estimating σ) · Fill in the blank

An X̄ and R chart uses subgroups of n = 4. The average range is R̄ = 0.024 in. For n = 4, d₂ = 2.059. Estimate the process standard deviation in inches. Enter to four decimals.

Show answer and solution

Answer: 0.0117 in (accepted: 0.0116 to 0.0117)

σ̂ = R̄ ÷ d₂ = 0.024 ÷ 2.059 = 0.0117 in.

Common wrong answers:

  • 0.024: Reports R̄ itself as σ.
  • 0.0494: Multiplies by d₂ instead of dividing.

If you missed it: The range of a small subgroup is larger than σ, so σ̂ must come out smaller than R̄.

Source: NIST/SEMATECH e-Handbook §6.3.2.1, Shewhart X̄ and R and S charts (σ̂ = R̄/d₂)

73. Capability against an upper limit only

PEIS-T73 · Quality Engineering · 5B Process capability analysis (one-sided) · Multiple choice

Seal leak rate has only an upper specification limit of 5.0 units. The process is stable with mean 3.8 and standard deviation 0.3. What is the appropriate capability index?

Show answer and solution

Answer: A. Cpu = 1.33

With one upper limit, use Cpu = (USL − μ) ÷ 3σ = (5.0 − 3.8) ÷ 0.9 = 1.33.

Why the others miss:

  • B: Divides by 6σ. One-sided indices use 3σ.
  • C: Divides the USL itself by 3σ, ignoring where the mean sits.
  • D: One-sided specifications use Cpu or Cpl. Cp is the index that needs both limits.

If you missed it: Each one-sided index measures the distance from the mean to that limit, in units of 3σ.

Source: NIST/SEMATECH e-Handbook §6.1.6, process capability (Cpu, Cpl, one-sided specifications)

74. Parts per million out of specification

PEIS-T74 · Quality Engineering · 5B Process capability analysis (expected nonconformance) · Multiple choice

A diameter is normal with mean 25.00 mm and σ = 0.04 mm. Specifications are 24.88 to 25.10 mm. Use P(Z > 2.5) = 0.00621 and P(Z < −3.0) = 0.00135. About how many parts per million fall outside specification?

Show answer and solution

Answer: A. 7,560 ppm

z(USL) = (25.10 − 25.00) ÷ 0.04 = 2.5 → 0.00621 above.

z(LSL) = (24.88 − 25.00) ÷ 0.04 = −3.0 → 0.00135 below.

Total = 0.00756 = 7,560 ppm.

Why the others miss:

  • B: Counts only the upper tail.
  • C: Counts only the lower tail.
  • D: Doubles the upper tail, as if the process were centered between the limits. It isn't.

If you missed it: An off-center process has two different tails. Compute each one.

Source: Derived calculation; method and arithmetic shown above

75. Acceptance on the first sample

PEIS-T75 · Quality Engineering · 5C Acceptance sampling (double sampling) · Multiple choice

A double sampling plan takes a first sample of n₁ = 50. Accept the lot if the first sample has 0 defectives; reject if it has 3 or more; otherwise take a second sample. Incoming quality is 2% defective. Using the binomial distribution, what is the probability of accepting the lot on the first sample?

Show answer and solution

Answer: A. 0.364

Accept on the first sample only with 0 defectives: P(0) = 0.98⁵⁰ = 0.364.

Why the others miss:

  • B: P(2 or fewer). Finding 1 or 2 defectives sends you to a second sample; it isn't an acceptance.
  • C: P(1 or 2), the chance of needing a second sample.
  • D: P(3 or more), the chance of rejecting on the first sample.

If you missed it: Map each first-sample outcome to accept, reject, or continue before adding probabilities.

Source: NIST/SEMATECH e-Handbook §6.2.4, double sampling

76. Average outgoing quality

PEIS-T76 · Quality Engineering · 5C Acceptance sampling (AOQ) · Multiple choice

Lots of N = 2,000 are inspected with a sample of n = 80. Rejected lots are 100% inspected and defectives replaced. At an incoming quality of 3% defective, the plan accepts with probability 0.85. What is the average outgoing quality?

Show answer and solution

Answer: A. 2.45%

AOQ = Pa × p × (N − n) ÷ N = 0.85 × 0.03 × 1,920 ÷ 2,000 = 0.0245 (2.45%).

Defectives remain only in the uninspected part of accepted lots.

Why the others miss:

  • B: Drops the (N − n)/N factor; the 80 inspected units are also cleaned up.
  • C: The incoming quality. Rectifying inspection improves it.
  • D: p × (1 − Pa), the share of defectives removed by rejecting lots.

If you missed it: Outgoing defectives come only from accepted lots, and only from the units nobody inspected.

Source: NIST/SEMATECH e-Handbook §6.2.2, LASP definitions (AOQ, AOQL)

77. What's true about MIL-STD-105E?

PEIS-T77 · Quality Engineering · 5C Acceptance sampling (MIL-STD-105E) · Select all that apply

Select all true statements about the MIL-STD-105 attribute sampling system.

Show answer and solution

Answer: A, B, D, and F

A, B, and D describe the system as NIST summarizes it: AQL is the foundation, the standard issues a code letter, and plans switch among normal, tightened, and reduced inspection. NIST notes the basic tables are the same in 105D and 105E.

F is also true: the current DoD cancellation notice says MIL-STD-105E is canceled, while the current NCEES PE Industrial and Systems specification still lists MIL STD 105E as an acceptance-sampling example.

Why the other choices are wrong:

  • C: Inspection begins at normal and moves to tightened when quality falls short.
  • E: Acceptance is probabilistic. A lot at the AQL can still be rejected (producer's risk), and worse lots are sometimes accepted.

If you missed it: An AQL plan protects the producer at the AQL; it doesn't certify any single accepted lot.

Source: NIST/SEMATECH e-Handbook §6.2.3.1, MIL Standard 105D; Defense Logistics Agency, MIL-STD-105E Notice 3 (cancellation); NCEES PE Industrial and Systems Exam Specifications, Quality Engineering 5C; NIST/SEMATECH e-Handbook §6.2.2, producer's risk

Acceptance-sampling interpretation:

A, B, and D describe the MIL-STD-105 sampling system as NIST summarizes it: AQL is foundational, the standard uses a sample-size code letter, and plans switch among normal, tightened, and reduced inspection. NIST notes that the basic tables in 105D and 105E are the same.

78. Match quality concepts to descriptions

PEIS-T78 · Quality Engineering · 5D Quality systems · Drag and drop: match

Match each concept to its description. One description is not used.

  1. PDSA
  2. ISO 9001
  3. Benchmarking
  4. Fishbone diagram

Options:

  • a. A cycle of planning a change, carrying it out, studying results against predictions, and acting on what was learned
  • b. An international standard that sets requirements for a quality management system
  • c. Measuring your products, services, and processes against organizations known as leaders
  • d. Sorting possible causes of a problem into categories such as methods, machines, materials, and measurement
  • e. Ranking problem categories by frequency to find the vital few
Match each numbered item to a lettered option

Show answer and solution

Answer: 1 → a, 2 → b, 3 → c, 4 → d

PDSA is Plan-Do-Study-Act. ISO 9001 is titled Quality management systems — Requirements. Benchmarking compares against recognized leaders. A fishbone (cause-and-effect) diagram sorts possible causes into categories.

Description e is a Pareto analysis.

If you missed it: ISO 9001 is the requirements standard; ISO 9000 covers fundamentals and vocabulary.

Source: The W. Edwards Deming Institute, PDSA Cycle; ISO, ISO 9001:2026 Quality management systems — Requirements; ASQ, What is benchmarking?; ASQ, What is a fishbone diagram?

79. Runs and a main effect in a 2³ design

PEIS-T79 · Quality Engineering · 5E Techniques for process improvement (design of experiments) · Multiple choice

A full 2³ factorial, one replicate, gives these responses in standard order: (1) 60, a 72, b 54, ab 80, c 62, ac 74, bc 58, abc 84. A letter means that factor is at its high level. How many runs does one replicate need, and what is the main effect of C?

Show answer and solution

Answer: A. 8 runs; effect of C = 3

A 2³ design has 2 × 2 × 2 = 8 runs.

C high: (62 + 74 + 58 + 84) ÷ 4 = 69.5. C low: (60 + 72 + 54 + 80) ÷ 4 = 66.5.

Main effect of C = 69.5 − 66.5 = 3.

Why the others miss:

  • B: 12 is the contrast (sum at high minus sum at low) before dividing by 4.
  • C: Counts 2 × 3 instead of 2³.
  • D: 19 is the main effect of A.

If you missed it: Main effect = average at the high level minus average at the low level.

Source: NIST/SEMATECH e-Handbook §5.3.3.3.2, full factorial example (2³ = 8 runs); NIST/SEMATECH e-Handbook §5.3.3.4.1, estimating effects

80. Quadratic quality loss

PEIS-T80 · Quality Engineering · 5E Techniques for process improvement (Taguchi) · Multiple choice

A shaft's target diameter is 25.00 mm. A shaft 0.10 mm off target is reworked at a cost of $8. Using the Taguchi quadratic loss function L = k(y − T)², what is the expected loss for a shaft at 25.04 mm?

Show answer and solution

Answer: A. $1.28

Find k: 8 = k(0.10)², so k = 800 $/mm².

Loss at 25.04: L = 800 × (0.04)² = 800 × 0.0016 = $1.28.

Why the others miss:

  • B: Scales the loss linearly (8 × 0.04 ÷ 0.10). Taguchi loss grows with the square of the deviation.
  • C: The goalpost view: no loss inside tolerance. The quadratic loss model charges for any deviation from target.
  • D: Computes k with an unsquared deviation (8 ÷ 0.10 = 80).

If you missed it: Halving the deviation cuts the loss to a quarter, not a half.

Source: Dassault Systèmes Isight documentation (hosted by MIT), Taguchi Robust Design: quality loss function

81. FMEA practice

PEIS-T81 · Quality Engineering · 5E Techniques for process improvement (FMEA) · Select all that apply

Select all statements consistent with ASQ's description of failure mode and effects analysis (FMEA).

Show answer and solution

Answer: A, B, C, and E

ASQ's procedure builds a cross-functional team, sets the scope, identifies functions and failure modes, identifies effects, rates severity (1–10, recording the highest severity per mode), and identifies root causes. Failures are then prioritized and acted on, highest priority first.

Why the other choices are wrong:

  • D: Scope comes before failure modes. Brainstorming without a defined scope wanders.
  • F: ASQ calls for a cross-functional team with knowledge of the process, product, and customer needs.

If you missed it: FMEA runs in order: team, scope, functions, failure modes, effects, severity, causes, then prioritized action.

Source: ASQ, What is FMEA?

82. Weibull reliability

PEIS-T82 · Quality Engineering · 5F Reliability analysis (Weibull) · Multiple choice

A bearing's life follows a Weibull distribution with shape γ = 2 and scale α = 1,200 hours, so R(t) = exp[−(t/α)^γ]. What is the probability a bearing survives 600 hours?

Show answer and solution

Answer: A. 0.779

R(600) = exp[−(600/1,200)²] = exp(−0.25) = 0.779.

Why the others miss:

  • B: Treats life as exponential (γ = 1): exp(−0.5).
  • C: Reports (t/α)^γ, the exponent, instead of the reliability.
  • D: 1 − R, the probability of failure.

If you missed it: A shape parameter above 1 means wear-out: early survival is higher than the exponential model predicts.

Source: NIST/SEMATECH e-Handbook §8.1.6.2, Weibull

83. Two-out-of-three system

PEIS-T83 · Quality Engineering · 5F Reliability analysis (system models) · Multiple choice

A safety interlock uses three identical, independent sensors and works if at least 2 of the 3 work. Each sensor's reliability is 0.90. What is the system reliability?

Show answer and solution

Answer: A. 0.972

R = Σ (i = 2 to 3) C(3, i) R^i (1 − R)^(3−i) = 3(0.90)²(0.10) + (0.90)³ = 0.243 + 0.729 = 0.972.

Why the others miss:

  • B: The 1-of-3 parallel result, 1 − 0.10³.
  • C: The series result: all three must work.
  • D: Only the case of exactly two working.

If you missed it: For r-out-of-n, add the binomial terms from r up to n.

Source: NIST/SEMATECH e-Handbook §8.1.8.4, r out of n model

84. Preventive replacement interval

PEIS-T84 · Quality Engineering · 5G Maintenance procedures · Multiple choice

A pump seal costs $400 to replace on a schedule and $2,400 if it fails in service (including downtime). Evaluate three policies with cost per operating hour = expected cost per cycle ÷ expected cycle length:

84. Preventive replacement interval
PolicyProbability of failure before scheduled replacementExpected cycle length
Replace every 1,000 h0.10980 h
Replace every 2,000 h0.351,850 h
Run to failure1.002,500 h

Which policy has the lowest cost per hour?

Show answer and solution

Answer: A. Replace every 2,000 h, about $0.59 per hour

1,000 h: (0.90 × 400 + 0.10 × 2,400) ÷ 980 = 600 ÷ 980 = $0.612/h.

2,000 h: (0.65 × 400 + 0.35 × 2,400) ÷ 1,850 = 1,100 ÷ 1,850 = $0.595/h.

Run to failure: 2,400 ÷ 2,500 = $0.960/h.

Why the others miss:

  • B: Correct for 1,000 h, but slightly higher than 2,000 h.
  • C: Run to failure is the most expensive here because each failure costs six times a planned replacement.
  • D: The fewest failures isn't the goal; the lowest cost per hour is.

If you missed it: Compare policies on cost per hour of operation, not cost per cycle.

Source: Derived calculation; method and arithmetic shown above

85. Where the five whys should stop

PEIS-T85 · Quality Engineering · 5H Root cause analysis · Multiple choice

A packing conveyor keeps jamming. Why? Carton flaps open on the conveyor. Why? The glue isn't setting. Why? Glue temperature is low. Why? The heater setpoint was changed during last month's maintenance and never restored. Why? The maintenance checklist has no step to verify setpoints before restart. Which cause should corrective action target?

Show answer and solution

Answer: A. The missing setpoint-verification step in the maintenance checklist

The five whys drill past symptoms to the cause that, once fixed, stops the problem from coming back. Resetting the heater fixes today's jam; adding a setpoint check to the checklist stops the next maintenance job from causing it again.

Why the others miss:

  • B: A symptom on the way down the chain.
  • C: The problem statement itself.
  • D: An intermediate cause. Fixing it once doesn't prevent a repeat.

If you missed it: Stop asking why when you reach a cause you can control that would prevent recurrence, usually a process or system gap.

Source: ASQ, Five whys

Score your test

Give yourself one point per question. Select-all, matching, ordering, and point-and-click questions count only if every part is right, which is how NCEES scores its alternative item types: right or wrong, with no partial credit. A fill-in answer counts if it falls inside the accepted range shown with its solution.

Answer key

Answer key
#IDAreaFormatAnswer
1PEIS-T011Multiple choiceA
2PEIS-T021Multiple choiceB
3PEIS-T031Multiple choiceA
4PEIS-T041Multiple choiceA
5PEIS-T051Select all that applyA + C + E
6PEIS-T061Multiple choiceA
7PEIS-T071Multiple choiceA
8PEIS-T081Fill in the blank3.79
9PEIS-T091Multiple choiceA
10PEIS-T101Multiple choiceA
11PEIS-T111Select all that applyA + C + E
12PEIS-T121Multiple choiceA
13PEIS-T131Drag and drop: orderQ–T–S–P–R
14PEIS-T141Multiple choiceA
15PEIS-T151Multiple choiceA
16PEIS-T161Multiple choiceA
17PEIS-T171Multiple choiceA
18PEIS-T182Multiple choiceA
19PEIS-T192Drag and drop: match1→a, 2→b, 3→c, 4→d
20PEIS-T202Multiple choiceB
21PEIS-T212Multiple choiceA
22PEIS-T222Fill in the blank2,118
23PEIS-T232Multiple choiceA
24PEIS-T242Multiple choiceA
25PEIS-T252Multiple choiceA
26PEIS-T262Multiple choiceA
27PEIS-T272Multiple choiceB
28PEIS-T282Multiple choiceA
29PEIS-T292Fill in the blank25
30PEIS-T302Multiple choiceA
31PEIS-T312Select all that applyB + D
32PEIS-T322Multiple choiceA
33PEIS-T332Multiple choiceA
34PEIS-T342Multiple choiceA
35PEIS-T353Multiple choiceA
36PEIS-T363Multiple choiceA
37PEIS-T373Fill in the blank1,450
38PEIS-T383Multiple choiceA
39PEIS-T393Multiple choiceA
40PEIS-T403Multiple choiceA
41PEIS-T413Multiple choiceA
42PEIS-T423Multiple choiceA
43PEIS-T433Fill in the blank64.0
44PEIS-T443Multiple choiceA
45PEIS-T453Multiple choiceA
46PEIS-T463Multiple choiceA
47PEIS-T473Multiple choiceA
48PEIS-T483Multiple choiceA
49PEIS-T493Select all that applyA + B + C
50PEIS-T503Multiple choiceA
51PEIS-T513Drag and drop: orderQ–P–R
52PEIS-T524Select all that applyA + B + C
53PEIS-T534Multiple choiceA
54PEIS-T544Multiple choiceA
55PEIS-T554Multiple choiceA
56PEIS-T564Fill in the blank50.4
57PEIS-T574Multiple choiceA
58PEIS-T584Multiple choiceA
59PEIS-T594Multiple choiceA
60PEIS-T604Multiple choiceA
61PEIS-T614Select all that applyA + B + C + E
62PEIS-T624Multiple choiceA
63PEIS-T634Drag and drop: match1→a, 2→b, 3→c, 4→d
64PEIS-T644Multiple choiceA
65PEIS-T654Multiple choiceA
66PEIS-T664Multiple choiceA
67PEIS-T674Multiple choiceA
68PEIS-T684Multiple choiceA
69PEIS-T695Multiple choiceA
70PEIS-T705Point and clickPoint 7
71PEIS-T715Multiple choiceA
72PEIS-T725Fill in the blank0.0117
73PEIS-T735Multiple choiceA
74PEIS-T745Multiple choiceA
75PEIS-T755Multiple choiceA
76PEIS-T765Multiple choiceA
77PEIS-T775Select all that applyA + B + D + F
78PEIS-T785Drag and drop: match1→a, 2→b, 3→c, 4→d
79PEIS-T795Multiple choiceA
80PEIS-T805Multiple choiceA
81PEIS-T815Select all that applyA + B + C + E
82PEIS-T825Multiple choiceA
83PEIS-T835Multiple choiceA
84PEIS-T845Multiple choiceA
85PEIS-T855Multiple choiceA

Your results by area

Your results by area
AreaQuestionsCorrect (of 17)MissedCorrect but unsure or slow
Systems Engineering1–17
Facilities Engineering and Planning18–34
Operations Engineering35–51
Work Design52–68
Quality Engineering69–85
Total1–85(of 85)

Rank the areas by missed plus unsure answers. The top two are where your next study hours should go. A lucky guess or a 15-minute solve still costs you on exam day, so count those too.

Keep the numbers in proportion. Your total is your score on these 85 practice items, not an NCEES result. NCEES converts the number of correct answers to a scaled score, compares it with a minimum ability level, reports only pass or fail, and doesn't publish the passing score. These questions also aren't calibrated to NCEES difficulty. Seventeen questions per area is enough to point you somewhere, not enough to measure an area precisely.

How this test compares with the real exam

  • Same question count. The real exam has 85 questions. NCEES publishes a range of 14 to 21 questions for each of the five areas (specification). We used 17 per area so the total is 85. That split is our design, not a promise about any exam form.
  • Practice across NCEES item families. NCEES says CBT exams use multiple choice plus alternative item types, which include multiple correct, point and click, drag and drop, and fill in the blank. This test uses 64 multiple-choice, 8 select-all, 7 fill-in, 5 drag-and-drop-style items (3 matching, 2 ordering), and 1 point-selection item. That mix is Castleport's practice design, not a claim about the exact format mix on your exam form.
  • Pacing. NCEES gives 8.5 hours of exam time inside a 9.5-hour appointment, which also covers a 2-minute nondisclosure agreement, an 8-minute tutorial, and a 50-minute scheduled break. That averages 6 minutes per question. To rehearse exam pace, give yourself 8 hours 30 minutes of working time for all 85, or about 4 hours 15 minutes for each half.
  • Units. The real exam uses both SI and U.S. Customary units, and so does this test.
  • References. The exam is closed book with an electronic reference. NCEES supplies its electronic reference handbook and any design standards named in the exam specification, and you can't bring your own copies (NCEES). Download the handbook from your MyNCEES account and practice finding formulas in it while you work these questions.

A note on standards: an earlier NCEES posting of this October 2020 specification included a standards page listing MIL-STD-105E and MTM-1 as supplied on exam day. The specification NCEES links from the exam page now, updated in 2025, has no standards page. Because the current public specification does not identify a standards list, do not assume the older list is still current; check the reference materials available through MyNCEES before your exam. None of the questions above requires a lookup in either document.

PE Industrial and Systems exam facts

PE Industrial and Systems exam facts
Row labelCurrent ruleSource
Questions85: multiple choice plus alternative item typesNCEES exam page
Time9.5-hour appointment with 8.5 hours of exam timeNCEES exam page
WhenOne day a year; next date October 28, 2026NCEES exam page
WherePearson VUE test centers, after you register with NCEES and your licensing board approves youNCEES exam page
Fee$400 to NCEES; your licensing board may charge its own application feeNCEES exam page
ContentFive areas, 14–21 questions each, under the specification effective with the October 2020 examsSpecification
ResultsPass or fail, typically 7–10 days after the exam; failing examinees get a diagnostic report by subject areaNCEES exam scoring
Pass rates69% of 80 first-time and 29% of 21 repeat examinees (table last updated January 2026)NCEES exam page

Those pass rates describe about 100 people, so a handful of results moves them noticeably. They're not your personal odds.

The exam's content may change in a later year. In 2026, NCEES surveyed licensed industrial and systems engineers for a professional activities and knowledge study of this exam; the survey closed June 12, 2026. As of October 11, 2026, the exam page still links the October 2020 specification and announces no new effective date. If you're studying for a later administration, check that page before you build your topic list.

After you score it

  1. Rework every miss in your two weakest areas without looking at the solution. If you still get stuck, read only the first line of the solution and try again.
  2. Cover what this test didn't. Our PE Industrial and Systems exam prep page has 35 more worked problems on different scenarios, a 14-day and a 12-week study plan, and an error log you can copy.
  3. Take a second full-length run. NCEES sells its own PE Industrial and Systems practice exam: a $59.95 nonrefundable PDF with 85 questions and solutions, based on the October 2020 specification and including fill-in-the-blank and matching items. NCEES discounts it if you buy it while registering for the exam, and it posts corrections to its practice exams. Because it's NCEES's own exam for this specification, it makes a good final timed rehearsal.

Quick answers

Are these real NCEES questions? No. We wrote every question for this page. They are not actual, recalled, or adapted NCEES exam or practice-exam questions.

Is this the FE Industrial and Systems exam? No. The FE is a separate NCEES exam with its own specification. If that's the one you're taking, use our free FE Industrial and Systems practice test.

What score do I need to pass? NCEES doesn't publish one. It scores the number of correct answers with no penalty for wrong answers, then converts that to a scaled score (NCEES). Be wary of any site that names a passing percentage for this exam.

Does passing make me a licensed PE? Not by itself. Your state or territory licensing board grants the license and sets its own education and experience requirements; NCEES describes the PE exam as designed for engineers with at least four years of post-college experience in their discipline (NCEES). Our guides to NCEES exam registration, results, the retake policy, and testing accommodations cover the steps around the exam. For other disciplines, start at our PE exam prep hub.

Sources

Exam facts on this page were checked against these NCEES sources on October 11, 2026:

Technical sources for the questions are linked beside each one. The main references are the NIST/SEMATECH e-Handbook of Statistical Methods, OSHA 29 CFR 1910.95, ASQ's quality resources, and a peer-reviewed NIOSH lifting equation case study that reproduces the equation from NIOSH Publication 94-110.

How we made this page. The Castleport Test Prep Editorial Team wrote these questions with AI-assisted research and drafting. We checked the current exam facts against the NCEES sources above, reviewed the question set for answer-key and calculation consistency, and checked source-dependent items against the references linked beside them. Source checking isn't professional engineering review: these questions haven't been reviewed by NCEES or by a licensed engineer. More on our process: methodology.

Castleport Test Prep is an independent exam prep publisher. We are not affiliated with, endorsed by, or approved by NCEES, Pearson VUE, or any licensing board. Exam and credential names are used to identify their subjects, and trademarks belong to their respective owners. The practice questions on this page are original and unofficial. Nothing here guarantees a passing result or a license; confirm your own requirements with your licensing board.

Free PE Industrial and Systems Practice Test: 85 Questions