A free study guide for the ARE 5.0 Project Management division. Work through 23 original, unofficial practice questions with full explanations, then use the section map and six-week plan below.

ARE PjM practice questions

Resource Management

PJM-01 · Related objective 1.2

A firm's Design Development fee is $120,000. The team estimates the phase is 50% complete, and $84,000 has been spent so far. If work continues at the same rate, what will the phase cost by the time it's finished? Select one.

Your response, PJM-01 (Select one.)
Reveal answer and explanation, PJM-01

Answer: C. Divide cost to date by percent complete: $84,000 ÷ 0.50 = $168,000. That's a projected $48,000 overrun, or 40% over the phase fee. Spotting it halfway through gives the project manager time to find the cause: inefficiency, an estimating error, or a change in the agreed scope.

  • Why not A: Assumes the fee will hold even though the first half already cost $24,000 more than its share.
  • Why not B: Adds the second half's original $60,000 share to the $84,000 spent, ignoring that the team is burning fee 40% faster than planned.
  • Why not D: Adds the money already spent to the entire fee, counting the first half twice.

Source: Original worked calculation (inputs shown in the question).

Original, unofficial practice questions written by Castleport Test Prep. They are not NCARB exam items. All project figures are invented.

There are 23 questions here, grouped by study topic so you can choose what to review. Most are single-answer. Four ask you to select a stated number of answers, and you only get the point if you choose every correct option and none of the wrong ones, which is how NCARB scores its check-all-that-apply items. One question asks you to select an activity from a schedule table. Use NCARB's practice environment to rehearse the exam's image-based hotspot interaction.

For contract questions, assume the named AIA form is unmodified unless the question states otherwise. This set emphasizes contract application, staffing, and schedules. Objective tags identify related study areas; the questions do not cover every NCARB objective or reproduce an official exam form.

Exhibit 1 — Four-week phase staffing plan (invented)

A firm has a $36,000 fee for this phase. That fee must also cover a $6,000 consultant allowance, $2,000 of nonlabor expenses, and a $4,000 contingency that is held back from staff planning. Planning rates already include salary, benefits, overhead, and planned margin. Availability is for the next four weeks, after other commitments. Work can't be moved between roles without a revised plan.

PJM-01 · Related objective 1.2
RolePlanned hoursPlanning rateAvailable hours per week
Project manager30$160/hour8
Project architect80$120/hour18
Designer100$90/hour30

PJM-02 · Related objective 1.2

Using Exhibit 1, which statement correctly describes the staffing plan? Select one.

Your response, PJM-02 (Select one.)
Reveal answer and explanation, PJM-02

Answer: B. Staffing budget: $36,000 − $6,000 − $2,000 − $4,000 = $24,000. Planned effort: (30 × $160) + (80 × $120) + (100 × $90) = $4,800 + $9,600 + $9,000 = $23,400, which leaves $600 unused. Capacity over four weeks: project manager 8 × 4 = 32 hours (needs 30), project architect 18 × 4 = 72 hours (needs 80, short 8), designer 30 × 4 = 120 hours (needs 100). The team has 224 available hours against 210 planned, but the total hides a shortage in one role.

  • Why not A: Checks the money and the total hours but misses the project architect's 8-hour gap.
  • Why not C: Reverses the fee result. The plan is $600 under the $24,000 staffing budget, not over it.
  • Why not D: Reverses the designer's position. The designer has 20 hours to spare, and the plan leaves $600 unused.

Source: Original worked calculation (inputs shown in the question).

Project Work Planning

Exhibit 2 — Design phase activities (invented)

Durations are in working days. Each activity starts when all of its predecessors finish. Assume enough staff for parallel work and no lags. Count elapsed working days from day 0, and use the earliest project finish as the backward-pass target.

Project Work Planning
ActivityDuration (days)Predecessors
A — Confirm program5—
B — Develop floor plans10A
C — Update site analysis4A
D — Coordinate structural grid6B
E — Coordinate civil and landscape7C
F — Assemble owner review package3D, E

PJM-03 · Related objective 2.2

Using Exhibit 2, what is the earliest the owner review package (Activity F) can be finished? Select one.

Your response, PJM-03 (Select one.)
Reveal answer and explanation, PJM-03

Answer: C. Find the longest path. A → B → D → F takes 5 + 10 + 6 + 3 = 24 days. A → C → E → F takes 5 + 4 + 7 + 3 = 19 days. F can't start until both D (day 21) and E (day 16) are done, so the longer path controls. A → B → D → F is the critical path.

  • Why not A: Follows the shorter path through C and E and ignores the longer one.
  • Why not B: Day 21 is when F can start, not when it finishes.
  • Why not D: Adds every duration as if nothing could happen in parallel.

Source: Original worked calculation (inputs shown in the question).

PJM-04 · Related objective 2.2

Using Exhibit 2, Activity C slips by 6 days. What happens to the finish of Activity F? Select one.

Your response, PJM-04 (Select one.)
Reveal answer and explanation, PJM-04

Answer: B. C has 5 days of total float, meaning it can slip 5 days before the finish moves. A 6-day slip uses all 5 and adds 1 day. The C–E path becomes 5 + 10 + 7 + 3 = 25 days, longer than the old critical path, so it becomes the new critical path.

  • Why not A: Float is limited. Being off the critical path doesn't protect an activity from every delay.
  • Why not C: Treats C as if it had no float at all.
  • Why not D: Miscounts the float. C has 5 days of float, not 4.

Source: Original worked calculation (inputs shown in the question).

PJM-05 · Related objective 2.2

Using Exhibit 2, select the one activity that can start up to 5 days late without delaying another activity's early start or the scheduled finish of the owner review package. Select one activity.

Your response, PJM-05 (table selection from Exhibit 2, Select one activity.)
Reveal answer and explanation, PJM-05

Answer: E. This question is about free float: how far an activity can slip before it delays the next activity. E finishes on day 16 at the earliest, but F can't start until D finishes on day 21. That gives E 5 days of free float. C also has 5 days of total float, but no free float. Any slip in C pushes back E's early start right away.

  • Why not A: A is on the critical path, so it has zero float.
  • Why not B: B is on the critical path, so it has zero float.
  • Why not C: C has 5 days of total float but zero free float. Delaying C delays E.
  • Why not D: D is on the critical path, so it has zero float.
  • Why not F: F is the last activity on the critical path, so it has zero float.

Source: Original worked calculation (inputs shown in the question).

PJM-06 · Related objective 3.3

During construction under A201–2017, the owner wants to phone the contractor directly to ask for a different lobby light fixture. Which approach matches A201? Select one.

Your response, PJM-06 (Select one.)
Reveal answer and explanation, PJM-06

Answer: B. A201 §4.2.4 requires the owner and contractor to include the architect in communications that affect the architect's services or responsibilities, and requires the owner to tell the architect about direct communications with the contractor about the project. A fixture swap affects the design and may affect cost and time, so it will need to go through the change process too.

  • Why not A: Being a party to the contract doesn't remove A201's communication rule.
  • Why not C: Under §4.2.4, communications with subcontractors go through the contractor, not the other way around.
  • Why not D: A201 doesn't bar owner–contractor conversations. It requires the architect to be kept informed.

Source: AIA A201–2017 full sample form.

Contracts

PJM-07 · Related objective 3.1

At the end of Construction Documents, the lowest bona fide bid is 12% over the owner's budget for the Cost of the Work. The overage traces to a premium curtain wall the architect specified without updating the cost estimate. The owner chooses to work with the architect to reduce scope and quality to meet the budget. Under B101–2017, how is the architect paid for revising the documents? Select one.

Your response, PJM-07 (Select one.)
Reveal answer and explanation, PJM-07

Answer: B. Under B101 §6.6, when the lowest bona fide bid exceeds the budget, one of the owner's options is to cooperate with the architect to reduce scope or quality. Under §6.7 the architect then revises the Construction Documents without additional pay. The one exception is an overage caused by market conditions the architect couldn't reasonably anticipate. Here the cause was the architect's own specification.

  • Why not A: The Additional Service exception applies only when unforeseeable market conditions caused the overage.
  • Why not C: Supplemental Services are services assigned in the agreement at signing, not redesign to fix an over-budget bid.
  • Why not D: Rebidding is one of the owner's options under §6.6, not a required first step.

Source: AIA B101–2007/2017 comparison (2017 provisions); AIA Contract Documents: Summary of B101–2017.

PJM-08 · Related objective 3.1

After Construction Documents are completed, the lowest bona fide bid exceeds the owner's budget for the Cost of the Work because steel prices spiked after the final estimate. The architect could not reasonably have anticipated the spike. No construction contract has been awarded. The owner chooses to work with the architect to reduce scope to meet the budget. Under B101–2017, how is the architect paid for the revisions? Select one.

Your response, PJM-08 (Select one.)
Reveal answer and explanation, PJM-08

Answer: B. B101–2017 §6.7 added this exception. When the overage comes from market conditions the architect couldn't reasonably anticipate, the revisions are paid as an Additional Service. B101–2007 §6.7 did not contain this market-conditions exception. Older study notes may still teach that rule.

  • Why not A: B101–2007 §6.7 did not contain the 2017 exception for market conditions the architect could not reasonably anticipate.
  • Why not C: There's no contract with a contractor yet. Bids are offers, and B101 doesn't shift this cost to a bidder.
  • Why not D: A budget increase is one of the owner's options, not a requirement.

Source: AIA B101–2007/2017 comparison (2017 provisions); AIA Contract Documents: Summary of B101–2017.

PJM-09 · Related objective 3.1

When they sign B101–2017, the owner and architect agree the architect will provide sustainable project services that go beyond the sustainability considerations already built into basic design. How are these services classified? Select one.

Your response, PJM-09 (Select one.)
Reveal answer and explanation, PJM-09

Answer: C. B101–2017 §4.1.1 lists Supplemental Services, which the architect provides only when they're assigned in the agreement. Sustainable project services are on that list. Basic design already considers sustainable alternatives, but more advanced sustainable services are Supplemental. Additional Services are different: they come up after the agreement is signed.

  • Why not A: Basic Services include considering sustainable alternatives, not these expanded services.
  • Why not B: Additional Services arise after signing. These were agreed at signing. B101–2007 called both kinds Additional Services, which is why older notes blur them.
  • Why not D: The architect is providing these services, not a consultant the owner hired separately.

Source: AIA B101–2007/2017 comparison (2017 provisions); AIA Contract Documents: Summary of B101–2017.

PJM-10 · Related objective 3.1

The architect's Basic Services fee is a percentage of the owner's budget for the Cost of the Work. Schematic Design was billed and paid based on a $10 million budget. During Design Development, the owner lowers the budget to $9 million. Under B101–2017, what happens to the Schematic Design payments? Select one.

Your response, PJM-10 (Select one.)
Reveal answer and explanation, PJM-10

Answer: B. B101 §11.6 bases each progress payment on the owner's most recent budget for the Cost of the Work and says payments already made aren't adjusted when the budget later changes.

  • Why not A: §11.6 rules out retroactive adjustment.
  • Why not C: B101 doesn't hold earned payments until bidding.
  • Why not D: Later payments follow the most recent budget, not the original one.

Source: AIA B101–2007/2017 comparison (2017 provisions); AIA: Calculating the architect's fee.

PJM-11 · Related objective 3.3

Under A201–2017, which of these are Contract Documents? Assume the Agreement doesn't list any bidding requirements. Select four.

Your response, PJM-11 (Select four.)
Reveal answer and explanation, PJM-11

Answer: A, B, C, and D. A201 §1.1.1 defines the Contract Documents as the Agreement, the Conditions, the Drawings, the Specifications, Addenda issued before execution, other documents listed in the Agreement, and Modifications issued after execution. A Change Order is a Modification. Bidding requirements such as Instructions to Bidders, including the bidding or proposal portions of addenda, are left out unless the Agreement lists them. Option C changes the Drawings and Specifications, so it is included. §3.12.4 says shop drawings aren't Contract Documents.

  • Why not E: Approval doesn't turn a submittal into a Contract Document (§3.12.4).
  • Why not F: Bidding requirements are excluded unless the Agreement lists them (§1.1.1).

Source: AIA A201–2017 full sample form.

PJM-12 · Related objective 3.2

An architect is hiring a mechanical engineer and wants the engineer's obligations to line up with what the architect owes the owner under B101. Which AIA agreement is built for that relationship? Select one.

Your response, PJM-12 (Select one.)
Reveal answer and explanation, PJM-12

Answer: B. C401–2017 is AIA's architect–consultant agreement. It incorporates the owner–architect agreement (the prime agreement) by reference and flows its provisions down to the consultant. The consultant's own defined scope still controls what it has to provide.

  • Why not A: A101 is an owner–contractor agreement.
  • Why not C: A201 is the General Conditions of the Contract for Construction.
  • Why not D: G801 is a notice of Additional Services, not an agreement.

Source: AIA Contract Documents: Summary of C401–2017.

PJM-13 · Related objective 3.4

B101–2017 governs, unmodified. The owner hired its own geotechnical engineer. The architect notices that the report's foundation recommendation describes the parcel next door instead of the project site. What should the architect do first? Select one.

Your response, PJM-13 (Select one.)
Reveal answer and explanation, PJM-13

Answer: C. B101 §3.1.2 lets the architect rely on information from the owner and the owner's consultants and says the architect isn't responsible for its accuracy. It also requires prompt written notice to the owner when the architect discovers an error, omission, or inconsistency. Reliance doesn't mean ignoring a problem you've spotted. B101 §5.5 makes geotechnical services the owner's to furnish, which is why the fix runs through the owner.

  • Why not A: Section 3.1.2 requires written notice of the discovered inconsistency; the right to rely on owner-provided information does not permit ignoring it.
  • Why not B: The architect isn't the geotechnical engineer and has no basis for substituting its own soil analysis.
  • Why not D: Nothing requires stopping all work or replacing the engineer. The first step is notice and clarification.

Source: AIA B101–2017 partial sample; AIA B101–2007/2017 comparison (2017 provisions).

Project Execution

PJM-14 · Related objective 4.2

Midway through Design Development, the owner asks to add a 40-seat training room that isn't in the program. The architect isn't at fault for the change. Under B101–2017, what should happen before the architect designs it? Select one.

Your response, PJM-14 (Select one.)
Reveal answer and explanation, PJM-14

Answer: B. B101 §4.2.1 covers Additional Services such as changes in project scope. The architect must notify the owner promptly and can't start those services without the owner's written authorization. AIA's G801 Notice of Additional Services form is built for this: it describes the services and the proposed changes to fee and schedule. B101 §4.2.2 is a separate path for certain services needed to avoid construction delay. It doesn't apply here.

  • Why not A: A new room outside the program is a scope change, not part of Basic Services.
  • Why not C: Absorbing the cost is how scope creep turns into an unpaid overrun, and it skips the authorization §4.2.1 requires.
  • Why not D: The owner can change the program. The change just carries fee and schedule consequences.

Source: AIA B101–2007/2017 comparison (2017 provisions); AIA Contract Documents: Instructions for G801–2017.

PJM-15 · Related objective 4.2

During construction under A201–2017, the owner needs an extra exit door added right away. The change is within the general scope of the Contract. The owner and contractor can't agree on the price, and the work has to keep moving. What should the architect prepare? Select one.

Your response, PJM-15 (Select one.)
Reveal answer and explanation, PJM-15

Answer: B. A Construction Change Directive lets a change go ahead before the price or time adjustment is agreed. It takes effect with the owner's and architect's signatures. The contractor signs only if it agrees, and an agreed CCD is then followed by a Change Order. The adjustment is set using the contract's pricing methods or, if needed, by the architect based on documented costs.

  • Why not A: A Change Order requires all three parties to agree, and here they don't.
  • Why not C: An RFI response clarifies the documents. It doesn't by itself authorize this change to the contract.
  • Why not D: Changes to the work are handled inside the existing contract, not with a new agreement.

Source: AIA Contract Documents: Change Orders vs. Construction Change Directives; AIA A201–2017 full sample form.

PJM-16 · Related objective 3.1

An owner wants one entity responsible for construction, a guaranteed maximum price, and construction that starts while design is still being finished. Which delivery method and AIA owner–construction manager agreement fit best? Select one.

Your response, PJM-16 (Select one.)
Reveal answer and explanation, PJM-16

Answer: B. A construction manager as constructor (CMc, often called CM at-risk) holds the subcontracts, takes on construction performance, and suits overlapping design and construction. A133–2019 is the CMc agreement when payment is the Cost of the Work plus a fee with a guaranteed maximum price.

  • Why not A: A CMa advises the owner but holds no trade contracts and does not take on the constructor's performance obligations.
  • Why not C: Conventional design-bid-build follows design with bidding and construction; A101–2017 is not the requested owner–CMc agreement.
  • Why not D: A134–2019 is the CMc agreement without a guaranteed maximum price.

Source: AIA Contract Documents: CMa vs. CMc; AIA Contract Documents: Choosing an Owner–CMc agreement.

PJM-17 · Related objective 3.1

A public owner wants an independent adviser through design and construction, wants to hold the trade contracts itself, and wants the adviser to remain separate from the constructor. Which arrangement fits? Select one.

Your response, PJM-17 (Select one.)
Reveal answer and explanation, PJM-17

Answer: A. A construction manager as adviser (CMa) acts as the owner's independent adviser, holds no trade contracts, and does not take on the constructor's performance obligations. The owner holds the contracts directly. AIA's CMa documents include A132, A232, B132, and C132.

  • Why not B: A CMc holds the subcontracts and takes on construction performance, which moves risk away from the owner.
  • Why not C: A design-builder holds both design and construction responsibility.
  • Why not D: One general contractor stands between the owner and the trades, instead of the owner holding the trade contracts directly.

Source: AIA Contract Documents: CMa vs. CMc.

PJM-18 · Related objective 3.3

A project uses A201–2017, and the Contract Documents don't say who handles the building permit. Who secures and pays for it? Select one.

Your response, PJM-18 (Select one.)
Reveal answer and explanation, PJM-18

Answer: C. Unless the Contract Documents say otherwise, A201 §3.7.1 makes the contractor responsible for the building permit and for the other permits, fees, and inspections customarily secured after the contract is signed. Under B101, the architect also responds to the authorities' design requirements and assists the owner with approval filings (§§3.1.5–3.1.6).

  • Why not A: The architect prepares documents that meet the authority's requirements but doesn't secure the building permit under A201.
  • Why not B: The Contract Documents have not reassigned the contractor's permit duty to the owner.
  • Why not D: The question asks who has the contractual duty under A201, and the Contract Documents have not reassigned it.

Source: AIA A201–2017 full sample form; AIA B101–2017 partial sample.

Project Quality Control

PJM-19 · Related objective 3.3

A steel fabricator's shop drawing changes a connection detail from what's shown in the Contract Documents. The contractor didn't point out the change, and the architect approved the shop drawing. The change was not authorized by a Change Order or Construction Change Directive. The connection later has to be rebuilt. Under A201–2017, which statement is correct? Select one.

Your response, PJM-19 (Select one.)
Reveal answer and explanation, PJM-19

Answer: B. A201 §3.12.8 says the architect's approval doesn't relieve the contractor of deviations from the Contract Documents unless the contractor specifically notified the architect at submittal and either obtained written approval of the specific deviation as a minor change or had it authorized by Change Order or Construction Change Directive. None of that happened here.

  • Why not A: Shop drawings aren't Contract Documents, even after approval (§3.12.4).
  • Why not C: A201 doesn't shift the cost of an unflagged deviation to the owner.
  • Why not D: Approval alone doesn't transfer design responsibility. This answer invents a rule.

Source: AIA A201–2017 full sample form.

PJM-20 · Related objective 5.3

Under A201–2017, what is the architect's review of shop drawings for? Select two.

Your response, PJM-20 (Select two.)
Reveal answer and explanation, PJM-20

Answer: A and B. A201 §4.2.7 limits the architect's submittal review to conformance with the information given and the design concept expressed in the Contract Documents. The review doesn't verify dimensions or quantities, approve means, methods, or safety precautions, or relieve the contractor of its own obligations. Shop drawings are not Contract Documents (§3.12.4).

  • Why not C: Dimensions and quantities stay the contractor's responsibility.
  • Why not D: Means and methods belong solely to the contractor (§3.3.1).
  • Why not E: Safety precautions aren't approved through submittal review.
  • Why not F: §3.12.4 says submittals aren't Contract Documents.

Source: AIA A201–2017 full sample form.

PJM-21 · Related objective 3.3

Which statements match how A201–2017 divides responsibilities during construction? Select three.

Your response, PJM-21 (Select three.)
Reveal answer and explanation, PJM-21

Answer: A, C, and E. A201 §3.3.1 makes the contractor solely responsible for means and methods. Under §4.2.2, the architect visits at appropriate intervals, isn't required to make exhaustive or continuous inspections, and doesn't control means, methods, or safety. Under §3.2.2, the contractor reviews the documents as a contractor, not as a licensed design professional, and reports errors it discovers as requests for information.

  • Why not B: §4.2.2 says the architect isn't required to make exhaustive or continuous inspections.
  • Why not D: §3.2.2 says the contractor's review is in its capacity as a contractor, not as a licensed design professional.
  • Why not F: Safety programs belong to the contractor, and the architect doesn't control them.

Source: AIA A201–2017 full sample form.

PJM-22 · Related objective 5.3

A firm's quality procedure says every review comment needs an assigned responder and must go back to the reviewer for closure before the documents are issued. A reviewer flags a conflict between the door hardware schedule and an accessibility detail. Which actions meet that procedure? Select two.

Your response, PJM-22 (Select two.)
Reveal answer and explanation, PJM-22

Answer: B and E. The procedure in the question asks for two things: a named responder, and a reviewer who confirms the fix before closing the comment. B and E do exactly that. Under this procedure, a comment is closed when someone has checked the corrected documents, not when it has been received or acknowledged.

  • Why not A: Receiving a comment isn't the same as resolving it.
  • Why not C: Pushing a known conflict into construction is the opposite of quality control, and it skips the required closure.
  • Why not D: A verbal acknowledgment without checking the revision fails the verification step.
  • Why not F: The original package is what had the conflict.

Source: Bill Schmalz, AIA CCA white paper: Differentiating between QA and QC.

PJM-23 · Related objective 5.4

During Design Development, the mechanical engineer says the equipment room has to grow. Expanding it would shrink the lobby below the minimum size in the owner's approved program. No program change has been approved. What is the best way to manage this? Select one.

Your response, PJM-23 (Select one.)
Reveal answer and explanation, PJM-23

Answer: D. Objective 5.4 is about protecting the agreed design objectives while solving real technical problems. D does both: it tests the change against what the owner approved, looks for alternatives, brings the owner in if the program itself has to change, and checks that the revised drawings are coordinated. The owner's approval matters because B101 has the architect submit Design Development documents for the owner's approval (§3.3.3).

  • Why not A: Being newer doesn't make a drawing approved, and this option quietly breaks the owner's program.
  • Why not B: The mechanical need is real. Putting it off leaves the coordination problem unresolved.
  • Why not C: Issuing conflicting documents on purpose is a coordination failure.

Source: NCARB: Project Management division; AIA B101–2017 partial sample; AIA: Managing quality in the design development phase.

Answer key

Answer key
QuestionAnswerStudy topicReview
PJM-01CResource ManagementFee, hours, and staff
PJM-02BResource ManagementFee, hours, and staff
PJM-03CProject Work PlanningSchedules: critical path and float
PJM-04BProject Work PlanningSchedules: critical path and float
PJM-05EProject Work PlanningSchedules: critical path and float
PJM-06BProject Work PlanningWho's responsible during construction
PJM-07BContractsBudget, bids, and redesign
PJM-08BContractsBudget, bids, and redesign
PJM-09CContractsSupplemental vs. Additional Services
PJM-10BContractsBudget, bids, and redesign
PJM-11A, B, C, DContractsWho's responsible during construction
PJM-12BContractsWhich AIA documents to study
PJM-13CContractsOwner's consultants and approvals
PJM-14BProject ExecutionSupplemental vs. Additional Services
PJM-15BProject ExecutionChanging the work
PJM-16BProject ExecutionDelivery methods at a glance
PJM-17AProject ExecutionDelivery methods at a glance
PJM-18CProject ExecutionOwner's consultants and approvals
PJM-19BProject Quality ControlWho's responsible during construction
PJM-20A, BProject Quality ControlWho's responsible during construction
PJM-21A, C, EProject Quality ControlWho's responsible during construction
PJM-22B, EProject Quality ControlQuality control that actually closes the loop
PJM-23DProject Quality ControlQuality control that actually closes the loop

How to read your result: Count your correct answers and look at which study topics they came from. A score on these 23 questions is feedback on these questions only. It isn't an NCARB scaled score, and it can't predict whether you'll pass. With two to seven questions per study group, one miss can swing that result a lot, so use your misses to choose what to review next, not to grade yourself.

Where the PjM points are

This guide is built on NCARB's current PjM objectives (updated April 27, 2026) and the ARE 5.0 Guidelines effective October 1, 2026.

PjM has 75 items in a 3-hour test, spread across five sections. Contracts is the biggest one, so it's the best place to start. (NCARB PjM division page)

Where the PjM points are
SectionShare of the examWhat it really asksStudy first
Resource Management7–13%Can you staff a project and keep its fee under control?Fee-burn math; matching people and hours to the work
Project Work Planning17–23%Can you build a workable plan and schedule and keep everyone informed?Critical path and float; who has to be told what
Contracts25–31%Can you read and apply the owner–architect, architect–consultant, and owner–contractor agreements?AIA B101 (services, budget, pay) and A201 (contract documents, roles)
Project Execution17–23%Can you keep design on budget, control scope, match documents to the delivery method, and get approvals?B101's over-budget rules; Additional Services; CMa vs. CMc; permits
Project Quality Control19–25%Can you run quality checks that catch conflicts and protect the design?Submittal review limits; contractor vs. architect duties; closing review comments

NCARB calls these weights typical; your exam form can vary slightly. Your result is based on the whole division, not section by section, so a strong Contracts score can carry a weaker section (ARE 5.0 Guidelines, "ARE Scoring," p. 40).

All 17 current PjM objectives

Objective numbers follow NCARB's section order. Wording is NCARB's, from its PjM division page.

ASWB exam resource table
#Objective
1.1Determine criteria required to assemble team
1.2Assess criteria required to allocate and manage project resources
2.1Develop and maintain project work plan
2.2Determine criteria required to develop and maintain project schedule
2.3Determine appropriate communication to project team—owner, contractor, consultants, and internal staff
3.1Evaluate and verify adherence to owner/architect agreement
3.2Interpret key elements of, and verify adherence to architect/consultant agreement
3.3Interpret key elements of the owner/contractor agreement
3.4Interpret key elements of the owner/architect agreement to integrate an owner's consultant's work into the project
4.1Monitor the project throughout its design and documentation for compliance with the construction budget (updated April 2026)
4.2Evaluate and address changes in scope of work and scope creep
4.3Implement appropriate policies and procedures to document a project for a specified delivery method (updated April 2026)
4.4Identify and conform with the requirements set forth by authorities having jurisdiction in order to obtain approvals for the project
5.1Apply procedures required for adherence to laws and regulations relating to the project
5.2Identify processes, policies, and resources for quality control and risk reduction in the project (updated April 2026)
5.3Implement quality control processes to ensure project coordination and constructability (updated April 2026)
5.4Implement quality control processes to maintain integrity of design objectives (updated April 2026)

NCARB reworded these five PjM objectives effective April 27, 2026, to clarify them (NCARB: Understand the ARE changes). NCARB said it didn't expect the changes to affect how candidates prepare. Still, if your notes predate 2026, check their objective wording against this list.

The rules PjM keeps coming back to

These are the ideas behind the questions above, gathered in one place. Contract provisions are paraphrased for study. On a real project, read the full document.

Budget, bids, and redesign (B101–2017)

The owner sets the budget and keeps it updated. If the budget for the Cost of the Work changes significantly, the owner tells the architect, and the two agree on a matching change in scope or quality (B101 §5.2).

The architect's estimates are professional judgment, not a guarantee. B101 says outright that neither party controls market prices, so the architect doesn't promise that bids will match the budget (§6.2). The architect can still steer toward the budget with contingencies, scope or program recommendations, and design alternates (§6.3). If the architect's own estimate goes over budget, the architect recommends changes to size, quality, or budget, and the owner cooperates (§6.5).

When the lowest bona fide bid comes in over budget at the end of Construction Documents, B101 §6.6 gives the owner five options:

  1. Approve a higher budget in writing.
  2. Authorize rebidding or renegotiation within a reasonable time.
  3. Terminate the agreement under §9.5.
  4. Work with the architect to reduce program, scope, or quality.
  5. Choose another option both parties accept.

If the owner picks option 4, the architect revises the Construction Documents at no extra charge, unless the overage came from market conditions the architect couldn't reasonably anticipate. In that case, the revisions are paid as an Additional Service (§6.7). That exception is new in the 2017 edition. B101–2007 §6.7 did not contain this market-conditions exception (AIA summary of B101–2017).

Watch the budget before bids, too. Objective 4.1 asks you to monitor cost all the way through design. A quick invented example: the approved construction budget is $2,400,000 and the current Design Development estimate is $2,520,000. That's $120,000, or 5%, over. The right move is to report the variance to the owner and recommend scope, quality, or budget changes now. B101 also has the architect flag estimate changes when it submits the Design Development documents for approval (§3.3.3). The calculation alone doesn't create a fee entitlement or a contractual tolerance.

Supplemental vs. Additional Services, and scope creep

  • Basic Services under B101 are organized into five phases: Schematic Design, Design Development, Construction Documents, Procurement, and Construction.
  • Supplemental Services are listed in B101 §4.1.1. The architect provides them only if the agreement assigns them at signing. Examples include commissioning and sustainable project services.
  • Additional Services come up after the agreement is signed (§4.2). Services provided in accordance with §4.2 entitle the architect to compensation and an appropriate schedule adjustment, except for services required because of the architect's own fault.

For the most common kind, such as an owner's change in scope, B101 §4.2.1 requires the architect to notify the owner promptly and not start without the owner's written authorization. AIA's G801 form is designed to give that notice, with the proposed fee and schedule changes (G801 instructions). A separate path, §4.2.2, covers certain services needed to avoid construction delay.

For an owner's scope change covered by §4.2.1: name the change, propose its fee and schedule effects, and obtain written authorization before doing the added work.

Assemble the team and maintain the work plan

Before assigning hours, identify the staff and outside consultants the signed scope requires, the responsibilities of each role, and the owner-retained inputs the team needs. Put deliverables, dependencies, review dates, and responsibility in the work plan. B101 requires the architect to manage its services and submit a schedule that allows time for the owner's review, the work of the owner's consultants, and authority approvals (§§3.1.1–3.1.3).

Here are two invented work-plan rows extending Exhibit 2:

Assemble the team and maintain the work plan
ActivityResponsible roleInput or dependencyCompletion check
A — Confirm programProject managerOwner's program and project requirementsRecord the agreed program before B and C begin
F — Assemble owner review packageProject architectD and E complete; their information coordinatedIssue one coordinated package for owner review at the planned day-24 finish

Update the work plan when a dependency, deliverable, or review date changes, and communicate the revised responsibilities and dates. This is the work-plan practice behind NCARB objectives 1.1 and 2.1 (Guidelines pp. 79–80).

Fee, hours, and staff

Two checks catch most staffing problems.

Will the phase fee hold? Divide what's been spent by percent complete. $84,000 spent at 50% complete projects to $168,000 against a $120,000 fee (PJM-01). Find out why before the second half starts.

Does each role have the hours? Compare planned hours with available hours role by role, not in total. In PJM-02, the team has 224 available hours against 210 planned, but the project architect is still 8 hours short. Spare designer hours don't fix that unless the plan changes.

Before staff planning, deduct the consultant costs, nonlabor costs, and contingency that the stated phase fee must cover. Treat separately reimbursable expenses according to the agreement (B101 §11.8.1).

Schedules: critical path and float

Here is Exhibit 2 from the practice set, solved with a forward pass (earliest start and finish) and a backward pass (latest start and finish).

Schedules: critical path and float
ActivityDurationEarly startEarly finishLate startLate finishTotal floatFree float
A5050500
B1051551500
C459101450
D61521152100
E7916142155
F32124212400
  • The critical path is the longest chain, A → B → D → F, at 24 days. Any delay on it delays the finish.
  • Total float is how far an activity can slip without moving the finish.
  • Free float is how far it can slip without delaying the next activity's early start. C and E both have 5 days of total float, but only E has free float.

B101 also has scheduling rules of its own. The architect's schedule has to allow time for owner review, the owner's consultants, and approvals by authorities having jurisdiction. Once the owner approves it, the architect can adjust it, with the owner's approval, until construction starts (B101 §3.1.3). So if an owner asks for an earlier finish date, don't just cut the owner-review time. Work out which activities can realistically change, get the revised schedule approved, and send the new dates to everyone affected.

Changing the work: Change Order or Construction Change Directive

Changing the work: Change Order or Construction Change Directive
SituationUseWho signs
Owner, contractor, and architect agree on the change, price, and timeChange Order (AIA G701)Owner, architect, and contractor
The work has to proceed, but price or time isn't agreed yetConstruction Change Directive (AIA G714)Owner and architect; the contractor signs only if it agrees, and a Change Order follows

When a directive's price isn't agreed, it's set using the contract's pricing methods or, if needed, by the architect based on the contractor's documented costs (AIA Contract Documents: Change Orders vs. CCDs). The architect may order a minor change in writing when it remains within the Contract Documents' intent, leaves the Contract Sum unchanged, and does not extend the Contract Time (A201 §§4.2.8, 7.4). If the contractor believes the proposed change affects price or time, it must notify the architect and must not proceed with that change.

Who's responsible during construction (A201–2017)

All citations below are to the A201–2017 General Conditions.

  • Contract Documents are the Agreement, the Conditions, the Drawings, the Specifications, Addenda issued before signing, other documents listed in the Agreement, and Modifications issued after. Bidding requirements, including the bidding or proposal portions of addenda, are left out unless the Agreement lists them (§1.1.1).
  • Submittals (shop drawings, product data, samples) are not Contract Documents (§3.12.4). The architect reviews them only for conformance with the information given and the design concept. That review doesn't check dimensions or quantities, and it doesn't approve means, methods, or safety (§4.2.7). Approval doesn't excuse a deviation the contractor didn't specifically point out (§3.12.8).
  • Means, methods, and safety belong to the contractor (§3.3.1). The architect visits at appropriate intervals but isn't required to make exhaustive or continuous inspections (§4.2.2).
  • The contractor's document review is done as a contractor, not as a licensed design professional. Errors it discovers go to the architect as requests for information (§3.2.2).
  • The building permit is the contractor's to secure, unless the Contract Documents say otherwise (§3.7.1).
  • Communications: the owner and contractor include the architect in anything that affects the architect's services. The architect's consultants are reached through the architect, and subcontractors through the contractor (§4.2.4).
  • Schedules: the contractor's construction schedule goes to the owner and architect for their information. The submittal schedule goes to the architect for approval (§3.10).
  • Owner's finances: before work starts, the owner must give reasonable evidence of its financial arrangements if the contractor asks in writing (§2.2.1).

Owner's consultants and approvals

The owner provides the site survey and the geotechnical services (B101 §§5.4–5.5). The architect coordinates with the owner's consultants and may rely on the information they provide. When the architect finds an error, omission, or inconsistency, it has to give the owner prompt written notice (§3.1.2).

For approvals, the architect contacts the authorities whose approval the documents need and responds to their design requirements, and it helps the owner with the filings (§§3.1.5–3.1.6).

A simple approval register keeps this under control. List each authority, what it must approve, who prepares the submission, what information it needs, the expected review time, the decision received, and any open comments. Fill it in from your project's actual requirements; there's no national permit sequence to memorize.

Delivery methods at a glance

Delivery methods at a glance
MethodWho holds the construction contractsWho carries construction riskAIA documents
Design-bid-buildThe owner signs one contract with a general contractor, after bidding complete documentsThe contractor, within its contractA101 + A201
CM as adviser (CMa)The owner holds the trade contracts directlyStays largely with the owner; the CMa advisesA132, A232, B132, C132
CM as constructor (CMc)The construction manager holds the subcontractsMoves to the CM, often with a guaranteed maximum priceA133 (with GMP), A134 (without), with A201
Design-buildOne entity provides both design and constructionThe design-builder, within its contractA141–2014 (owner–design-builder); B143–2014 (design-builder–architect)

The CMa and CMc rows come from AIA Contract Documents' CMa vs. CMc overview and its CMc agreement FAQ. Objective 4.3 asks you to document a project to fit its delivery method. That starts with knowing who has signed with whom, because it decides where documents go and who approves them.

Document control for the delivery method

Knowing the contract relationships is the starting point for objective 4.3. The next step is controlling what each package is for, who receives it, and which revision applies. Here is an invented register entry for a CMc project with overlapping design and construction:

Document control for the delivery method
PackageRevisionIntended useRecipientsStatus
Foundation drawings2Coordination reviewOwner, CMc, structural consultantReplaces revision 1 for coordination; not issued for construction

When a revision changes another discipline's work, send the affected team the current package, identify what changed, and record the response before the next issue. A coordination issue must not silently become a construction issue. Match the actual recipients and approvals to the project's agreements. AIA's design-development guidance supports stating and sharing deliverables; this register is an original study example, not a prescribed AIA form (AIA: phase objectives and deliverables).

Quality control that actually closes the loop

PjM's quality objectives are about process: set review points and criteria, give every comment an owner, and confirm the fix before you call it closed. When disciplines collide, as in PJM-23, check the change against the owner's approved program, coordinate alternatives, get the owner's decision if the program must change, and recheck the revised set. A checklist supports that review. It doesn't prove compliance on its own. The response-and-verification workflow is described in Bill Schmalz's AIA CCA white paper.

Which AIA documents to study for PjM

Start with these relationships, then use NCARB's list to fill in the rest.

Which AIA documents to study for PjM
DocumentRelationshipWhat to pull out of it
B101–2017Owner–architectServices, owner's budget, over-budget bids, Additional Services, compensation, termination
C401–2017Architect–consultantHow the prime agreement flows down; the consultant's defined scope
A101–2017Owner–contractor, stipulated sumThe construction agreement that brings in A201
A201–2017General ConditionsContract Documents, submittals, changes, roles, payment
A133–2019 / A134–2019Owner–CM as constructorGuaranteed maximum price vs. no GMP
G701, G714, G801FormsChange Order, Construction Change Directive, Notice of Additional Services

NCARB lists the AIA documents most often referenced on the ARE, with their editions, in “AIA Contract Documents,” printed page 116 of the ARE 5.0 Guidelines:

Which AIA documents to study for PjM
Document and editionRelationship or purpose
A101–2017Owner–contractor agreement, stipulated sum
A133–2019Owner–CMc agreement, Cost of the Work plus a fee with GMP
A141–2014Owner–design-builder agreement
A195–2008Owner–contractor agreement for integrated project delivery
A201–2017General Conditions of the Contract for Construction
A701–2018Instructions to Bidders
B101–2017Owner–architect agreement
B143–2014Design-builder–architect agreement
B195–2008Owner–architect agreement for integrated project delivery
C401–2017Architect–consultant agreement
G701–2017Change Order
G702–1992Application and Certificate for Payment
G703–1992Continuation Sheet
G704–2017Certificate of Substantial Completion
G709–2018Proposal Request

A134–2019, G714–2017, and G801–2017 are useful companion forms discussed above; they are not entries in this NCARB reference table.

Candidates can find NCARB's link to free AIA contracts in their NCARB Record under Exams → Additional Resources (Guidelines p. 118). The B101 comparison cited here shows 2017 additions underlined and deleted 2007 text struck through; use the current provisions when studying.

Check that list rather than assuming the newest AIA edition is the one tested. NCARB's item writers must be able to point to a recognized reference such as The Architect's Handbook of Professional Practice for every answer (Guidelines, p. 49). So read for how a provision decides a project situation, not to memorize clause numbers.

A reading drill that works: for each scenario, write down who retained whom, which agreement applies, what services are involved, what notice or approval is required, and which section supports your answer.

Six-week PjM study plan

Use this schedule as written if you can give PjM about 8 hours a week, or 48 hours in total. That's our editorial estimate, not an NCARB requirement or a guarantee of readiness. With about 4 hours a week, stretch each week to two. With 16, do two weeks' work in each week, and keep the full practice exam in the final study block as one sitting.

Six-week PjM study plan
WeekFocusTasks (about 8 hours)
1Contracts I: B101Take all 23 questions cold and start your error log (1.5 h). Read B101 Articles 3–6 and 9–11 alongside the summary above (4 h). Redo PJM-07 to PJM-10 and PJM-13, and explain each answer out loud (1.5 h). Write a one-page B101 sheet from memory, then check it (1 h).
2Contracts II: A201, A101, C401Read A201 Articles 1–4, 7, and 9 (4 h). Read the C401 and A101 summaries (1 h). Redo PJM-11, PJM-12, PJM-15, and PJM-19 to PJM-21 (1.5 h). Write the "who signs what" and "who's responsible for what" tables from memory (1.5 h).
3Project ExecutionBudget monitoring and the §6.6 options (1.5 h). Additional Services and G801 (1.5 h). Delivery methods, their document families, and the document-control example above (2 h). Approval register for a project you know (1 h). Redo PJM-14 to PJM-18 (1 h). Review your error log (1 h).
4Work Planning and ResourcesRebuild the critical-path table above from a blank page (1.5 h). Make up two schedule changes and solve them (1 h). Do fee-burn and role-capacity math with your own numbers (1.5 h). Read B101 §3.1.3 and A201 §§3.10 and 4.2.4 on schedules and communication (1.5 h). Redo PJM-01 to PJM-06 (1 h). Mixed review from your error log (1.5 h).
5Quality ControlSubmittal review limits and contractor vs. architect duties (2 h). Set up a review-comment log for a sample drawing set (1.5 h). Practice coordination conflicts like PJM-23 against an approved program (1.5 h). Redo PJM-19 to PJM-23 (1 h). Re-read your two weakest sections (2 h).
6Full rehearsalTake NCARB's free PjM practice exam in test mode, timed, using breaks the way you will on exam day (4 h with setup). Review every rationale, especially the ones you got right by guessing (2.5 h). Make targeted fixes from the results (1.5 h).

Error log

Keep one row for every miss and every lucky guess.

Error log
Question or topicMy answer and how sure I wasWhat I missedWhere to re-readNext action
Example: PJM-02B, unsureTotal hours can hide a shortage in one role"Fee, hours, and staff" aboveRecheck each role before comparing totals
Blank row for your own entry

Use NCARB's free PjM practice exam

NCARB offers a free practice exam for each division, with the same number of items as the real one. Results show what you got right and wrong, your percentages by section, and a rationale for every item (NCARB practice exams).

  • With active exam eligibility: log in to your NCARB Record, open the Exams tab, and go to Additional Resources, then the Practice Exam Dashboard.
  • Without active eligibility: log in to your NCARB Record and choose Practice the ARE under Quick Links.
  • Choose the right version: if the dashboard shows two versions, pick "ARE 5.0 Practice Exams (Effective Beginning April 27, 2026)" (NCARB, Feb. 23, 2026).

Use practice mode first to learn the tools and read the rationales as you go. Save test mode for a timed run. The practice exam's cut score is a fixed ~68%; the real divisions use passing standards NCARB sets for each division, so a practice percentage isn't your exam score. The public PDF versions leave out the case study resources, so do the case studies in your NCARB Record.

PjM exam facts and test-day rules

Last verified October 12, 2026, against NCARB's published pages and the ARE 5.0 Guidelines effective October 1, 2026.

PjM exam facts and test-day rules
TopicCurrent rule
Length75 items, 3 hours of testing, 30 minutes of break time, 3 hours 40 minutes total appointment (Guidelines p. 8)
Unscored itemsPjM includes 7 unscored pretest items and 68 scored items. Pretest items are mixed in and not identified (Guidelines pp. 40, 51, 78)
Question typesMultiple choice, check-all-that-apply, and hotspot; one point each, no partial credit (NCARB question types). Drag-and-place was retired April 28, 2025 (NCARB)
Case studiesUp to 7 case studies containing up to 16 items within the 75-item division (Guidelines p. 78). They come after the standalone items, and you can answer them in any order. Since April 27, 2026, each has one or two resources (NCARB)
ScoringPass/fail against a cut score for the whole division; wrong answers cost nothing, and blanks count as wrong, so answer everything (Guidelines p. 40)
ResultsProvisional feedback at the end of the exam; official score report in your NCARB Record within 7–10 calendar days (Guidelines p. 37)
RetakesAs soon as 60 days after your last attempt at PjM, and no more than three attempts at PjM in any 12 months (Guidelines p. 41)
Cost$263 per attempt. An exam seat can be rescheduled up to three times: free 31 or more days out, $75 at 15–30 days, and $150 at 7–14 days. Rescheduling and cancellation are not allowed less than seven days (168 hours) before the appointment. Canceling costs $200 and provides a replacement seat valid for one year from cancellation. Fees aren't refundable (NCARB fees)
Pass rate63% in 2025 and 60% in 2024, counting all attempts, first-time and repeat (NCARB pass rates)
Score validityA passed division stays valid while ARE 5.0 is delivered and carries credit into the next version. Passing score reports show an expiration date five years out, which matters if your jurisdiction has a rolling-clock-type requirement (Guidelines pp. 10, 38)

Breaks lock what you've seen. After any break, every item you've already viewed is locked, including items you marked for review. Finish the items you've opened before you step away (Guidelines p. 22).

Pace check: 180 minutes ÷ 75 items = 2.4 minutes per item on average. Allow for reading case-study resources; the average is a pacing check, not a time limit for every item.

For ID rules, accommodations, online-proctoring setup, and appointment changes, see the ARE 5.0 Guidelines.

Common questions

Is ARE Project Management the same as PMP? No. PjM is a division of the Architect Registration Examination, which architecture licensing boards use. It isn't a PMI project-management certification. Passing the ARE is one requirement for a license; the license itself comes from your jurisdiction's board (NCARB licensure requirements).

How is PjM different from Practice Management (PcM)? NCARB describes PcM as managing an architectural practice, including ethics and pre-contract work like negotiation (NCARB PcM page). PjM, in NCARB's words, covers the management of architectural projects: the team, the schedule, the contracts, and quality control. The two overlap on contracts, so B101 study helps with both.

Do the April 2026 changes make my older study materials useless? No. NCARB reworded five PjM objectives and changed how case studies are presented, but kept the division's items and time the same and said it didn't expect the changes to affect how candidates prepare (NCARB). Check old notes against the current objective list above.

How long should I study for PjM? Our six-week plan assumes about 48 hours; adjust it using your error log and your practice exam results.

Can I talk about PjM with other candidates? General topics and study strategy, yes. Anything specific you saw on your exam, no. The ARE Candidate Agreement prohibits sharing exam content, including in study groups and online (Guidelines pp. 43–44).

Sources

Checked October 12, 2026.

How we checked this page: We compared the exam facts with NCARB's current pages and the October 2026 ARE 5.0 Guidelines. We checked each contract explanation against the cited AIA form or AIA's own published summary, and we recalculated every worked example. The study plan is our editorial guidance. AI tools assisted research and editing; these are source and editorial checks. See our methodology.

By Castleport Test Prep Editorial Team · Last verified October 12, 2026

Castleport Test Prep is an independent exam prep publisher. We are not affiliated with, endorsed by, or approved by NCARB or the American Institute of Architects. Exam, credential, and document names are used only to identify their subjects; trademarks belong to their respective owners. The practice questions on this page are original and are not ARE exam items. Contract provisions are paraphrased for study; rely on the full document for any real project.