Castleport Test Prep

PE Civil Water Resources and Environmental Exam Prep

Start your PE Civil Water Resources and Environmental exam prep with this original, unofficial problem. All 40 problems, two fully worked examples, and a 12-week plan are free on this page.

Problem 1 · NRCS curve-number runoff depth

WRE-HYD-01 · Area 7, Hydrology · Select one

A watershed has a curve number CN = 80. A 24-hour storm drops 5.0 in of rain. Using the NRCS (SCS) runoff equation with Ia = 0.2S, what is the runoff depth?

  • A. 1.25 in
  • B. 2.89 in
  • C. 3.33 in
  • D. 4.50 in
Show answer and solution

Answer: B. 2.89 in.

Find the potential maximum retention first: S = 1000/CN − 10 = 1000/80 − 10 = 2.5 in. The initial abstraction is Ia = 0.2S = 0.5 in. Then Q = (P − Ia)² / (P − Ia + S) = (4.5)² / (4.5 + 2.5) = 20.25/7.0 = 2.89 in.

Why not the others: A sets Ia equal to S instead of 0.2S. C drops Ia entirely (P²/(P + S)). D is P − Ia, as if every drop after the initial abstraction ran off.

Try a change: Raise CN to 90 with the same storm. S drops to 1.11 in, Ia to 0.22 in, and Q rises to about 3.88 in. Higher CN means less retention and more runoff.

Source: USDA NRCS, TR-55 Urban Hydrology for Small Watersheds, 2nd ed. (June 1986), copy hosted by San Diego State University, Eqs. 2-1, 2-2 and 2-4, p. 2-1

By Castleport Test Prep Editorial Team · Exam facts last verified October 8, 2026

Topic weights · References for my test date · Worked examples · All 40 problems · 12-week plan

The exam at a glance

  • 80 questions, computer-based, year-round at Pearson VUE test centers
  • 8 hours of exam time inside a 9-hour appointment (2-minute nondisclosure agreement, 8-minute tutorial, 50-minute scheduled break)
  • Multiple-choice questions plus alternative formats such as multiple-correct, point-and-click, drag-and-drop, and fill-in-the-blank
  • Both SI and U.S. customary units
  • $400 exam fee paid to NCEES; your licensing board may charge its own application fee
  • References are supplied on screen: the NCEES PE Civil Reference Handbook plus the design standards listed for your test date. You can't bring your own.
  • Results are pass/fail, typically 7–10 days after the exam
  • First-time pass rate: 71% of 2,620 examinees (January–June 2026)

Sources: NCEES PE Civil exam page; PE Civil: WRE exam specifications, effective April 2024, p. 1; NCEES Examinee Guide, May 2026, pp. 11, 14, 16.

What to study first: the 12 areas by weight

NCEES publishes a question range for each of the 12 knowledge areas. Here they are, heaviest first. The ranges are numbers of questions out of 80, not percentages.

What to study first: the 12 areas by weight
RankKnowledge areaQuestionsWhat it coversPractice here
1Project Sitework9–14Excavation and embankment (grading, cut and fill); construction site layout and control; temporary and permanent erosion and sediment control; impact of construction on adjacent facilities; safety; basic horizontal and vertical curve elements; retaining walls; construction methodsProblems 37–40
2Hydrology8–12Storm characteristics; runoff analysis (rational and SCS/NRCS methods); hydrograph development, including synthetic hydrographs; rainfall intensity, duration, frequency, and probability of exceedance; time of concentration; rainfall and stream gauging stations; depletions; stormwater management and treatmentProblems 1–4
3Hydraulics–Closed Conduit7–11Energy and continuity equations (Bernoulli, grade lines, momentum); pressure conduits (single pipe, force mains, Hazen-Williams, Darcy-Weisbach, major and minor losses); pump application and analysis, including wet wells, lift stations, and cavitation; pipe networks (series, parallel, loops)Problems 15–18
3Hydraulics–Open Channel7–11Open-channel flow; hydraulic grade lines and energy dissipation (plunge pools, drop structures, culvert outlets); stormwater collection and drainage (culverts, inlets, gutter, street, and storm sewer flow); sub- and supercritical flowProblems 19–21
3Wastewater Collection and Treatment7–11Collection systems (lift stations, sewer networks, infiltration and inflow, smoke testing, maintenance, odor control); treatment systems; preliminary, primary, and secondary treatment; nutrient removal; solids treatment, handling, and disposal; disinfection; advanced treatmentProblems 33–36
6Analysis and Design6–9Mass balance; hydraulic loading; solids loading (sediment, sludge); hydraulic flow measurementProblems 12–14
6Drinking Water Distribution and Treatment6–9Distribution systems; treatment processes; present, short-term, and long-term demands; storage; sedimentation; coagulation and flocculation; membranes and media filtration; disinfection and disinfection byproducts; hardness and softening; other treatment (ion exchange, carbon adsorption, ozone, UV, specific constituent removal)Problems 29–32
8Surface Water and Groundwater Quality5–8Stream degradation and oxygen dynamics; total maximum daily loads (nutrients, DO, load allocation); biological and chemical contaminantsProblems 25–28
9Project Planning4–6Quantity take-off; cost estimating; project schedules; activity identification and sequencing; economic and sustainability analysis (present worth, lifecycle costs, comparing alternatives)Problems 5–6
9Materials4–6Soil classification and boring logs; soil properties (strength, permeability, compressibility, phase relationships); concrete; piping materials; test methods and specification conformanceProblems 9–11
9Groundwater and Wells4–6Aquifers; groundwater flow; well and drawdown analysisProblems 22–24
12Soil Mechanics3–5Lateral earth pressure; consolidation and compaction; bearing capacity; settlement; slope stabilityProblems 7–8

The ranges and topic lists are NCEES's (specifications, pp. 1–3); the ranking is ours, and it says nothing about which topics are hardest. Three things stand out:

  • Sitework has the highest published question range. Earthwork, erosion control, trench safety, and curves can be 9 to 14 questions. The ranges overlap, so it won't necessarily outnumber every water topic on a particular exam. Don't skip it because it doesn't feel like "water."
  • Hydrology and the two hydraulics areas together are 22 to 34 questions. That's the core of the exam.
  • Planning, soils, materials, and sitework add up to 20 to 31 questions (our arithmetic: 4 + 3 + 4 + 9 and 6 + 5 + 6 + 14). If you work in treatment or drainage every day, those are probably your blind spots.

The combined figures add the published minimum and maximum counts; these are not separate NCEES allocations or a promise that the groups’ maximum counts can occur together.

Which references you'll get on exam day

NCEES supplies the handbook and a specific list of design standards as searchable PDFs. Your test date decides the list. The topics above don't change. Both NCEES documents carry the same April 2024 topic pages; only the reference list is updated for April 2027.

Which references you'll get on exam day
Reference supplied on screenExams before April 2027Exams beginning April 2027What it means for you
NCEES PE Civil Reference HandbookCurrent versionCurrent versionDownload it free in MyNCEES and practice searching it
Recommended Standards for Wastewater Facilities (Ten States Standards)20142014No change
Recommended Standards for Water Works (Ten States Standards)20182022Section numbers shift (2018 §4.9.10, printed p. 93, is 2022 §4.10.10, printed p. 116), and new policy statements were added, including one on potable water reuse (2022, printed pp. v–vii)
29 CFR Part 1926, Safety and Health Regulations for Construction (listed subparts, including P, Excavations, and M, Fall Protection)Not listed2024, addedTrench sloping and other construction-safety rules become a supplied lookup
USACE EM 1110-2-1902, Slope StabilityNot listed2003, addedFactor-of-safety criteria and analysis conditions
FHWA HDS-5, Hydraulic Design of Highway CulvertsNot listed3rd ed., 2012, addedCulvert inlet and outlet control
FHWA HEC-14, Hydraulic Design of Energy Dissipators for Culverts and ChannelsNot listed3rd ed., 2006, addedOutlet velocity, scour, hydraulic jumps, stilling basins, riprap, drop structures
UFC 3-220-05, Dewatering and Groundwater ControlNot listed2004, addedConstruction dewatering methods and design

Sources: design standards for exams before April 2027, PDF p. 4; design standards for exams beginning April 2027, PDF pp. 4–5.

"Not listed" refers only to the supplied-reference list. Culverts, energy dissipation, slope stability, and construction safety were already on the April 2024 topic list. What changes in April 2027 is the supplied-reference list and the applicable listed editions. NCEES also states that answers to standards-based questions are scored against the listed editions; solutions based on other standards won't receive credit.

Study the references for your booked test date. If you move the appointment across April 2027, switch to the corresponding list and recheck the editions.

Free copies of the listed references

Every design standard on the WRE lists comes from a government agency or an interstate board of state health agencies, so you can study from the actual documents. Read the edition that matches your test date.

Free copies of the listed references
ReferenceEdition to studyWhere to read it
NCEES PE Civil Reference HandbookCurrent versionMyNCEES (free account)
Recommended Standards for Wastewater Facilities2014GLUMRB 2014 full PDF (mirror) · Official Minnesota archive
Recommended Standards for Water Works2018 (before April 2027)Copy hosted by the New York State Department of Health
Recommended Standards for Water Works2022 (April 2027 and later)Copy hosted by the Iowa Department of Natural Resources
29 CFR Part 19262024 (April 2027 and later)GovInfo annual 2024 edition record
EM 1110-2-1902, Slope Stability2003 (April 2027 and later)ASDSO Dam Safety Toolbox
HDS-5, Hydraulic Design of Highway Culverts3rd ed., 2012 (April 2027 and later)FHWA publication page and full PDF
HEC-14, Energy Dissipators3rd ed., 2006 (April 2027 and later)FHWA publication page
UFC 3-220-05, Dewatering and Groundwater Control2004 (April 2027 and later)WBDG archived PDF (marked inactive by the publisher; this 2004 edition remains on NCEES's April 2027 list)

Watch the wastewater edition. The Ten States board has released a 2026 edition of the Recommended Standards for Wastewater Facilities. NCEES still lists the 2014 edition for both test-date windows, so study 2014 (Minnesota Department of Health standards page).

Practice finding the rule, not just a word

On exam day you search the supplied PDFs with a search box on the left side of the reference window; Ctrl+F doesn't work (Examinee Guide, p. 10). Design standards open one chapter at a time. Knowing which document answers which kind of question saves more time than any search trick.

Practice finding the rule, not just a word
If the problem is about…Start in…
Equations for hydraulics, hydrology, groundwater, water quality, treatment, soils, and economicsNCEES PE Civil Reference Handbook
Water treatment and distribution design criteriaRecommended Standards for Water Works (edition for your date)
Sewer and wastewater treatment design criteria, such as minimum sewer slopes and velocitiesRecommended Standards for Wastewater Facilities, 2014
Culvert inlet or outlet control (April 2027 and later)HDS-5
Outlet protection, scour, jumps, stilling basins, drop structures (April 2027 and later)HEC-14
Trench sloping, egress, fall protection (April 2027 and later)29 CFR 1926
Slope factor-of-safety criteria (April 2027 and later)EM 1110-2-1902
Construction dewatering (April 2027 and later)UFC 3-220-05

A good lookup drill takes five steps. Pick a problem you've already solved on this page. Name the document you'd expect to need. Search a distinctive technical term. Read the variable definitions and nearby conditions. Then write down where you found it. Keep a log, and repeat the slow lookups until they're fast:

Practice finding the rule, not just a word
TopicDocument and editionSection foundSearch term that workedTime to findWhat slowed you down
(example) Minimum sewer velocityWastewater Facilities, 2014Section 33.41, Recommended Minimum Slopes"minimum slopes"2 minSearched "velocity" first and got dozens of hits

Two worked examples

These walk through every step, so you can see the method before you try the problems. Both are original, unofficial practice in SI units.

Worked example 1 · Pipe losses, pump head, and shaft power (SI)

WRE-WX01 · Area 5, Hydraulics–Closed Conduit · Original, unofficial practice

A pump transfers 0.0400 m³/s of water between two large reservoirs open to the atmosphere. The receiving water surface is 18.0 m above the source water surface. The pipe is 400 m long with a 0.200 m inside diameter, and the Darcy friction factor at this flow is 0.0240. The entrance, exit, and fitting loss coefficients add up to ΣK = 4.00, based on pipe velocity. Pump efficiency is 72.0%. Use ρ = 1,000 kg/m³ and g = 9.81 m/s². Reservoir surface velocities are negligible. Find the required pump head and the pump shaft power.

Step 1. Find the pipe velocity. A = πD²/4 = π(0.200)²/4 = 0.03142 m². V = Q/A = 0.0400/0.03142 = 1.273 m/s. Velocity head V²/2g = 1.273²/(2 × 9.81) = 0.0826 m.

Step 2. Calculate the losses. Friction (Darcy-Weisbach): h_f = f(L/D)(V²/2g) = 0.0240 × (400/0.200) × 0.0826269 ≈ 3.966 m. Local losses: h_m = ΣK(V²/2g) = 4.00 × 0.0826269 ≈ 0.331 m.

Step 3. Add up the pump head. H = Δz + h_f + h_m = 18.0 + 3.966 + 0.331 = 22.30 m, or 22.3 m.

Step 4. Convert to shaft power. Hydraulic power = ρgQH = 1,000 × 9.81 × 0.0400 × 22.2966 ≈ 8,749.18 W. Shaft power = 8,749.18/0.720 ≈ 12,152 W = 12.2 kW.

Check: Shaft power (12.2 kW) is larger than hydraulic power (8.75 kW), as it must be. The exit loss is already inside ΣK, so don't add another velocity head for it. Motor efficiency wasn't given, so 12.2 kW is shaft power, not electrical input. Problem 15 extends this to electrical input.

Source: FHWA HDS-4, Introduction to Highway Hydraulics, metric version (June 1997), Section 6.2 (energy equation) and Sections 6.3.1–6.3.2 (friction and local losses); U.S. DOE, Improving Pumping System Performance: A Sourcebook for Industry, 2nd ed. (May 2006), Fluid power and pump efficiency, printed p. 9 (PDF p. 13)

Worked example 2 · Detention time and F/M in activated sludge (SI)

WRE-WX02 · Area 11, Wastewater Collection and Treatment · Original, unofficial practice

An activated-sludge plant runs two aeration basins, each with 600 m³ of working volume. Forward flow is 4,800 m³/day, and the BOD₅ (5-day biochemical oxygen demand) entering aeration is 180 mg/L. Mixed-liquor suspended solids (MLSS) are 3,200 mg/L, and 75% of those are volatile (mixed-liquor volatile suspended solids, MLVSS). Use forward flow for detention time and the aeration-basin MLVSS inventory only for the food-to-microorganism ratio (F/M). Find the nominal detention time and F/M. Then find the aeration volume needed to keep both values if flow rises to 7,200 m³/day with the same BOD₅ and MLVSS concentrations.

Step 1. Detention time. Total volume = 2 × 600 = 1,200 m³. θ = V/Q = 1,200/4,800 = 0.250 day = 6.00 hours.

Step 2. Food (BOD₅ load). 180 mg/L = 0.180 kg/m³. F = 4,800 × 0.180 = 864 kg BOD₅/day.

Step 3. Microorganisms (MLVSS inventory). MLVSS = 0.75 × 3,200 = 2,400 mg/L = 2.40 kg/m³. M = 1,200 × 2.40 = 2,880 kg MLVSS.

Step 4. F/M. F/M = 864/2,880 = 0.300 kg BOD₅ per kg MLVSS per day. Using MLSS instead (3.20 kg/m³) would give 0.225, which is on a different solids basis.

Step 5. Higher flow. In the existing basins, θ = 1,200/7,200 × 24 = 4.00 hours and F/M = (7,200 × 0.180)/2,880 = 1,296/2,880 = 0.450. To get back to 6.00 hours: V = 7,200 × 6/24 = 1,800 m³, or 600 m³ more. At 2.40 kg/m³ that volume holds 4,320 kg MLVSS, so F/M = 1,296/4,320 = 0.300 again.

Check: A 50% flow increase needs 50% more volume to hold both values when concentrations stay fixed. These numbers don't predict effluent quality or set the SRT; Problem 35 covers SRT.

Source: EPA, Preventive Maintenance for Small Public Water Systems Using Ground Water: Tasks and Logs, Detention time = volume ÷ flow, p. 5; EPA, Process Control Manual for Aerobic Biological Wastewater Treatment Facilities (1977), Section 2.04, food-to-microorganism ratio using aeration-basin MLVSS inventory, printed pp. II-43–II-44

40 original practice problems with worked solutions

These are original Castleport problems written to the NCEES WRE topic list. They are not NCEES questions. The set covers all 12 knowledge areas, but it isn't a full-length exam, it isn't weighted like the real one, and it doesn't cover every subtopic. Most problems are single-answer multiple choice; a few use formats like the real exam's enter-a-number and select-two items. On the actual exam, scored questions, including those formats, are scored right or wrong with no partial credit (Examinee Guide, p. 11).

Work each problem before you open its solution. Carry unrounded values through intermediate steps and round the final answer as requested. When you miss one, write down the first step that went wrong; the error log below shows what to do with it.

Area 7: Hydrology (4 problems)

Problem 1, NRCS curve-number runoff depth, is at the top of this page.

Problem 2 · Risk of exceedance over a design life

WRE-HYD-02 · Area 7, Hydrology · Select one

A culvert is sized for the 100-year flood. Its design life is 30 years. Assuming independent years, what is the probability that the design flood is equaled or exceeded at least once during the design life?

  • A. 1%
  • B. 26%
  • C. 30%
  • D. 74%
Show answer and solution

Answer: B. 26%.

The annual exceedance probability is 1/100 = 0.01, so the chance of no exceedance in a year is 0.99. Over 30 independent years: risk = 1 − (0.99)³⁰ = 1 − 0.740 = 0.260, or about 26%.

Why not the others: A is the annual probability. C adds 1% per year for 30 years, which overstates the risk. D is the probability of no exceedance at all.

Source: Ventura County Public Works, Flood statistics: commonly asked questions (risk equation), Risk = 1 − (1 − 1/T)ⁿ, with a 50-year worked example

Problem 3 · TR-55 sheet-flow travel time

WRE-HYD-03 · Area 7, Hydrology · Select one

Use the TR-55 sheet-flow equation Tt = 0.007(nL)^0.8 / (P₂^0.5 · s^0.4), with Tt in hours. The flow path is 100 ft of dense grass (n = 0.24), the 2-year, 24-hour rainfall is P₂ = 3.6 in, and the land slope is 0.02 ft/ft. What is the sheet-flow travel time?

  • A. 0.22 min
  • B. 2.1 min
  • C. 7.1 min
  • D. 13.5 min
Show answer and solution

Answer: D. 13.5 min.

nL = 0.24 × 100 = 24. (24)^0.8 = 12.71. P₂^0.5 = 1.897 and s^0.4 = (0.02)^0.4 = 0.2091. Tt = 0.007 × 12.71 / (1.897 × 0.2091) = 0.224 hr = 13.5 min. The 100-ft length is within TR-55's sheet-flow limit of less than 300 ft.

Why not the others: A reports the 0.224 result as minutes instead of hours. B enters the slope as 2 (percent) instead of 0.02 ft/ft. C forgets the square root on P₂.

Source: USDA NRCS, TR-55 Urban Hydrology for Small Watersheds, 2nd ed. (June 1986), copy hosted by San Diego State University, Eq. 3-3 and Table 3-1 (dense grasses n = 0.24), p. 3-3; 300-ft limit, pp. 3-3 to 3-4

Problem 4 · Rational method with mixed land use (SI)

WRE-HYD-04 · Area 7, Hydrology · Select one

A 4.00 ha catchment has 1.50 ha with C = 0.90 and 2.50 ha with C = 0.30. Time of concentration is 15 min, and the design intensity for that duration is 60 mm/h. Assume the rational method applies (small area, uniform rainfall, no significant storage). A downstream drain can carry 0.320 m³/s. Use Q = CiA/360 (Q in m³/s, i in mm/h, A in ha). Which result is correct?

  • A. 0.035 m³/s; below the drain capacity
  • B. 0.350 m³/s; exceeds the drain capacity
  • C. 0.400 m³/s; exceeds the drain capacity
  • D. 0.667 m³/s; exceeds the drain capacity
Show answer and solution

Answer: B. 0.350 m³/s; exceeds the drain capacity.

Weight C by area: C = (1.50 × 0.90 + 2.50 × 0.30)/4.00 = (1.35 + 0.75)/4.00 = 0.525. Then Q = 0.525 × 60 × 4.00/360 = 0.350 m³/s, which is 0.030 m³/s more than the drain can carry.

Why not the others: A slips a factor of 10 in the unit conversion. C averages the two coefficients (0.60) without weighting by area. D leaves out C entirely, as if all rain ran off.

Source: TxDOT Hydraulic Design Manual, Chapter 4, Section 12: Rational Method, Eq. 4-20 (Z = 360 for metric), Eq. 4-23 (mixed land use), and Assumptions and Limitations

Area 1: Project Planning (2 problems)

Problem 5 · Present worth of two alternatives

WRE-PP-01 · Area 1, Project Planning · Select one

Two pump-station alternatives each last 20 years with no salvage value; interest is 6% per year. Alternative A costs $40,000 now plus $6,000 per year in operation and maintenance (O&M). Alternative B costs $55,000 now plus $3,500 per year in O&M. O&M is paid at the end of each year. Which alternative has the lower present worth of costs, and what are the two present worths?

  • A. The two are within 1% of each other
  • B. Choose A: its first cost is $15,000 lower
  • C. Choose B: total cost $125,000 vs. $160,000 for A
  • D. Choose B: present worth about $95,100 vs. about $108,800 for A
Show answer and solution

Answer: D. Choose B: present worth about $95,100 vs. about $108,800 for A.

The uniform-series present worth factor is (P/A, 6%, 20) = [(1.06)²⁰ − 1] / [0.06(1.06)²⁰] = 11.4699. PW of A = 40,000 + 6,000 × 11.4699 = $108,820. PW of B = 55,000 + 3,500 × 11.4699 = $95,145. B is about $13,700 cheaper in present-worth terms.

Why not the others: A isn't supported by either calculation; the gap is about 13% of A's present worth. B looks only at first cost and ignores 20 years of O&M. C reaches the right choice but adds undiscounted dollars, which ignores the time value of money.

Source: NIST IR 85-3273-39, Energy Price Indices and Discount Factors for Life-Cycle Cost Analysis – 2024 (March 2024), Section 2.1, uniform present value factor, printed p. 5 (PDF p. 13); the 6% rate and project costs are supplied exercise inputs

Problem 6 · Critical path and project duration

WRE-PP-02 · Area 1, Project Planning · Select one

All links below are finish-to-start with no lag, resources allow parallel work, and the project starts at time zero.

Problem 6 · Critical path and project duration
ActivityDuration (working days)Immediate predecessor
A: Site preparation2None
B: Equipment procurement6A
C: Excavation4A
D: Installation3B and C
E: Testing2D

What is the earliest project completion time?

  • A. 8 working days
  • B. 11 working days
  • C. 13 working days
  • D. 17 working days
Show answer and solution

Answer: C. 13 working days.

A finishes at day 2. B finishes at 2 + 6 = 8 and C at 2 + 4 = 6. D cannot start until both B and C finish, so it starts at day 8 and finishes at 11. E finishes at 13. The critical path, the longest path through the network, is A–B–D–E.

Why not the others: A stops when B finishes. B follows the shorter A–C–D–E path and forgets that D must wait for B. D adds every duration, as if B and C ran one after the other.

Source: GAO-16-89G, Schedule Assessment Guide (Dec. 2015), Critical path and total float definitions, pp. 4 and 6

Area 2: Soil Mechanics (2 problems)

Problem 7 · Primary consolidation settlement (SI)

WRE-SOIL-01 · Area 2, Soil Mechanics · Select one

A normally consolidated clay layer is 3.0 m thick, with initial void ratio e₀ = 0.80 and compression index Cc = 0.18. The effective vertical stress at mid-layer rises from 100 kPa to 200 kPa. Estimate primary consolidation settlement only.

  • A. 30.1 mm
  • B. 90.3 mm
  • C. 162.6 mm
  • D. 207.9 mm
Show answer and solution

Answer: B. 90.3 mm.

For a normally consolidated layer: Sc = [Cc·H₀/(1 + e₀)] · log₁₀(σ′f/σ′₀) = (0.18 × 3.0/1.80) × log₁₀(2) = 0.300 × 0.3010 = 0.0903 m = 90.3 mm.

Why not the others: A leaves out the layer thickness. C forgets to divide by 1 + e₀. D uses the natural log, but Cc is defined with log₁₀. None of these adds immediate or secondary settlement, which the question excludes.

Source: FHWA-NHI-06-088, Soils and Foundations Reference Manual, Vol. I (Dec. 2006), Section 7.5.2.1, Normally Consolidated Soils, p. 7-24

Problem 8 · Slope stability: minimum factor of safety lookup

WRE-SOIL-02 · Area 2, Soil Mechanics · Select one

Reference note: this standard is on the supplied list for exams beginning April 2027. The skill applies either way.

A limit-equilibrium analysis of the downstream slope of a proposed new earth dam gives a factor of safety of 1.42 for long-term steady seepage at maximum storage pool (spillway crest or top of gates). Compare it with the minimum required factors of safety in USACE EM 1110-2-1902 (2003), Table 3-1. Which statement is correct?

  • A. It does not meet the minimum, because 1.5 is required for this condition
  • B. It meets the minimum, because 1.3 is required for this condition
  • C. It meets the minimum, because any value above 1.0 is stable
  • D. It meets the minimum, because 1.4 is required for this condition
Show answer and solution

Answer: A. It does not meet the minimum; 1.5 is required.

EM 1110-2-1902, Table 3-1 lists a minimum of 1.5 for the downstream slope under long-term steady seepage at maximum storage pool (spillway crest or top of gates) for new earth and rock-fill dams. 1.42 is below that, so the slope needs redesign (for example, a flatter slope or better drainage) before it meets the criterion.

Why not the others: B uses the 1.3 minimum that Table 3-1 gives for end-of-construction conditions, not long-term steady seepage. C confuses the theoretical stability threshold (FS = 1.0) with a design minimum. D isn't a value the table gives for this condition.

Try a change: Same dam, end-of-construction condition, FS = 1.42. Now the slope exceeds the table's listed 1.3 minimum. However, footnote 2 says a higher minimum may be appropriate for a dam over 50 ft high on a soft foundation, or for a dam subjected to pool loading during construction. The loading condition and footnotes decide which criterion applies.

Source: USACE EM 1110-2-1902, Slope Stability (31 Oct. 2003), Table 3-1, Minimum Required Factors of Safety: New Earth and Rock-Fill Dams, printed p. 3-2, including footnote 2; Original USACE Table 3-1 reproduced in a TCU report, hosted by Brazil’s Câmara dos Deputados, Figure 15, printed/PDF p. 47, complete table and footnotes

Area 3: Materials (3 problems)

Problem 9 · Field dry density and relative compaction

WRE-MAT-01 · Area 3, Materials · Select one

A field specimen has a moist mass of 3.24 kg, an oven-dry mass of 2.70 kg, and an in-place volume of 0.00150 m³. The laboratory maximum dry density for this material and compaction test is 2,000 kg/m³. The project requires at least 95% of that maximum. Which result is correct?

  • A. 1,800 kg/m³; does not meet the requirement
  • B. 1,800 kg/m³; meets the requirement
  • C. 2,160 kg/m³; meets the requirement
  • D. 2,160 kg/m³; does not meet the requirement
Show answer and solution

Answer: A. 1,800 kg/m³; does not meet the requirement.

Dry density uses the dry mass: 2.70/0.00150 = 1,800 kg/m³. Relative compaction = 1,800/2,000 = 90%, which is below the 95% requirement.

Why not the others: B gets the density right but misreads the comparison. C and D use the moist mass (3.24 kg), which gives a wet density of 2,160 kg/m³, not dry density.

Source: FHWA-NHI-06-088, Soils and Foundations Reference Manual, Vol. I (Dec. 2006), Section 2.1.3 (weight-volume ratios), p. 2-5; Table 2-2, p. 2-8; Section 5.8.3 and Eq. 5-19 (relative compaction), pp. 5-76–5-77

Problem 10 · Phase relationships for a saturated soil

WRE-MAT-02 · Area 3, Materials · Enter a number

A fully saturated clay has a water content of 15% and a specific gravity of solids Gs = 2.70. Use γw = 62.4 pcf. Enter the dry unit weight in pcf, rounded to the nearest whole number.

Show answer and solution

Answer: 120 pcf.

For a saturated soil, S = 1, so Se = wGs gives e = 0.15 × 2.70 = 0.405. Dry unit weight γd = Gs·γw/(1 + e) = 2.70 × 62.4/1.405 = 119.9 pcf, or 120 pcf.

Common mistakes: Setting e equal to the water content (0.15) gives about 147 pcf. Computing the saturated unit weight, (Gs + e)γw/(1 + e), gives about 138 pcf, which answers a different question.

Source: FHWA-NHI-06-088, Soils and Foundations Reference Manual, Vol. I (Dec. 2006), Sections 2.1.3–2.1.4 and Table 2-2, Weight-volume relations, pp. 2-5 to 2-8

Problem 11 · Constant-head permeability test

WRE-MAT-03 · Area 3, Materials · Select one

In a constant-head permeability test, 500 cm³ of water passes through a sample in 300 s. The sample is 20 cm long with a cross-sectional area of 80 cm², and the head difference across it is 40 cm. What is the hydraulic conductivity k?

  • A. 1.0 × 10⁻² cm/s
  • B. 4.2 × 10⁻² cm/s
  • C. 5.2 × 10⁻⁴ cm/s
  • D. 3.1 cm/s
Show answer and solution

Answer: A. 1.0 × 10⁻² cm/s.

Darcy's law, Q = kA(h/L), rearranges to k = VL/(Aht), where V is the volume collected in time t. k = (500 × 20)/(80 × 40 × 300) = 10,000/960,000 = 0.0104 cm/s.

Why not the others: B flips the gradient (uses L/h instead of h/L). C leaves out the sample length. D forgets to divide by the 300-s test time.

Source: University of Connecticut, Groundwater Education and Research Program: Darcy Column Test for Permeability, Darcy-law equation and variable definitions below the column-test diagram, Q = K A dh/L; constant-head procedure, Q = Volume/time; FHWA-NHI-06-088, Soils and Foundations Reference Manual, Vol. I (Dec. 2006), Section 5.6, Permeability, p. 5-58

Area 4: Analysis and Design (3 problems)

Problem 12 · Solids mass balance and sludge volume

WRE-AD-01 · Area 4, Analysis and Design · Select one

A solids-separation process receives 8,000 m³/day with 150 mg/L of suspended solids and captures 60% of the incoming dry solids. All captured solids leave in one sludge stream that is 3.0% dry solids by wet mass, with a wet density of 1,000 kg/m³. Assume no chemical or biological solids production. What sludge volume leaves the process each day?

  • A. 14.4 m³/day
  • B. 24.0 m³/day
  • C. 40.0 m³/day
  • D. 240 m³/day
Show answer and solution

Answer: B. 24.0 m³/day.

150 mg/L = 0.150 kg/m³, so incoming solids = 8,000 × 0.150 = 1,200 kg/day. Captured solids = 0.60 × 1,200 = 720 kg/day. Each cubic meter of sludge holds 0.030 × 1,000 = 30.0 kg of dry solids, so sludge volume = 720/30.0 = 24.0 m³/day.

Why not the others: A applies the 60% capture twice. C sends all incoming solids to the sludge. D treats 3.0% as 0.003 instead of 0.030.

Source: MIT OpenCourseWare 1.061 Transport Processes in the Environment (Fall 2008), Lecture 2: Conservation of Mass, Integral conservation-of-mass statement, Eq. (4), reduced here to a steady balance

Problem 13 · Clarifier surface overflow rate

WRE-AD-02 · Area 4, Analysis and Design · Select one

Two identical circular primary clarifiers, each 60 ft in diameter, split a total flow of 4.0 MGD equally. What is the surface overflow rate?

  • A. 0.71 gpd/ft²
  • B. 177 gpd/ft²
  • C. 707 gpd/ft²
  • D. 1,415 gpd/ft²
Show answer and solution

Answer: C. 707 gpd/ft².

Surface overflow (surface loading) rate = flow ÷ surface area. Each clarifier has area π(30)² = 2,827 ft², so the two total 5,655 ft². Rate = 4,000,000 gpd/5,655 ft² = 707 gpd/ft². Compare the result with the design criteria in the wastewater standard supplied for your exam rather than a remembered number.

Why not the others: A converts 4.0 MGD to 4,000 gpd instead of 4,000,000 gpd. B uses the 60-ft diameter as a radius. D sends all 4.0 MGD through one clarifier.

Source: Sacramento State College for EPA, Operation of Wastewater Treatment Plants: A Field Study Training Program, Surface Settling Rate or Surface Loading Rate, printed p. 5-34; flow in gpd divided by liquid surface area in ft²

Problem 14 · Suppressed rectangular weir

WRE-AD-03 · Area 4, Analysis and Design · Select one

A sharp-crested rectangular weir is suppressed (no end contractions). Assume the USBR standard installation and free-flow conditions are satisfied. The crest is 4.0 ft long and the measured head is 0.75 ft. Use the Francis form Q = 3.33LH^1.5 (Q in cfs, L and H in ft). What is the flow?

  • A. 7.49 cfs
  • B. 8.33 cfs
  • C. 8.65 cfs
  • D. 9.99 cfs
Show answer and solution

Answer: C. 8.65 cfs.

Q = 3.33 × 4.0 × (0.75)^1.5 = 3.33 × 4.0 × 0.6495 = 8.65 cfs.

Why not the others: A raises H to the second power. B shortens the crest for two end contractions (L − 0.2H), which applies only to contracted weirs; this weir is suppressed. D raises H to the first power.

Source: USBR Water Measurement Manual, Chapter 7, Section 10: Standard Suppressed Rectangular Weir, Francis equation for the standard suppressed rectangular weir, Eq. 7-5

Area 5: Hydraulics–Closed Conduit (4 problems)

Problem 15 · Hydraulic, shaft, and electrical power (SI)

WRE-CC-01 · Area 5, Hydraulics–Closed Conduit · Select one

A pump moves 0.060 m³/s of water between two large reservoirs open to the atmosphere. The receiving water surface is 12.0 m higher, and total pipe and fitting losses are 8.0 m at this flow. Reservoir surface velocities are negligible. Pump efficiency is 75% and motor efficiency is 90%. Use ρ = 1,000 kg/m³ and g = 9.81 m/s². What electrical input power is required?

  • A. 7.95 kW
  • B. 11.8 kW
  • C. 15.7 kW
  • D. 17.4 kW
Show answer and solution

Answer: D. 17.4 kW.

The pump must add H = 12.0 + 8.0 = 20.0 m. Hydraulic (fluid) power = ρgQH = 1,000 × 9.81 × 0.060 × 20.0 = 11,772 W. Shaft power = 11,772/0.75 = 15,696 W. Electrical input = 15,696/0.90 = 17,440 W = 17.4 kW.

Why not the others: A multiplies by both efficiencies instead of dividing. B stops at hydraulic power. C stops at shaft power and ignores motor losses.

Source: U.S. DOE, Improving Pumping System Performance: A Sourcebook for Industry, 2nd ed. (May 2006), Fluid power and pump efficiency, printed p. 9 (PDF p. 13); shaft power divided by motor efficiency, Simple Calculation, printed p. 58 (PDF p. 62); FHWA HDS-4, Introduction to Highway Hydraulics, metric version (June 1997), Section 6.2, energy equation and losses

Problem 16 · Hazen-Williams head loss (U.S. units)

WRE-CC-02 · Area 5, Hydraulics–Closed Conduit · Select one

Use the Hazen-Williams form h = 4.727 L Q^1.852 / (C^1.852 d^4.871), with h, L, and d in feet and Q in cfs. Water flows at 3.0 cfs through 2,000 ft of 12-in pipe with C = 120. What is the friction head loss?

  • A. 5.1 ft
  • B. 10.2 ft
  • C. 14.3 ft
  • D. 20.4 ft
Show answer and solution

Answer: B. 10.2 ft.

d = 12 in = 1.0 ft, so d^4.871 = 1. h = 4.727 × 2,000 × 3.0^1.852 / 120^1.852 = 4.727 × 2,000 × 7.6494/7,089.958 ≈ 10.2 ft.

Why not the others: A uses 1,000 ft of pipe. C uses C = 100 (rougher pipe). D doubles the correct result.

Try a change: Double the flow to 6.0 cfs. Head loss rises by 2^1.852 = 3.6 times, to about 36.8 ft. Loss grows much faster than flow.

Source: U.S. EPA, EPANET 2.2 User Manual, Section 3.1, Table 3.1: Pipe Headloss Formulas for Full Flow, Table 3.1, Hazen-Williams resistance coefficient and flow exponent (feet, cfs)

Problem 17 · Darcy-Weisbach friction loss

WRE-CC-03 · Area 5, Hydraulics–Closed Conduit · Select one

Water flows at 2.5 cfs through 1,000 ft of 12-in pipe. The Darcy friction factor is f = 0.020. What is the friction head loss?

  • A. 0.16 ft
  • B. 1.94 ft
  • C. 3.15 ft
  • D. 6.29 ft
Show answer and solution

Answer: C. 3.15 ft.

Area = π(1.0)²/4 = 0.7854 ft², so V = 2.5/0.7854 = 3.18 ft/s. h = f(L/D)V²/(2g) = 0.020 × (1,000/1.0) × (3.18)²/(2 × 32.2) = 0.020 × 1,000 × 0.157 = 3.15 ft. The same answer follows from EPANET's flow form, h = 0.0252 f L Q²/d⁵.

Why not the others: A is only the velocity head, V²/2g. B plugs the flow (2.5) in where the velocity belongs. D drops the 2 in 2g.

Source: U.S. EPA, EPANET 2.2 User Manual, Section 3.1, Table 3.1: Pipe Headloss Formulas for Full Flow, Table 3.1, Darcy-Weisbach resistance coefficient (feet, cfs); FHWA HDS-4, Introduction to Highway Hydraulics, metric version (June 1997), Section 6.3.1, friction losses

Problem 18 · NPSH available and cavitation

WRE-CC-04 · Area 5, Hydraulics–Closed Conduit · Select one

A pump draws from an open sump whose water surface is 12.0 ft below the pump centerline. Atmospheric pressure head is 33.9 ft, suction-line friction loss is 2.0 ft, and the vapor pressure head of the water is 0.84 ft. The sump surface velocity is negligible, and the stated suction-line loss includes all suction-side losses. The pump's required NPSH at the duty point is 22 ft. Which statement is correct?

  • A. NPSHa ≈ 19.1 ft; cavitation risk
  • B. NPSHa ≈ 43.1 ft; adequate
  • C. NPSHa ≈ 21.1 ft; cavitation risk
  • D. NPSHa ≈ 19.9 ft; cavitation risk
Show answer and solution

Answer: A. NPSHa ≈ 19.1 ft; cavitation risk.

For a suction lift, NPSHa = atmospheric head − static lift − friction − vapor pressure head = 33.9 − 12.0 − 2.0 − 0.84 = 19.06 ft. That is less than the 22 ft the pump requires, so it is at risk of cavitation, which occurs when pressure in the pump drops below the liquid's vapor pressure.

Why not the others: B adds the 12-ft lift as if the pump had a flooded suction. C ignores suction friction. D ignores vapor pressure. C and D still flag cavitation, but with the wrong NPSHa.

Source: Goulds Water Technology/Xylem, Water Products: Technical Data and Pump Fundamentals (Technical Manual TTECHWP R6), NPSHA for an open system with suction lift, Figure 4a, PDF p. 13; suction-pressure/velocity-head formulation, PDF p. 12; U.S. DOE, Improving Pumping System Performance: A Sourcebook for Industry, 2nd ed. (May 2006), Cavitation, printed p. 14; NPSH overview, printed p. 21; available-versus-required NPSH, printed pp. 38–39

Area 6: Hydraulics–Open Channel (3 problems)

Problem 19 · Manning capacity check (SI)

WRE-OC-01 · Area 6, Hydraulics–Open Channel · Select one

A rectangular channel is 4.00 m wide with water 1.00 m deep. Flow is steady and uniform, Manning's n = 0.020, and the bed slope is 0.0010 m/m. The required discharge is 5.00 m³/s. Using Q = (1/n)AR^(2/3)S^(1/2), which statement is correct at the stated depth?

  • A. 0.153 m³/s; below the required discharge
  • B. 3.43 m³/s; below the required discharge
  • C. 4.83 m³/s; below the required discharge
  • D. 6.32 m³/s; meets the required discharge
Show answer and solution

Answer: C. 4.83 m³/s; below the required discharge.

A = 4.00 × 1.00 = 4.00 m². The wetted perimeter counts the bed and both walls: P = 4.00 + 2(1.00) = 6.00 m. R = A/P = 0.667 m. Q = (1/0.020)(4.00)(0.667)^(2/3)(0.0010)^(1/2) = 4.83 m³/s, about 0.17 m³/s short at this depth.

Why not the others: A uses S instead of √S. B includes the free surface in the wetted perimeter. D uses the depth (1.00 m) in place of the hydraulic radius.

Source: FHWA HDS-4, Introduction to Highway Hydraulics, metric version (June 1997), Section 4.3.1, Manning's equation and hydraulic radius, Eqs. 13, 15 and 17

Problem 20 · Critical depth in a rectangular channel

WRE-OC-02 · Area 6, Hydraulics–Open Channel · Select one

A wide rectangular channel carries a unit discharge of q = 25 cfs per foot of width. What is the critical depth?

  • A. 0.92 ft
  • B. 2.69 ft
  • C. 4.03 ft
  • D. 19.4 ft
Show answer and solution

Answer: B. 2.69 ft.

At critical flow, Q²/g = A³/T. For a rectangular section this reduces to yc = (q²/g)^(1/3) = (25²/32.2)^(1/3) = (19.41)^(1/3) = 2.69 ft.

Why not the others: A uses q instead of q². C is the minimum specific energy, Ec = 1.5yc. D stops before taking the cube root.

Source: Design Manual Chapter 2 Stormwater, Section 2F-2 Open Channel Flow (2013 ed.), hosted by Iowa State University InTrans, Eq. 2F-2.07, critical flow condition, p. 5; FHWA HDS-4, Introduction to Highway Hydraulics, metric version (June 1997), Section 4.6.2, critical depth in rectangular channels, Eq. 33

Problem 21 · Froude number, flow regime, and specific energy

WRE-OC-03 · Area 6, Hydraulics–Open Channel · Select one

A rectangular channel 8.0 ft wide carries 120 cfs at a depth of 1.2 ft. Which set of results is correct?

  • A. Fr = 2.01; E = 3.63 ft; supercritical
  • B. Fr = 2.01; E = 3.63 ft; subcritical
  • C. Fr = 4.04; E = 3.63 ft; supercritical
  • D. Fr = 2.01; E = 6.05 ft; supercritical
Show answer and solution

Answer: A. Fr = 2.01; E = 3.63 ft; supercritical.

V = Q/A = 120/(8.0 × 1.2) = 12.5 ft/s. For a rectangular channel the hydraulic depth A/T equals y, so Fr = V/√(gy) = 12.5/√(32.2 × 1.2) = 2.01. Fr > 1, so the flow is supercritical. Specific energy E = y + V²/2g = 1.2 + 12.5²/64.4 = 3.63 ft.

Why not the others: B gets the numbers right but reverses the regime: Fr greater than 1 means supercritical. C reports Fr² as Fr. D drops the 2 in 2g.

Try a change: If this flow enters a mild downstream channel, check the downstream water depth and control conditions. A hydraulic jump may form if they force a transition to subcritical flow; the mild slope alone does not guarantee it. For exams starting April 2027, FHWA HEC-14 is on the supplied reference list for jumps and energy dissipators.

Source: Design Manual Chapter 2 Stormwater, Section 2F-2 Open Channel Flow (2013 ed.), hosted by Iowa State University InTrans, Eq. 2F-2.05 (specific energy), p. 3; Eq. 2F-2.08 and Fr > 1 supercritical, p. 6; hydraulic-jump conditions, pp. 8–9

Area 8: Groundwater and Wells (3 problems)

Problem 22 · Darcy flux vs. seepage velocity

WRE-GW-01 · Area 8, Groundwater and Wells · Select one

Steady saturated flow moves through a homogeneous aquifer. Hydraulic head drops from 101.8 m to 100.0 m over 300 m. Hydraulic conductivity is 12.0 m/day and effective porosity is 0.24. Assume the same gradient applies along a 120-m flow line, with advection only. Which pair gives the Darcy flux q and the average travel time along that line?

  • A. q = 0.072 m/day; 400 days
  • B. q = 0.072 m/day; 1,667 days
  • C. q = 0.300 m/day; 400 days
  • D. q = 0.0173 m/day; 6,944 days
Show answer and solution

Answer: A. q = 0.072 m/day; 400 days.

Gradient i = 1.8/300 = 0.0060. Darcy flux q = Ki = 12.0 × 0.0060 = 0.072 m/day. Water actually moves through the pores faster: v = q/nₑ = 0.072/0.24 = 0.300 m/day. Travel time = 120/0.300 = 400 days.

Why not the others: B uses the Darcy flux as the travel speed. C labels the pore velocity as the Darcy flux. D multiplies by porosity instead of dividing, then uses that as a speed.

Source: EPA, EPACMTP Parameters/Data Background Document (April 2003), Section 5.3.5, definition of seepage velocity and Eq. 5.8, printed p. 5-49 (PDF p. 154); v = Ki/nₑ and Darcy flux = nₑv

Problem 23 · Thiem equation for a confined aquifer

WRE-GW-02 · Area 8, Groundwater and Wells · Select one

A fully penetrating well pumps a confined aquifer at steady state. Hydraulic conductivity is 40 ft/day and the aquifer is 50 ft thick. Observation wells 10 ft and 100 ft from the pumping well show a head difference of 5.0 ft. What is the pumping rate? (1 ft³ = 7.48 gal.)

  • A. 19 gpm
  • B. 142 gpm
  • C. 326 gpm
  • D. 27,300 gpm
Show answer and solution

Answer: B. 142 gpm.

Transmissivity T = Kb = 40 × 50 = 2,000 ft²/day. The Thiem equation gives Q = 2πT(h₂ − h₁)/ln(r₂/r₁) = 2π × 2,000 × 5.0/ln(10) = 62,832/2.303 = 27,290 ft³/day. Convert: 27,290 × 7.48/1,440 = 142 gpm.

Why not the others: A stops at cubic feet per minute. C uses log₁₀ in place of the natural log. D labels the ft³/day result as gpm.

Source: EPA, Handbook: Ground Water and Wellhead Protection (September 1994), Eq. 3-1, printed pp. 51–52, for transmissivity; Section 4.5.2, Eq. 4-15, printed p. 80, for the Thiem equilibrium relation. The two-observation form is derived by subtracting the drawdowns at the two radii

Problem 24 · Water released from aquifer storage

WRE-GW-03 · Area 8, Groundwater and Wells · Enter a number

A confined aquifer has a storage coefficient (storativity) of 0.0004. Over an area of 2.0 square miles, the head declines an average of 10 ft. Enter the volume of water released from storage in acre-feet, to two decimals. (1 square mile = 640 acres.)

Show answer and solution

Answer: 5.12 acre-ft.

Volume released = S × area × head decline = 0.0004 × (2.0 × 640 acres) × 10 ft = 0.0004 × 1,280 × 10 = 5.12 acre-ft (about 223,000 ft³).

Common mistakes: Skipping the square-mile-to-acre conversion gives 0.008. Storativity in a confined aquifer is tiny, so a large head drop releases a modest volume.

Source: MIT OpenCourseWare 1.72 Groundwater Hydrology (Fall 2005), Lecture 7: Groundwater Storage, Specific-storage definition, p. 1, and S = Sₛb, p. 7; together give released volume = S × area × head decline

Area 9: Surface Water and Groundwater Quality (4 problems)

Problem 25 · Allowable tributary concentration (mass balance)

WRE-WQ-01 · Area 9, Surface Water and Groundwater Quality · Select one

A river carries 1.20 m³/s with 18.0 mg/L of a conservative dissolved constituent. A tributary adds 0.300 m³/s. The fully mixed downstream concentration must not exceed 30.0 mg/L (an assessment target for this exercise, not a regulatory limit). Assume steady flow, complete mixing, no reaction, and no other inputs. What is the highest allowable tributary concentration?

  • A. 30.0 mg/L
  • B. 42.0 mg/L
  • C. 60.0 mg/L
  • D. 78.0 mg/L
Show answer and solution

Answer: D. 78.0 mg/L.

At the limit, 1.20(18.0) + 0.300Ct = (1.20 + 0.300)(30.0). So 21.6 + 0.300Ct = 45.0 and Ct = 23.4/0.300 = 78.0 mg/L. Check: (21.6 + 23.4)/1.50 = 30.0 mg/L.

Why not the others: A applies the downstream target to the tributary. B weights the two flows equally. C finds the allowable increase above 18.0 mg/L but leaves off the baseline.

Source: MIT OpenCourseWare 1.061 Transport Processes in the Environment (Fall 2008), Lecture 2: Conservation of Mass, Integral conservation-of-mass statement, Eq. (4), reduced to a steady mixing balance

Problem 26 · Ultimate BOD from BOD₅

WRE-WQ-02 · Area 9, Surface Water and Groundwater Quality · Select one

A wastewater has a 5-day biochemical oxygen demand (BOD₅) of 180 mg/L. The first-order BOD rate constant is k = 0.23/day (base e). What is the ultimate BOD?

  • A. 180 mg/L
  • B. 194 mg/L
  • C. 263 mg/L
  • D. 568 mg/L
Show answer and solution

Answer: C. 263 mg/L.

BOD exerted by day t is BODt = L₀(1 − e^(−kt)). Solve for L₀: L₀ = 180/(1 − e^(−0.23 × 5)) = 180/(1 − 0.3166) = 180/0.6834 = 263 mg/L.

Why not the others: A assumes the BOD is finished after 5 days. B uses 10^(−kt), mixing a base-10 form with a base-e constant. D divides by e^(−kt) instead of by (1 − e^(−kt)).

Source: EPA, Technical Guidance Manual for Developing Total Maximum Daily Loads, Book II: Streams and Rivers, Part 1, Section 2.3.4.1, Eq. 2-5, printed p. 2-8 (PDF p. 25): exerted BOD = ultimate BOD × (1 − e^(−kt))

Problem 27 · Dissolved-oxygen sag: minimum DO

WRE-WQ-03 · Area 9, Surface Water and Groundwater Quality · Enter a number

Just below an outfall, a stream has ultimate BOD L₀ = 20 mg/L and an initial DO deficit D₀ = 1.0 mg/L. The deoxygenation rate is kd = 0.20/day and the reaeration rate is kr = 0.40/day (both base e). DO saturation is 9.0 mg/L. Using the Streeter-Phelps model, enter the minimum DO downstream in mg/L, to one decimal.

Show answer and solution

Answer: 3.7 mg/L.

Set dD/dt = 0 to find the critical time: tc = [1/(kr − kd)] ln{(kr/kd)[1 − D₀(kr − kd)/(kd·L₀)]} = 5 × ln(2 × 0.95) = 5 × ln(1.9) = 3.21 days. At that point the critical deficit is Dc = (kd/kr)·L₀·e^(−kd·tc) = 0.5 × 20 × e^(−0.642) = 5.26 mg/L. Minimum DO = 9.0 − 5.26 = 3.74, or 3.7 mg/L.

Common mistakes: One slip is entering the deficit (5.3) instead of the DO. Another is plugging tc into the deficit equation with a sign error; check that DO at tc is lower than DO at, say, 2 or 5 days.

Source: EPA, Technical Guidance Manual for Developing Total Maximum Daily Loads, Book II: Streams and Rivers, Part 1, Section 2.4.2, Eq. 2-27, printed p. 2-22 (PDF p. 39), and minimum-DO explanation, p. 2-24 (PDF p. 41); the critical-time formula is derived from this model. EPA uses Kₐ for the reaeration rate labeled kr here

Problem 28 · TMDL load allocation

WRE-WQ-04 · Area 9, Surface Water and Groundwater Quality · Select one

A phosphorus total maximum daily load (TMDL) is 400 lb/day with an explicit 10% margin of safety (MOS). For this exercise, the only point source is a wastewater plant whose assigned wasteload allocation is the load corresponding to 5.0 MGD at 3.0 mg/L total phosphorus. How much load remains for nonpoint sources and natural background (the load allocation)?

  • A. 235 lb/day
  • B. 275 lb/day
  • C. 345 lb/day
  • D. 360 lb/day
Show answer and solution

Answer: A. 235 lb/day.

TMDL = wasteload allocations + load allocations + MOS. MOS = 0.10 × 400 = 40 lb/day. Wasteload allocation (WLA) = 5.0 MGD × 3.0 mg/L × 8.34 = 125.1 lb/day. Load allocation = 400 − 40 − 125.1 = 234.9, or about 235 lb/day.

Why not the others: B skips the margin of safety. C forgets the 8.34 conversion, so the plant's load comes out as only 15 lb/day. D subtracts the MOS but forgets the point source.

Source: 40 CFR 130.2, Definitions (eCFR), §130.2(g)–(i), LA, WLA and TMDL definitions; 40 CFR 130.7, TMDLs and individual water quality-based effluent limitations (eCFR), §130.7(c)(1), margin of safety; EPA, Preventive Maintenance for Small Public Water Systems Using Ground Water: Tasks and Logs, Commonly Used Formulas, printed/PDF p. 5; pounds per day = MGD × mg/L × 8.34

Area 10: Drinking Water Distribution and Treatment (4 problems)

Problem 29 · Parallel tanks with one out of service

WRE-DW-01 · Area 10, Drinking Water Distribution and Treatment · Select one

A drinking water plant will install three identical flocculation tanks in parallel. With any one tank out of service, the other two must split the full 4.80 MGD equally. The design target for this exercise is a nominal detention time of 30 minutes in each operating tank. What minimum working volume does each tank need?

  • A. 33,333 gal
  • B. 50,000 gal
  • C. 100,000 gal
  • D. 150,000 gal
Show answer and solution

Answer: B. 50,000 gal per tank.

With one tank down, each operating tank gets 4,800,000/2 = 2,400,000 gal/day. Detention time = volume/flow, so V = 2,400,000 × (30/1,440) = 50,000 gal.

Why not the others: A spreads the flow over all three tanks and ignores the outage. C is the combined volume of the two operating tanks. D is the total installed volume of all three.

Source: EPA, Preventive Maintenance for Small Public Water Systems Using Ground Water: Tasks and Logs, Commonly Used Formulas: detention time = volume ÷ flow, p. 5

Problem 30 · CT with a baffling factor

WRE-DW-02 · Area 10, Drinking Water Distribution and Treatment · Select one

A clearwell holds 200,000 gal at its low operating level. Chlorine is applied at the inlet. Peak hourly flow is 2.0 MGD. At that water level and flow, a tracer study gives a baffling factor of 0.30 and the free chlorine residual at the outlet is 1.2 mg/L. What CT does the clearwell provide?

  • A. 51.8 mg·min/L
  • B. 86.4 mg·min/L
  • C. 172.8 mg·min/L
  • D. 240 mg·min/L
Show answer and solution

Answer: A. 51.8 mg·min/L.

Theoretical detention time = V/Q = 200,000 gal/(2,000,000/1,440 gpm) = 144 min. Contact time T (the T₁₀ time) = TDT × baffling factor = 144 × 0.30 = 43.2 min. CT = C × T = 1.2 × 43.2 = 51.8 mg·min/L.

Why not the others: B uses an average baffling factor (0.5) instead of the measured 0.30. C uses the full theoretical detention time and ignores short-circuiting. D multiplies the residual by the volume in thousands of gallons. A common slip not shown here is stopping at T = 43.2 min, which is a time, not a CT.

Source: EPA 815-R-20-003, Disinfection Profiling and Benchmarking Technical Guidance Manual (June 2020), Eq. 4-1 (CT), printed p. 24; Eq. 4-2 (TDT at peak hourly flow), p. 26; Table 4-2 (baffling factors), p. 27; Eq. 4-3 (T = TDT × BF), p. 28 (PDF pp. 34, 36–38)

Problem 31 · Total hardness from calcium and magnesium

WRE-DW-03 · Area 10, Drinking Water Distribution and Treatment · Select one

A water contains 80 mg/L calcium and 24 mg/L magnesium. Assume other hardness-forming ions are negligible. What is its total hardness, expressed as mg/L of CaCO₃?

  • A. 104 mg/L
  • B. 200 mg/L
  • C. 249 mg/L
  • D. 299 mg/L
Show answer and solution

Answer: D. 299 mg/L as CaCO₃.

Convert each ion to its CaCO₃ equivalent: hardness = 2.497(Ca) + 4.118(Mg) = 2.497 × 80 + 4.118 × 24 = 199.8 + 98.8 = 298.6, or about 299 mg/L as CaCO₃. (The factors are 50.04/20.04 for calcium and 50.04/12.15 for magnesium, ratios of equivalent weights.)

Why not the others: A adds the ion concentrations without converting. B counts calcium only. C uses magnesium's atomic weight (24.3) instead of its equivalent weight (12.15).

Source: EPA, 2021 MSGP Appendix J: Calculating Hardness, Section iii, mg/L CaCO₃ = 2.497(Ca) + 4.118(Mg), printed p. J-2 (PDF p. 2); cited for the chemistry equation

Problem 32 · Future maximum-day demand

WRE-DW-04 · Area 10, Drinking Water Distribution and Treatment · Select one

A town of 25,000 people grows 2% per year, compounded, for 20 years. Average use is 120 gallons per capita per day, and this utility's maximum-day factor is 1.8. What maximum-day demand should the 20-year design use?

  • A. 4.5 MGD
  • B. 5.4 MGD
  • C. 7.6 MGD
  • D. 8.0 MGD
Show answer and solution

Answer: D. 8.0 MGD.

Future population = 25,000 × (1.02)²⁰ = 37,150. Average-day demand = 37,150 × 120 = 4.46 MGD. Maximum-day demand = 4.46 × 1.8 = 8.0 MGD.

Why not the others: A stops at average-day demand. B applies the factor to today's population. C grows the population linearly (25,000 × 1.40 = 35,000), which understates compound growth. Peaking factors vary by system; on the exam, use the one the problem gives you.

Source: Worked from the stated inputs (compound growth and the given peaking factor)

Area 11: Wastewater Collection and Treatment (4 problems)

Problem 33 · What activated sludge does (select two)

WRE-WW-01 · Area 11, Wastewater Collection and Treatment · Select TWO

Consider a conventional aerobic activated-sludge process with an aeration tank and a secondary clarifier. Select TWO correct statements.

  • A. Microorganisms in the aeration tank consume biodegradable organic matter.
  • B. Return activated sludge is the process's main source of oxygen.
  • C. Some settled biomass returns to the aeration tank, and the excess is wasted.
  • D. The secondary clarifier removes dissolved salts by gravity settling.
Show answer and solution

Answer: A and C.

A describes biological treatment: microorganisms mixed with the wastewater break down organic matter. C describes the return and waste of biomass after the secondary clarifier. You must select both A and C, and only those, to get credit, the same all-or-nothing rule NCEES uses.

Why not the others: B confuses biomass recycle with aeration; oxygen comes from mixing air into the aeration tank. D confuses settling suspended solids with removing dissolved material, which gravity can't do.

Source: EPA 832-R-04-001, Primer for Municipal Wastewater Treatment Systems (Sept. 2004), Secondary treatment and activated sludge, pp. 12–14; NCEES Examinee Guide, May 2026, Item formats and no partial credit, printed/PDF p. 11

Problem 34 · Full-pipe sewer capacity and minimum velocity

WRE-WW-02 · Area 11, Wastewater Collection and Treatment · Select one

An 8-in sewer (n = 0.013) is laid at a 0.40% slope. Using Manning's equation Q = (1.486/n)AR^(2/3)S^(1/2) in U.S. units, what is its capacity flowing full?

  • A. 231 gpm
  • B. 343 gpm
  • C. 544 gpm
  • D. 864 gpm
Show answer and solution

Answer: B. 343 gpm.

Flowing full, R = A/P = D/4 = (8/12)/4 = 0.167 ft. V = (1.486/0.013)(0.167)^(2/3)(0.004)^(1/2) = 2.19 ft/s. A = π(0.667)²/4 = 0.349 ft², so Q = 0.764 cfs = 343 gpm. The 2.19 ft/s full-flow velocity also clears the 2.0 ft/s minimum in the 2014 Recommended Standards for Wastewater Facilities, which bases its minimum slopes on n = 0.013.

Why not the others: A leaves out the 1.486 constant. C uses R = D/2. D uses R = D. For a full circular pipe, R = πD²/4 ÷ πD = D/4.

Source: Design Manual Chapter 2 Stormwater, Section 2F-2 Open Channel Flow (2013 ed.), hosted by Iowa State University InTrans, Eq. 2F-2.01, Manning's equation in U.S. units, p. 2; Recommended Standards for Wastewater Facilities, 2014 ed. (GLUMRB), full-document mirror, Section 33.41, printed p. 30-1 (PDF p. 27): 2.0 ft/s full-flow minimum with n = 0.013; 8-in slope table, p. 30-2 (PDF p. 28)

Problem 35 · Solids retention time

WRE-WW-03 · Area 11, Wastewater Collection and Treatment · Select one

An aeration basin of 1.0 MG holds mixed liquor at 3,000 mg/L suspended solids. Waste sludge leaves at 0.025 MGD and 10,000 mg/L; plant effluent is 4.0 MGD at 15 mg/L suspended solids. Count only the solids in the aeration basin. What is the solids retention time (SRT)?

  • A. 0.25 day
  • B. 9.7 days
  • C. 12.0 days
  • D. 50 days
Show answer and solution

Answer: B. 9.7 days.

SRT = solids in the system ÷ solids leaving per day. Inventory = 1.0 × 3,000 × 8.34 = 25,020 lb. Wasted = 0.025 × 10,000 × 8.34 = 2,085 lb/day; effluent = 4.0 × 15 × 8.34 = 500 lb/day. SRT = 25,020/2,585 = 9.7 days. (The 8.34 factors cancel: 3,000/(250 + 60).)

Why not the others: A is the hydraulic detention time, V/Q. C ignores the solids lost in the effluent. D ignores the wasted sludge.

Source: Operation of Wastewater Treatment Plants, 2nd ed., Vol. II (1980), California State University, Sacramento, hosted by EPA, Sections 11.73–11.74, MLSS aeration-basin inventory divided by wasted plus effluent solids, printed p. 63

Problem 36 · Alkalinity consumed by nitrification

WRE-WW-04 · Area 11, Wastewater Collection and Treatment · Select one

A plant fully nitrifies 30 mg/L of ammonia nitrogen. Using the theoretical stoichiometric ratio, how much alkalinity is consumed?

  • A. 30 mg/L as CaCO₃
  • B. 107 mg/L as CaCO₃
  • C. 214 mg/L as CaCO₃
  • D. 428 mg/L as CaCO₃
Show answer and solution

Answer: C. 214 mg/L as CaCO₃.

Nitrification consumes about 7.14 mg of alkalinity (as CaCO₃) per mg of ammonia nitrogen oxidized: 7.14 × 30 = 214 mg/L. If influent alkalinity is lower than that plus a working residual, the plant may need to add alkalinity to keep pH stable.

Why not the others: A treats the ratio as 1:1. B uses 3.57, the alkalinity recovered by denitrification, not consumed by nitrification. D doubles the ratio.

Source: Long Island Sound Nitrogen Removal Training Program, Module 4 (SUNY Farmingdale, 1997), hosted by NYSDEC, Unit 1, transparencies 1-2 and 1-17 (7.14 lb as CaCO₃ per lb N oxidized); 1-19 (3.57 recovered)

Area 12: Project Sitework (4 problems)

Problem 37 · Average-end-area volume and swell

WRE-SW-01 · Area 12, Project Sitework · Select one

Two cut cross sections on a straight alignment are 280 ft² and 440 ft², 90 ft apart. Use the average-end-area method. For this material, 1 cubic yard in the ground becomes 1.20 cubic yards loose. What loose volume will be hauled?

  • A. 1,000 yd³
  • B. 1,200 yd³
  • C. 1,440 yd³
  • D. 38,880 yd³
Show answer and solution

Answer: C. 1,440 yd³ loose.

Bank volume = [(280 + 440)/2] × 90 = 32,400 ft³ = 32,400/27 = 1,200 yd³. Loose volume = 1,200 × 1.20 = 1,440 yd³.

Why not the others: A divides by 1.20 instead of multiplying. B stops at bank volume. D is the loose volume in cubic feet, mislabeled as cubic yards.

Source: INDOT, Earthworks, Chapter 6: Measurements and Earthwork Calculations, Volumes, average-end-area equation with the 2 × 27 divisor, printed p. 6-3 (PDF p. 4)

Problem 38 · OSHA trench sloping in Type C soil

WRE-SW-02 · Area 12, Project Sitework · Select one

Reference note: this standard is on the supplied list for exams beginning April 2027. The skill applies either way.

An unshored trench 10 ft deep in Type C soil will be sloped using OSHA's Appendix B maximum allowable slopes. The ground is level, there is no surcharge or sign of distress, both sides are sloped, and the bottom must be 4 ft wide. What is the minimum top width?

  • A. 19 ft
  • B. 24 ft
  • C. 30 ft
  • D. 34 ft
Show answer and solution

Answer: D. 34 ft.

Table B-1 allows 1½H:1V for Type C soil in excavations less than 20 ft deep. Each side runs 1.5 × 10 = 15 ft horizontally, so the top width is 4 + 2(15) = 34 ft.

Why not the others: A uses Type A soil (¾H:1V on both sides), or Type C on one side only. B uses Type B (1H:1V). C leaves out the 4-ft bottom. Sloping deeper than 20 ft must be designed by a registered professional engineer.

Source: OSHA, 29 CFR 1926 Subpart P, Appendix B: Sloping and Benching, Table B-1, Maximum Allowable Slopes, note 3; paragraphs (c)(3)(ii)–(iii), distress and surcharge conditions

Problem 39 · Low point of a sag vertical curve

WRE-SW-03 · Area 12, Project Sitework · Select one

A parabolic sag vertical curve joins a −2.0% grade to a +3.0% grade over a length of 500 ft. How far from the beginning of the curve is the low point?

  • A. 200 ft
  • B. 250 ft
  • C. 300 ft
  • D. 400 ft
Show answer and solution

Answer: A. 200 ft.

The low point is where the grade along the curve is zero: x = g₁L/(g₁ − g₂) = (−2.0)(500)/(−2.0 − 3.0) = 200 ft from the beginning of the curve.

Why not the others: B assumes the low point is at mid-curve, which only happens when the grades are equal and opposite. C gives the 300-ft distance measured back from the end of the curve. D doubles the correct value.

Source: University of Washington CIVE 316, Lecture 12: High or Low Points on a Curve, x = g₁L/(g₁ − g₂), distance from the BVC to the high or low point

Problem 40 · Sediment basin storage under EPA's CGP

WRE-SW-04 · Area 12, Project Sitework · Select one

A construction site will use a sediment basin draining 7.5 acres. The site is covered by EPA's 2022 Construction General Permit (CGP), and the operator chooses the per-acre storage option rather than computing runoff from the 2-year, 24-hour storm. What is the minimum storage volume?

  • A. 1,000 ft³
  • B. 3,600 ft³
  • C. 13,500 ft³
  • D. 27,000 ft³
Show answer and solution

Answer: D. 27,000 ft³.

Part 2.2.12.c of the 2022 CGP requires storage for either the calculated runoff from a 2-year, 24-hour storm or 3,600 ft³ per acre drained. Using the per-acre option: 3,600 × 7.5 = 27,000 ft³ (1,000 yd³).

Why not the others: A is the right quantity in cubic yards, mislabeled as cubic feet. B is the per-acre rate only. C halves the requirement. If your site is covered by a state construction stormwater permit instead of EPA's, check that permit's own basin criteria.

Source: EPA 2022 Construction General Permit (as modified), Part 2.2.12(c), sediment basin storage, printed p. 15 (PDF p. 17)

How to read your results

Treat your result as feedback on these 40 problems, not an NCEES score or a prediction of passing. Two to four problems per area can show you which methods you can't yet explain, but they can't measure an area precisely. NCEES converts your number of correct answers to a scaled score, compares it with a passing standard set by subject-matter experts, and doesn't publish the passing score (Examinee Guide, p. 14). No practice percentage converts into an exam result.

Your 12-week study plan

Example: 12 weeks at about 10 hours a week (120 hours). This is our planning example, weighted toward the heaviest NCEES areas. It isn't an NCEES requirement, and no number of hours guarantees a pass. A typical week: about 2 hours on concepts and reference lookups, 5 hours solving problems in writing, and 3 hours on corrections and mixed review. The 40 problems here are a starting set; you'll need more fresh problems from other legitimate sources to fill the weeks.

Your 12-week study plan
WeekFocusDo thisFinish the week with
1Setup and baselineConfirm your test date and its reference list. Download the handbook from MyNCEES and the free standards for your date. Work all 40 problems before reading the solutions, spread over several sessions.An error log and a list of the areas where you missed the most
2Hydrology IStorm frequency and risk, intensity-duration-frequency data, rational and NRCS runoff, time of concentration. Rework Problems 1–4.A runoff worksheet with every assumption and unit written out
3Hydrology II and stormwaterHydrographs (including synthetic), detention and retention, infiltration, depletions, gauging; sediment basins (Problem 40).A short list of cases where a peak-flow method isn't enough and you need a hydrograph or volume
4Closed-conduit hydraulicsEnergy equation, Hazen-Williams and Darcy-Weisbach, minor losses, pumps and NPSH, pipe networks. Rework Worked Example 1 and Problems 15–18.A pump-system sketch with the grade lines, and hydraulic, shaft, and electrical power labeled separately
5Open-channel hydraulicsManning, specific energy, critical depth, Froude number, jumps, culverts, energy dissipators, storm drainage. Rework Problems 19–21. If you test April 2027 or later, practice HDS-5 and HEC-14 lookups.One culvert or channel problem checked two ways
6Drinking waterDemand projections, storage, sedimentation, coagulation and flocculation, filtration and membranes, disinfection and byproducts, softening. Rework Problems 29–32.Five Water Works lookups logged in the edition for your date
7WastewaterCollection systems and inflow/infiltration, lift stations, primary and secondary treatment, nutrients, solids, disinfection. Rework Worked Example 2 and Problems 33–36.Five Wastewater Facilities (2014) lookups logged
8Water quality and groundwaterBOD and DO sag, TMDL allocations, contaminants; Darcy flow, wells and drawdown, storage. Rework Problems 22–28.A DO-sag sketch and a well problem with transmissivity labeled
9Analysis and design, materialsMass balances, hydraulic and solids loading, flow measurement; soil phase relationships, permeability, piping materials, test conformance. Rework Problems 9–14.A one-page mass-balance template you can reuse
10Sitework, soils, planningEarthwork, erosion and sediment control, trench safety, curves, retaining walls; consolidation, lateral pressure, slope stability; scheduling and economics. Rework Problems 5–8 and 37–40. If you test April 2027 or later, add 29 CFR 1926, EM 1110-2-1902, and UFC 3-220-05 lookups.A formula sheet with the handbook location of each formula
11Timed mixed practiceWork Blocks A and B below at 120 minutes each, with your searchable references and solutions closed until each block ends. Spend the rest of the week on fresh problems and misses.A record of time per block, flagged problems, and slow lookups
12Targeted reviewRework every logged miss with the solution hidden. Repeat your five slowest lookups. Confirm your appointment, ID, and calculator.A short final review list and a checked exam-day plan

Week 11 mixed blocks. Each block has 20 problems, for a 120-minute budget at the exam's six-minute average. These are problems you've already studied, so this is pacing practice, not a fresh full-length exam.

Your 12-week study plan
BlockProblemsTime budget
A1, 3, 5, 7, 9, 11, 13, 15, 17, 19, 21, 23, 25, 27, 29, 31, 33, 35, 37, 39120 minutes
B2, 4, 6, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30, 32, 34, 36, 38, 40120 minutes

Adjusting the plan:

  • Fewer hours a week? Stretch the calendar rather than cutting areas. At 6 hours a week, the same 120 hours takes 20 weeks. That arithmetic doesn't say 120 hours will be enough for you.
  • Only 6 weeks? Pair the weeks (1 and 2, 3 and 4, and so on). That's about 20 hours a week; if that isn't realistic, consider a later test date.
  • Already strong in an area? Keep a short review there and move the saved time to your weakest area. Don't drop an area because you got its sample problems right.
  • Testing April 2027 or later? Add lookup practice for the five newly listed references in Weeks 5 and 10, and switch your Water Works practice to the 2022 edition.

Turn each miss into your next study task

Turn each miss into your next study task
What went wrongNext stepHow you know it's fixed
Picked the wrong methodWrite in one sentence what the problem asks for and which model fits, then rework it with one input changedYou can say why the wrong method doesn't apply
Used the wrong reference or missed a conditionRepeat the lookup: document, chapter, section. Read the definitions and limits nearby.You can name the condition that triggers the rule
Mixed up units or basesWrite the conversion chain with units on every line (cfs vs. gpm, MLSS vs. MLVSS, bank vs. loose)Units cancel to the one the problem asks for
Arithmetic or sign errorRedo it from scratch, then check magnitude or directionThe check agrees without copying your first attempt
Answered a different quantityCircle what the question asks for before you start (shaft or electrical power, deficit or DO, T or CT)You stop at the right step
Took too long on a familiar problemNote where the time went, then practice flagging and returning during a timed blockThe same setup or lookup takes less time next round

Error log fields: problem or topic · your answer · first wrong step · error type (from the table above) · corrected method · reference and section · result with one input changed · date to review again. Log lucky guesses too. A right answer you can't explain is a miss waiting to happen.

If your exam is next week

Don't start a new system. Pick the two errors you repeat most and your two slowest lookups, fix those, do one timed block, and confirm your logistics. If big gaps remain, be honest with yourself; you can reschedule a Pearson appointment at least 48 hours ahead for a $50 fee paid to Pearson (Examinee Guide, p. 6).

If you're preparing for a retake

If you didn't pass, NCEES gives you a diagnostic report that compares your performance in each knowledge area with the average of passing examinees. It doesn't show the passing score or how many questions you missed. Use it with your error log to pick your first two focus areas, weighing both the gap and the size of each area's question range. NCEES allows one attempt per quarterly testing window and no more than three in any 12 months; your board may be stricter. See NCEES exam retake rules and how NCEES exam results work.

Exam-day rules that change how you practice

  • About 6 minutes per question on average. That's 480 minutes ÷ 80 questions. It's a budgeting guide, not a per-question limit.
  • Two sections, one clock. After roughly half the questions, you review and submit them, and you can't go back. Clear your flagged questions before you submit.
  • Breaks. The optional 50-minute break comes after you submit the first section. Unused break time doesn't add to your exam time, and unscheduled breaks come out of your exam time.
  • No penalty for wrong answers, so answer everything.
  • Calculator. One NCEES-approved model. For 2026 exams, that means the HP 33s or HP 35s, or any Casio fx-115, Casio fx-991, TI-30X, or TI-36X model (NCEES memo, Oct. 2025, p. 1). An on-screen TI-30XS is also available. Recheck NCEES's list if your test date moves into a later year.
  • Scratch work. You get two reusable booklets and three markers, not pencils and paper.
  • No personal references. Only the supplied handbook and the standards for your test date.

Sources: NCEES Examinee Guide, May 2026, pp. 8–12 and 14.

Quick answers

Is PE Civil WRE the same as the PE Environmental exam?

No. They're separate NCEES exams with separate specifications; the PE Environmental exam's current specifications took effect in April 2026. Make sure your registration and your study materials match the same exam. See NCEES's PE Environmental page.

Can I use older materials written for "breadth" and "depth" sections?

For concepts, yes. For exam structure, topic weights, and reference editions, no. The current PE Civil exam is one 80-question exam built on the April 2024 specification for your chosen discipline.

Is WRE mostly a handbook exam?

Through March 2027, only two design standards are supplied alongside the handbook. From April 2027, seven standards are listed. Either way, fast handbook searching is a core skill.

What's the pass rate?

For January–June 2026, 71% of 2,620 first-time examinees and 49% of 876 repeat examinees passed (NCEES). Those rates describe that group of test takers, not your odds.

What score do I need?

NCEES doesn't publish a passing score. It scales your number of correct answers and compares that with a passing standard, so claims like "you need 70%" have no official basis.

Do I need a prep course?

No, a course is optional. Whatever you use should match the April 2024 topics and the references for your test date.

Does passing the PE give me a license?

No. Your state or territorial licensing board issues the license, and passing the exam is one of its requirements. NCEES designs the PE for engineers with at least four years of post-college experience, but your board decides when you can sit.

Do I register with NCEES or my board?

Start with your board: check its approval process and any separate application, then register and pay the $400 exam fee in MyNCEES. See NCEES exam registration steps or find your licensing board.

Can I get testing accommodations?

You can request accommodations, but you have to indicate the need during registration. Approval depends on eligibility and supporting documentation. See how to request NCEES exam accommodations.

Haven't passed the FE yet?

Start with FE Civil exam prep or FE Environmental exam prep. For other PE disciplines, see PE exam prep.

Sources

Exam facts on this page were last verified October 8, 2026, against the NCEES sources below. We compared the before-April-2027 and beginning-April-2027 WRE documents side by side. The original problems and worked examples were checked against the teaching sources cited with each one, and every numerical answer was recalculated. They have not been reviewed by NCEES or a licensed professional engineer.

NCEES

Listed exam references

Teaching sources for the problems and examples

These teaching sources explain the methods. Except where noted as a listed exam reference, they are not supplied on the exam.

Castleport Test Prep Editorial Team. This guide was developed with AI-assisted research and editing. Source checking is not professional engineering review. See how Castleport uses sources and AI assistance.

Castleport Test Prep is an independent exam prep publisher. It is not affiliated with, endorsed by, or approved by the National Council of Examiners for Engineering and Surveying (NCEES). Exam and credential names identify their subjects; trademarks belong to their respective owners. The worked examples and practice problems are original and unofficial, and nothing on this page guarantees a passing result or a license.

PE Civil Water Resources & Environmental Exam Prep (Free)