Castleport Test Prep

Free PE Civil Construction Practice Test

This free PE Civil Construction practice test has 40 original, unofficial questions with worked solutions across all 11 NCEES Civil: Construction knowledge areas, and there's no signup.

Practice questions

Question 1

Design for Support of Construction Loads · Support of excavation · Select one · PECON-01

A trench will be dug 8 ft deep with a 4 ft wide bottom next to a highway that carries heavy truck traffic all day. The soil is an unfissured, previously undisturbed, cohesive clay with an unconfined compressive strength of 2.0 tsf. It is subject to vibration from that traffic, with no layering, water, or other conditions that would make it Type C. Both walls will use the tabulated maximum simple slope in OSHA's Appendix B, Table B-1. What ground-surface width corresponds to that slope, before any additional flattening required by site conditions?

  • A. 12 ft
  • B. 16 ft
  • C. 20 ft
  • D. 28 ft
Answer and explanation, Question 1

Answer: C. 20 ft.

Start with classification, not the slope table. A strength of 2.0 tsf meets the Type A threshold (1.5 tsf or more), but Appendix A says no soil is Type A if it is subject to vibration from heavy traffic. Soil that meets the Type A strength but is subject to vibration is Type B. Type B's maximum allowable slope is 1H:1V for excavations 20 ft deep or less, so each wall lays back 8 ft. Top width = 4 + 2(8) = 20 ft.

Why the other choices miss: A: Type A's short-term ½H:1V slope (4 + 2 × 4). It doesn't apply: this soil isn't Type A. B: Type A's ¾H:1V slope (4 + 2 × 6). The strength qualifies, but the traffic vibration disqualifies Type A. D: Type C's 1½H:1V slope (4 + 2 × 12). Nothing in the stem makes this Type C.

This is the width corresponding to the tabulated slope. Appendix B(c)(3) also requires site conditions, including traffic surcharge and signs of distress, to be addressed when determining the actual slope. If factors affecting the soil classification change, Appendix A(c)(5) requires the competent person to evaluate them and reclassify the deposit as necessary.

Edition check: The classification and slope provisions used here match in the July 2020 CFR (Appendix A, Appendix B) and the 2024 CFR listed by NCEES.

Source: 29 CFR 1926 Subpart P, Appendix A (soil classification), Definitions of Type A (exception ii, vibration) and Type B (item iv); (c)(1)–(2), classification; (c)(5), reclassification; 29 CFR 1926 Subpart P, Appendix B (sloping and benching), (b), maximum allowable slope; (c)(3)(ii)–(iii), distress and surcharge; Table B-1; Figure B-1.2 (Type B simple slope).

It's half the length of the 80-question exam, and every question is written to hold under both the design standards in use now and the set that takes effect with the April 2027 exam.

How to use this test: work each question before you open its answer. For exam pace, give yourself 240 minutes for all 40; the real exam averages 6 minutes a question. Untimed is fine for a first pass. Scoring rules and the answer key follow Question 40.

Question 2

Project Planning and Scheduling · Network analysis (CPM) · Select one · PECON-02

All relationships are finish-to-start with no lag. Durations are in working days, starting at day 0, with no resource limits.

Question 2
ActivityDurationPredecessors
A2—
B6A
C4A
D3B
E5C
F2D and E

If activity B alone is shortened by one day, what is the earliest project finish?

  • A. Day 11
  • B. Day 12
  • C. Day 13
  • D. Day 14
Answer and explanation, Question 2

Answer: C. Day 13.

List the paths. A–B–D–F = 2 + 6 + 3 + 2 = 13 days. A–C–E–F = 2 + 4 + 5 + 2 = 13 days. Both are critical. Shortening B drops the first path to 12, but A–C–E–F still takes 13, so the project still finishes on day 13. To finish earlier, you'd have to shorten both paths or an activity they share (A or F).

Why the other choices miss: A: Subtracts the one-day change twice. B: Assumes there's only one critical path. D: Moves the finish the wrong way; a shorter activity can't lengthen this network.

Source: Hendrickson, Project Management for Construction, Chapter 10: Fundamental Scheduling Procedures, §10.3, critical path and forward pass.

Question 3

Soil Mechanics · Effective and total stress · Enter a number · PECON-03

Level ground. Before dewatering, the water table is 1 m below grade. A dewatering system lowers it to 4 m below grade and holds it there. Soil above the water table weighs 18 kN/m³ (including the zone that drains); soil below it weighs 20 kN/m³ (saturated). Assume hydrostatic water pressure, no seepage forces, no capillary rise, and γw = 9.81 kN/m³. By how much does the vertical effective stress at 8 m depth increase?

Enter your answer in kPa, rounded to one decimal place.

Answer and explanation, Question 3

Answer: 23.4 kPa. Any entry that rounds to 23.4 at the stated precision counts as correct.

Effective stress = total stress − pore-water pressure, with water pressure measured from the water table. Before: total = 1(18) + 7(20) = 158 kPa; u = 7(9.81) = 68.67 kPa; σ′ = 89.33 kPa. After: total = 4(18) + 4(20) = 152 kPa; u = 4(9.81) = 39.24 kPa; σ′ = 112.76 kPa. Increase = 112.76 − 89.33 = 23.43 kPa, or 23.4 kPa. Total stress actually drops a little, but pore pressure drops more, so the soil skeleton carries more load. That added effective stress is why dewatering can settle nearby structures.

Common wrong answers: 29.4 kPa: Keeps the 20 kN/m³ saturated weight in the drained 1–4 m zone, so it only counts the 3 m drop in water head (3 × 9.81).

Source: USACE EM 1110-1-1904, Settlement Analysis (Sept. 1990), hosted copy, Eq. 1-1, para. 1-5a(3)(a), p. 1-7: effective stress and hydrostatic pore-water pressure; Table 3-5, step 2, p. 3-29.

Question 4

Estimating Quantities and Costs · Quantity take-off · Select one · PECON-04

A continuous footing is 120 ft long, 2 ft wide, and 1 ft deep. The wall on it is 120 ft long, 8 in. thick, and 4 ft high. Add 5% waste to the total, then round the order up to the next 0.5 CY. How much concrete should be ordered?

  • A. 21.0 CY
  • B. 22.0 CY
  • C. 24.5 CY
  • D. 65.5 CY
Answer and explanation, Question 4

Answer: B. 22.0 CY.

Footing = 120 × 2 × 1 = 240 ft³. Wall = 120 × (8/12) × 4 = 320 ft³. Total = 560 ft³ ÷ 27 = 20.74 CY. With 5% waste: 20.74 × 1.05 = 21.78 CY. Round up to the next 0.5 CY: 22.0 CY.

Why the other choices miss: A: Skips the waste allowance (20.74 rounded up). C: Treats 8 in. as 0.8 ft instead of 0.667 ft. D: Divides cubic feet by 9 instead of 27.

Source: Worked from the stated inputs (unit conversion: 27 ft³ = 1 yd³).

Question 5

Construction Operations and Methods · Lifting and rigging · Select one · PECON-05

A 50 kN precast panel is lifted by two vertical slings attached at pick points A and B, 4.0 m apart. The panel's center of gravity lies between them, 1.6 m from A. Treat the lift as static and ignore rigging weight. What is the tension in the sling at B?

  • A. 20 kN
  • B. 25 kN
  • C. 30 kN
  • D. 50 kN
Answer and explanation, Question 5

Answer: A. 20 kN.

Take moments about A. The load acts 1.6 m from A, and B is 4.0 m from A. T_B × 4.0 = 50 × 1.6, so T_B = 20 kN. Then T_A = 50 − 20 = 30 kN. The sling farther from the center of gravity carries less.

Why the other choices miss: B: Splits the load evenly, which only works when the CG is centered. C: That's the tension at A; the lever arms are swapped. D: Puts the whole load on one sling.

Source: OpenStax, University Physics Vol. 1, Section 12.1: Conditions for Static Equilibrium, Equations 12.2–12.3 and 12.5–12.6, force and torque equilibrium.

Question 6

Material, Production, and Execution Quality Control · Compaction (field testing) · Enter a number · PECON-06

A field sample of compacted fill has a moist mass of 2,150 g. After oven drying, its mass is 1,925 g. What is its water content?

Enter your answer in percent, rounded to one decimal place.

Answer and explanation, Question 6

Answer: 11.7%. Any entry that rounds to 11.7 at the stated precision counts as correct.

Water content is the mass of water divided by the mass of dry solids: w = (2,150 − 1,925) ÷ 1,925 = 225 ÷ 1,925 = 0.1169, or 11.7%. If the spec required placement within 2 percentage points of a 13.5% optimum (11.5% to 15.5%), this sample meets that moisture criterion.

Common wrong answers: 10.5%: Divides by the moist mass (225 ÷ 2,150). Against the same moisture criterion, that wrong number would reject a sample that actually meets it.

Source: FHWA NHI-05-037, Geotechnical Aspects of Pavements, Chapter 5, Table 5-11: w = Ww/Ws.

Question 7

Structural Mechanics · Bending stress · Select one · PECON-07

A wood plank with actual dimensions 1.5 in. × 11.25 in. is laid flat across supports 8 ft apart. A 250 lb worker stands at midspan. Model the plank as simply supported and ignore its weight. What is the maximum bending stress in the plank?

  • A. 190 psi
  • B. 711 psi
  • C. 750 psi
  • D. 1,422 psi
Answer and explanation, Question 7

Answer: D. 1,422 psi.

For a center point load on a simple span, M = PL/4 = 250 × 96 / 4 = 6,000 lb-in. Laid flat, the bending depth is 1.5 in. and the width is 11.25 in., so S = bh²/6 = 11.25 × 1.5² / 6 = 4.219 in³. Stress = M/S = 6,000 / 4.219 = 1,422 psi. Orientation matters: on edge, the same plank would see only about 190 psi.

Why the other choices miss: A: Uses the plank on edge (h = 11.25 in.), which isn't how it's laid. B: Uses M = PL/8 by spreading the same total load uniformly over the span. C: Uses nominal dimensions (12 in. × 2 in.) instead of actual dressed size.

This is the demand stress only. Whether the plank is adequate depends on its allowable stress, which isn't given.

Source: American Wood Council, Design Aid 6: Beam Formulas with Shear and Moment Diagrams, Figure 7, simple beam with concentrated load at center, p. 7; Roylance, Stresses in Beams (MIT, 2000), Eqs. 5 and 7: I = bh³/12, σ = My/I.

Question 8

Health and Safety · OSHA excavation rules · Select two · PECON-08

Under 29 CFR 1926.652(a)(1), which two cases meet one of the stated exceptions to the requirement for a cave-in protective system?

Select two.

  • A. An 8 ft deep excavation made entirely in stable rock
  • B. A 4.5 ft deep trench where a competent person's examination of the ground shows no indication of a potential cave-in
  • C. A trench exactly 5.0 ft deep where a competent person's examination shows no indication of a potential cave-in
  • D. A 4.0 ft deep trench where no competent-person examination has been made
Answer and explanation, Question 8

Answer: A and B. Both must be selected, and nothing else, to score the point.

The rule lists two exceptions: excavations made entirely in stable rock, and excavations less than 5 ft deep where a competent person's examination of the ground gives no indication of a potential cave-in. A meets the first. B meets both parts of the second.

Why the other choices miss: C: Exactly 5.0 ft is not less than 5 ft. D: Meets the depth part only. The shallow-trench exception also needs the competent person's examination.

These exceptions cover cave-in protection only. Other applicable excavation requirements still apply.

Edition check: The provisions used in this question match in the July 2020 and 2024 CFR editions listed by NCEES.

Source: 29 CFR 1926.652, Requirements for protective systems, (a)(1)(i)–(ii).

Question 9

Site Layout and Development · Horizontal curves · Select one · PECON-09

A circular horizontal curve has its PI at station 25+00.00, a radius of 600 ft, and a deflection angle Δ of 40°. Stations are measured along the curve. What is the station of the PT?

  • A. 26+92.04
  • B. 27+00.50
  • C. 27+18.38
  • D. 29+18.88
Answer and explanation, Question 9

Answer: B. 27+00.50.

Tangent length T = R tan(Δ/2) = 600 tan 20° = 218.38 ft. PC = 2,500.00 − 218.38 = 22+81.62. Curve length L = 2πRΔ/360 = 2π(600)(40)/360 = 418.88 ft. PT = PC + L = 2,281.62 + 418.88 = 27+00.50.

Why the other choices miss: A: Adds the long chord (410.42 ft) instead of the arc length. C: Adds T to the PI station instead of adding the arc length to the PC station. D: Adds L to the PI instead of the PC.

Source: Caltrans Bridge Design Details, Attachment E: Horizontal Curve Equations (June 2025), Tangent distance T = R tan(Δ/2) and curve length L = 2πRΔ/360, p. 2A.E.1.

Question 10

Material Properties · Soil and aggregate classification · Select one · PECON-10

A borrow sample is mostly sand: more than half of its coarse fraction passes the No. 4 sieve, and only 3% passes the No. 200 sieve. From the gradation curve, D10 = 0.15 mm, D30 = 0.60 mm, and D60 = 1.80 mm. What is its USCS group symbol?

  • A. SW
  • B. SP
  • C. SM
  • D. GW
Answer and explanation, Question 10

Answer: A. SW.

Fines are under 5%, so it's a clean sand with no dual symbol. Cu = D60/D10 = 1.80/0.15 = 12. Cc = D30² / (D10 × D60) = 0.36 / 0.27 = 1.33. Cu = 12 exceeds 6, and Cc = 1.33 lies between 1 and 3. Both gradation checks pass: SW.

Why the other choices miss: B: Poorly graded sand fails at least one of these gradation checks; this sample passes both. C: Silty sand needs more than 12% fines; this has 3%. D: The sample is predominantly sand, not gravel.

Source: USDA NRCS, National Engineering Handbook Part 631, Chapter 3: Engineering Classification of Earth Materials (June 2022), Cu and Cc definitions, p. 631-3.23; Figure 3-17, p. 631-3.24 (gradation and fines criteria).

Question 11

Design for Support of Construction Loads · Shoring · Enter a number · PECON-11

An 8 in. normal-weight concrete slab (150 pcf) is supported on single post shores in a square grid. Use a formwork dead load of 10 psf and a construction live load of 50 psf, both supplied for this problem. Each shore has an allowable load of 4,000 lb and carries its full tributary area. What is the maximum square shore spacing based on shore axial capacity and tributary load alone?

Enter your answer in feet, rounded to one decimal place.

Answer and explanation, Question 11

Answer: 5.0 ft. Any entry that rounds to 5.0 at the stated precision counts as correct.

Slab weight = (8/12) × 150 = 100 psf. Total = 100 + 10 + 50 = 160 psf. Maximum tributary area per shore = 4,000 / 160 = 25 ft². For a square grid, spacing = √25 = 5.0 ft each way.

Common wrong answers: 6.0 ft: Leaves out the 50 psf live load (√(4,000/110) = 6.0 ft). 25 ft: Stops at the area and skips the square root.

The live load is a stipulated value for this problem, not a value from ASCE 37. A real shoring layout also checks stringers, joists, sills, and bracing.

Source: Worked from the stated inputs (statics: force = pressure × tributary area).

Question 12

Construction Operations and Methods · Cranes (lifting capacity) · Select one · PECON-12

A crane's load chart, in the configuration being used, lists these gross capacities: 35 ft radius, 21,200 lb; 40 ft, 18,500 lb; 45 ft, 16,100 lb. The chart's notes say to use the next longer listed radius when the actual radius falls between rows, and to deduct the hook block (650 lb), rigging (420 lb), and a stowed-jib deduction (1,200 lb) from the gross capacity. The load weighs 15,800 lb and will be set at a 42 ft radius. Can this lift be made within the chart?

  • A. Yes. Net capacity is 16,230 lb.
  • B. No. Net capacity is 13,830 lb.
  • C. Yes. The 16,100 lb capacity exceeds the 15,800 lb load.
  • D. Yes. Gross capacity is 18,500 lb.
Answer and explanation, Question 12

Answer: B. No. Net capacity is 13,830 lb.

A 42 ft radius falls between rows, so use the 45 ft row: 16,100 lb. Net capacity = 16,100 − 650 − 420 − 1,200 = 13,830 lb. The 15,800 lb load exceeds it, so the lift can't be made in this configuration.

Why the other choices miss: A: Uses the 40 ft row, which is shorter than the actual radius. C: Uses the right row but skips the deductions. D: Uses the wrong row and skips the deductions.

OSHA prohibits operating equipment above its rated capacity. Use the manufacturer's chart and notes for the actual configuration; this chart was invented for practice.

Edition check: The provisions used in this question match in the July 2020 and 2024 CFR editions listed by NCEES.

Source: 29 CFR 1926.1417, Cranes and derricks: operation, (a), manufacturer procedures; (o)(1), compliance with rated capacity; Worked from the stated inputs (chart values and deductions are supplied in the stem).

Question 13

Hydraulics and Hydrology · NRCS (SCS) runoff · Enter a number · PECON-13

A construction site's watershed has a runoff curve number CN = 80 (average runoff condition). The design storm's 24-hour rainfall is P = 4.0 in. Use the NRCS curve number method with Ia = 0.2S. What is the runoff depth Q?

Enter your answer in inches, rounded to two decimal places.

Answer and explanation, Question 13

Answer: 2.04 in. Any entry that rounds to 2.04 at the stated precision counts as correct.

S = 1,000/CN − 10 = 1,000/80 − 10 = 2.5 in. Ia = 0.2S = 0.5 in. Q = (P − 0.2S)² / (P + 0.8S) = (4.0 − 0.5)² / (4.0 + 2.0) = 12.25 / 6.0 = 2.04 in. TR-55's Table 2-1 lists the same value for CN 80 and 4.0 in. of rain.

Common wrong answers: 2.46 in: Drops the initial abstraction: P² / (P + S). 1.88 in: Uses S instead of 0.8S in the denominator.

Source: USDA NRCS (SCS), TR-55, Urban Hydrology for Small Watersheds, 2nd ed. (June 1986), university-hosted copy, Chapter 2, Eqs. 2-1 to 2-4, p. 2-1; Table 2-1, p. 2-3.

Question 14

Project Planning and Scheduling · Activity relationships and lags · Select one · PECON-14

Activity A (excavate trench) takes 10 days and starts on day 0. Activity B (lay pipe) takes 8 days. B has a start-to-start lag of 2 days from A and a finish-to-finish lag of 2 days from A. B can't be interrupted once it starts. Activity C (backfill) takes 3 days and starts after B finishes, with no lag. What is the earliest finish of C?

  • A. Day 13
  • B. Day 15
  • C. Day 21
  • D. Day 23
Answer and explanation, Question 14

Answer: B. Day 15.

B's start must satisfy both links. Start-to-start: B can't start before day 0 + 2 = 2. Finish-to-finish: B can't finish before A finishes plus 2 = day 12, so with an 8-day duration it can't start before day 4. The later limit controls: B runs days 4–12. C runs days 12–15.

Why the other choices miss: A: Ignores the finish-to-finish lag, so B runs 2–10. C: Treats the link as plain finish-to-start with no lag: B 10–18, C 18–21. D: Treats the 2-day start-to-start lag as a finish-to-start lag: B 12–20, C 20–23.

Source: Hendrickson, Project Management for Construction, Chapter 10: Fundamental Scheduling Procedures, §10.6, Example 10-4 (start-to-start and finish-to-finish lags).

Question 15

Estimating Quantities and Costs · Engineering economics (break-even) · Select one · PECON-15

Two pieces of equipment produce the same output per operating hour. Over the same job, option A costs $2,500 fixed plus $120 per operating hour. Option B costs $6,000 fixed plus $70 per operating hour. Ignore the time value of money and any other costs. At how many operating hours do the two options cost the same?

  • A. 18.4 hours
  • B. 50 hours
  • C. 70 hours
  • D. 120 hours
Answer and explanation, Question 15

Answer: C. 70 hours.

Set the costs equal: 2,500 + 120h = 6,000 + 70h. So 50h = 3,500 and h = 70 hours. Below 70 hours, A is cheaper; above it, B's lower hourly cost wins.

Why the other choices miss: A: Divides the fixed-cost difference by the sum of the hourly costs instead of the difference. B: Divides B's fixed cost by A's hourly cost. D: Divides B's whole fixed cost by the hourly difference, ignoring A's $2,500.

Source: Worked from the stated inputs (equating two linear cost expressions).

Question 16

Material, Production, and Execution Quality Control · Quality assurance and quality control · Select one · PECON-16

On a federal-aid highway project, a qualified evaluator who is independent of the acceptance testers watches them take samples, checks their testing equipment, and compares split-sample results. The goal is to evaluate the sampling and testing procedures used in the acceptance program. Under 23 CFR 637.203, what is this activity?

  • A. Contractor quality control
  • B. Verification sampling and testing
  • C. The agency's acceptance decision
  • D. Independent assurance
Answer and explanation, Question 16

Answer: D. Independent assurance.

The regulation defines an independent assurance program as an unbiased and independent evaluation of the sampling and testing procedures used in the acceptance program. The evaluator here is judging how the testing is done, not whether the material passes.

Why the other choices miss: A: Quality control is the contractor's own operational activity to meet the contract. B: Verification testing checks the quality of the product itself. C: The acceptance program covers the agency's determination of product quality; this activity evaluates the reliability of that program's testing.

Source: 23 CFR 637.203, Definitions (construction quality assurance), Definitions: independent assurance program, quality control, verification sampling and testing, acceptance program.

Question 17

Soil Mechanics · Lateral earth pressure · Select one · PECON-17

A temporary vertical wall retains 3.0 m of level, dry, cohesionless backfill with γ = 18 kN/m³ and φ′ = 30°. A uniform surcharge of q = 12 kPa sits on the backfill surface. Assume Rankine active conditions (the wall moves enough to mobilize active pressure), no wall friction, and no water. Treat the surcharge as adding a uniform lateral pressure of Ka·q over the full height. What is the total active thrust per meter of wall?

  • A. 27 kN/m
  • B. 39 kN/m
  • C. 66 kN/m
  • D. 351 kN/m
Answer and explanation, Question 17

Answer: B. 39 kN/m.

Ka = tan²(45° − φ′/2) = tan²(30°) = 1/3. Soil thrust (triangle) = ½ Ka γ H² = ½ × (1/3) × 18 × 3.0² = 27 kN/m. Surcharge thrust (rectangle) = Ka q H = (1/3) × 12 × 3.0 = 12 kN/m. Total = 39 kN/m.

Why the other choices miss: A: Leaves out the surcharge. C: Drops the ½ on the soil triangle (54 + 12). D: Uses the passive coefficient Kp = 3 instead of Ka.

The two parts act at different heights: the triangle's resultant at H/3, the surcharge's at H/2.

Source: Caltrans Trenching and Shoring Manual, Chapter 4 (July 2025), Eq. 4-3-11, p. 4-8; §4-3.02A, p. 4-9; Eq. 4-3-17, p. 4-10; Worked from the stated inputs (the surcharge term is the stem's stated assumption).

Question 18

Structural Mechanics · Combined axial and bending stress · Select one · PECON-18

At one section of a member, the internal axial force is 24 kip compression and the internal bending moment is 60 kip-in. The section's area is 12 in² and its elastic section modulus is 20 in³. Using linear elastic superposition, what is the normal stress at the extreme fiber where bending causes tension?

  • A. 1 ksi tension
  • B. 5 ksi compression
  • C. 5 ksi tension
  • D. 2 ksi compression
Answer and explanation, Question 18

Answer: A. 1 ksi tension.

Axial stress = P/A = 24/12 = 2 ksi compression everywhere on the section. Bending stress = M/S = 60/20 = 3 ksi, tension on one face and compression on the other. On the tension face: −2 + 3 = +1 ksi, or 1 ksi tension.

Why the other choices miss: B: That's the other face, where bending compression adds to the axial compression. C: Adds the magnitudes without signs. D: Ignores bending.

This is a stress calculation, not a capacity check; buckling and allowable stresses are outside it.

Source: Roylance, Stresses in Beams (MIT, 2000), Eq. 7, σ = My/I; OpenStax, University Physics Vol. 1, Section 12.3: Stress, Strain, and Elastic Modulus, Eq. 12.34, stress = F/A.

Question 19

Design for Support of Construction Loads · Scaffolding · Select two · PECON-19

A supported scaffold weighs 250 lb and has a maximum intended load of 1,250 lb. The general rule in 29 CFR 1926.451(a)(1) applies, and none of its exceptions does. Which two statements are correct under 1926.451(a)(1) and (f)(1)?

Select two.

  • A. The scaffold must support at least 5,250 lb without failure.
  • B. The scaffold must support at least 6,000 lb, because its own weight is also multiplied by 4.
  • C. Because of the factor of 4, workers may load it with up to 5,000 lb in normal use.
  • D. In use, it may not be loaded beyond its maximum intended load or its rated capacity, whichever is less.
Answer and explanation, Question 19

Answer: A and D. Both must be selected, and nothing else, to score the point.

Paragraph (a)(1) requires each scaffold to support its own weight plus at least 4 times the maximum intended load: 250 + 4(1,250) = 5,250 lb. Paragraph (f)(1) separately limits actual loading to the lesser of the maximum intended load and the rated capacity.

Why the other choices miss: B: The factor of 4 applies to the intended load, not the scaffold's own weight. C: The factor of 4 is a capacity margin, not permission to load four times higher.

Edition check: The provisions used in this question match in the July 2020 and 2024 CFR editions listed by NCEES.

Source: 29 CFR 1926.451, Scaffolds: general requirements, (a)(1) and (f)(1).

Question 20

Construction Operations and Methods · Dewatering and pumping · Enter a number · PECON-20

A dewatering pump moves 600 gpm of water (specific gravity 1.0). The static lift is 24 ft, and all other system losses at that flow total 18 ft. Pump efficiency is 70%. Using P = Q·H·s / (3,960·η), with Q in gpm and H in ft, what pump input (shaft) power is required?

Enter your answer in horsepower, rounded to two decimal places.

Answer and explanation, Question 20

Answer: 9.09 hp. Any entry that rounds to 9.09 at the stated precision counts as correct.

Total head H = 24 + 18 = 42 ft. P = 600 × 42 × 1.0 / (3,960 × 0.70) = 25,200 / 2,772 = 9.09 hp.

Common wrong answers: 6.36 hp: The hydraulic (water) power, before dividing by efficiency. 5.19 hp: Uses only the 24 ft static lift and leaves out the losses. 4.45 hp: Multiplies by the efficiency instead of dividing.

This is shaft power. Motor or electrical input would also include motor efficiency, and pump selection would check suction conditions.

Source: Hydraulic Institute Data Tool, Pump Curves, Eqs. 1.B.3–1.B.5 (pump efficiency and input power).

Question 21

Material Properties · Structural steel properties · Select one · PECON-21

A steel tie rod 1.60 m long carries a uniform axial tensile stress of 150 MPa, within its linear elastic range. Take E = 200 GPa. How much does it stretch?

  • A. 0.0012 mm
  • B. 0.75 mm
  • C. 1.20 mm
  • D. 1,200 mm
Answer and explanation, Question 21

Answer: C. 1.20 mm.

Strain = stress / E = 150 MPa / 200,000 MPa = 0.00075. Elongation = strain × length = 0.00075 × 1,600 mm = 1.20 mm.

Why the other choices miss: A: Mixes meters and millimeters. B: Multiplies the strain by 1,000 mm instead of the rod's 1,600 mm length. D: Treats 200 GPa as 200 MPa.

Stiffness (E) controls stretch; strength controls whether the rod yields. They're different properties.

Source: OpenStax, University Physics Vol. 1, Section 12.3: Stress, Strain, and Elastic Modulus, Eqs. 12.33–12.36 (stress, strain, Young's modulus).

Question 22

Site Layout and Development · Vertical curves · Enter a number · PECON-22

An equal-tangent parabolic crest vertical curve has an incoming grade of +3.0%, an outgoing grade of −2.0%, and a length of 600 ft. Its BVC is at station 12+00. How far from the BVC, measured horizontally, is the high point?

Enter your answer in feet, rounded to the nearest whole foot.

Answer and explanation, Question 22

Answer: 360 ft. Any entry that rounds to 360 at the stated precision counts as correct.

The curve's grade changes linearly from g1 to g2 over its length: grade at x = g1 + (g2 − g1)x/L. The high point is where that grade is zero: x = g1·L / (g1 − g2) = 0.03 × 600 / 0.05 = 360 ft, or station 15+60.

Common wrong answers: 300 ft: Assumes the high point has the PVI's station, halfway through the curve. That station is correct only when the grades are equal and opposite. 240 ft: Uses g2 in the numerator, which locates the point measured from the EVC instead.

Source: Caltrans Bridge Design Details, Attachment D: Vertical Curve Calculations (June 2025), Eq. 5 (elevation on a vertical curve, rate of grade change R/C), p. 2A.D.1; Worked from the stated inputs (high-point location found by setting the curve's slope to zero).

Question 23

Health and Safety · Work zone traffic control · Put in order · PECON-23

A temporary traffic control zone is divided into four areas. Put them in the order a driver reaches them, first to last.

Write the areas in order, first to last.

  • Activity area
  • Termination area
  • Advance warning area
  • Transition area
Answer and explanation, Question 23

Answer: Advance warning area → Transition area → Activity area → Termination area.

Drivers are first warned (advance warning area), then moved out of their normal path (transition area, where merging and shifting tapers redirect traffic), then pass the work (activity area, which holds the buffer space and work space), and finally return to normal (termination area).

Common mistake: Swapping transition and activity areas is a mistake to watch for. Merging and shifting tapers redirect traffic in the transition area; downstream tapers can be in the termination area.

Edition check: The same four areas, in the same order, in the 2009 MUTCD (current exam) and the 11th edition (from April 2027). The relevant sections are 6C.03 and 6B.03.

Source: MUTCD 2009 Edition with Revisions 1 and 2 (May 2012), Part 6, §6C.03, p. 552; §6C.08, paragraph 01, p. 555; MUTCD 11th Edition (Dec. 2023), Part 6, §6B.03, p. 771; §6B.08, paragraph 01, p. 775.

Question 24

Project Planning and Scheduling · Resource scheduling · Select one · PECON-24

One crane is available. Activities that don't need the crane can run at the same time as anything else. All links are finish-to-start with no lag, activities can't be interrupted, and work starts at day 0.

Question 24
ActivityDuration (days)PredecessorsNeeds crane?
A2—Yes
B4—No
C3BYes
D5AYes
E1C and DNo

What is the earliest feasible project finish?

  • A. Day 8
  • B. Day 10
  • C. Day 11
  • D. Day 13
Answer and explanation, Question 24

Answer: C. Day 11.

Crane work totals 2 + 3 + 5 = 10 days, so with E after it the project can't finish before day 11. One schedule achieves that: A on days 0–2, D on 2–7, C on 7–10 (B already finished on day 4), and E on 10–11. The crane never sits idle.

Why the other choices miss: A: The unconstrained CPM answer, which ignores the single-crane conflict. B: Forgets activity E. D: Starts C as soon as B finishes (day 4), which leaves the crane idle on days 2–4 and pushes D to days 7–12.

Source: Hendrickson, Project Management for Construction, Chapter 10: Fundamental Scheduling Procedures, §10.9, scheduling with resource constraints; Worked from the stated inputs (lower bound from total crane-days, then a feasible schedule that meets it).

Question 25

Material, Production, and Execution Quality Control · Bolt installation · Select two · PECON-25

Under the RCSC Specification, which two of these bolted shear joints must be slip-critical?

Select two.

  • A. A joint that uses oversized holes
  • B. A joint with short-slotted holes whose load acts perpendicular (within 80° to 100°) to the slot
  • C. A joint subject to fatigue loading with reversal of the loading direction
  • D. A statically loaded joint with standard holes where slip would not affect the structure
Answer and explanation, Question 25

Answer: A and C. Both must be selected, and nothing else, to score the point.

RCSC §4.3 requires slip-critical joints for fatigue loading with load reversal, oversized holes, slotted holes except where the load is approximately normal (80° to 100°) to the slot, and cases where slip would be detrimental. A and C are on that list.

Why the other choices miss: B: This is the stated exception for slotted holes. D: Nothing here calls for slip resistance; a snug-tightened joint is typical.

Edition check: Same four triggers in the 2014 RCSC Specification (printed in the AISC 15th edition Manual) and the 2020 edition (16th edition Manual).

Source: RCSC, Specification for Structural Joints Using High-Strength Bolts (Aug. 2014, with April 2015 errata), §4.3, Slip-Critical Joints, pp. 16.2-29–16.2-30; RCSC, Specification for Structural Joints Using High-Strength Bolts (June 2020), §4.3, p. 16.2-35.

Question 26

Estimating Quantities and Costs · Cost estimating (unit cost) · Select one · PECON-26

A pipe crew is one foreman at $62/hr, four laborers at $44/hr each, and equipment at $95/hr. The crew installs 45 linear feet of pipe per hour. What is the crew's cost per linear foot?

  • A. $0.93/LF
  • B. $4.47/LF
  • C. $5.29/LF
  • D. $7.40/LF
Answer and explanation, Question 26

Answer: D. $7.40/LF.

Crew cost = 62 + 4(44) + 95 = $333/hr. Unit cost = 333 / 45 = $7.40 per LF.

Why the other choices miss: A: Divides the hourly cost by a full day's output (8 × 45 = 360 LF). B: Counts only one laborer. C: Leaves out the equipment.

Source: Worked from the stated inputs (unit cost = crew cost per hour ÷ production per hour).

Question 27

Design for Support of Construction Loads · Bracing and anchorage · Select one · PECON-27

A 12 ft tall wall form must resist a uniform wind pressure of 20 psf over its full height (a supplied design value). The base of the form is treated as a pin. One brace per 8 ft of wall attaches to the form 9 ft above the base and slopes down to a ground anchor at 60° from horizontal. Ignore the form's weight. What is the axial force in each brace?

  • A. 1,280 lb
  • B. 1,478 lb
  • C. 2,560 lb
  • D. 3,840 lb
Answer and explanation, Question 27

Answer: C. 2,560 lb.

Per foot of wall, wind = 20 × 12 = 240 lb acting at 6 ft. Moments about the pinned base: H × 9 = 240 × 6, so the brace's horizontal component H = 160 lb per ft. Per brace: 160 × 8 = 1,280 lb. The brace is at 60° from horizontal, so its axial force = 1,280 / cos 60° = 2,560 lb.

Why the other choices miss: A: Stops at the horizontal component. B: Divides by sin 60° instead of cos 60°. D: Gives the brace the whole wind load (240 × 8 = 1,920 lb) instead of sharing it with the base, then divides by cos 60°.

The brace force also has a vertical component (2,560 × sin 60° ≈ 2,217 lb) that the anchor and the form connection must carry.

Source: OpenStax, University Physics Vol. 1, Section 12.1: Conditions for Static Equilibrium, Equations 12.2–12.3 and 12.5–12.6, force and torque equilibrium.

Question 28

Construction Operations and Methods · Excavation (borrow pit volume) · Enter a number · PECON-28

A borrow area is laid out as two adjacent 20 ft × 20 ft grid squares sharing one side. Cut depths at the six grid corners, from existing ground to a flat planned bottom, are: top row 2.0, 3.0, 5.0 ft and bottom row 1.0, 2.0, 3.0 ft (the middle values in each row are the shared corners). Using the average of each square's four corner depths, what is the excavated volume?

Enter your answer in bank cubic yards, rounded to one decimal place.

Answer and explanation, Question 28

Answer: 77.8 BCY. Any entry that rounds to 77.8 at the stated precision counts as correct.

Left square corners: 2.0, 3.0, 1.0, 2.0, average 2.0 ft, volume 400 × 2.0 = 800 ft³. Right square: 3.0, 5.0, 2.0, 3.0, average 3.25 ft, volume 400 × 3.25 = 1,300 ft³. Total 2,100 ft³ ÷ 27 = 77.8 BCY. The shortcut V = (A/4)(Σh₁ + 2Σh₂) gives the same: (400/4)(11 + 2 × 5) = 2,100 ft³, where h₁ are corners used once and h₂ corners shared by two squares.

Common wrong answers: 79.0 BCY: Averages all six depths equally (2.67 ft × 800 ft²), which over-weights the outer corners.

Source: Worked from the stated inputs (each square is treated as a prism with the average of its corner depths; consistent with the average end-area idea of averaging bounding dimensions).

Question 29

Structural Mechanics · Deflection · Select one · PECON-29

Two separate simply supported beams have the same material, cross section, and uniform load per unit length w. The second span is half as long as the first. Assuming small elastic deflections and neglecting shear deformation, what is the ratio of the second beam's maximum deflection to the first's?

  • A. 1/2
  • B. 1/4
  • C. 1/8
  • D. 1/16
Answer and explanation, Question 29

Answer: D. 1/16.

Maximum deflection of a simple span under uniform load is Δ = 5wL⁴ / (384EI). With w, E and I unchanged, Δ scales with L⁴: (1/2)⁴ = 1/16.

Why the other choices miss: A: Assumes deflection is proportional to span. B: Uses the L² scaling of moment. C: Holds the total load fixed instead of the load per foot (PL³ scaling).

Halving the span by adding a support under one continuous beam is a different structural model, with a different answer.

Source: American Wood Council, Design Aid 6: Beam Formulas with Shear and Moment Diagrams, Figure 1, simple beam with uniformly distributed load, p. 4.

Question 30

Soil Mechanics · Consolidation settlement · Select one · PECON-30

A 10 ft thick clay layer has e0 = 0.90, Cc = 0.35, and Cr = 0.05. At mid-layer, the current effective stress is 1,000 psf and the preconsolidation stress is 2,500 psf. A new fill raises the mid-layer effective stress to 2,000 psf. Treating the layer as one sublayer with mid-depth values, what is the ultimate primary consolidation settlement?

  • A. 0.95 in.
  • B. 1.81 in.
  • C. 2.19 in.
  • D. 6.65 in.
Answer and explanation, Question 30

Answer: A. 0.95 in.

The final stress (2,000 psf) stays below the preconsolidation stress (2,500 psf), so the clay only recompresses: use Cr. Δe = Cr log₁₀(σ′f / σ′0) = 0.05 × log₁₀(2) = 0.01505. Settlement = Δe / (1 + e0) × H = 0.01505 / 1.90 × 120 in. = 0.95 in.

Why the other choices miss: B: Leaves out the 1 + e0 divisor. C: Uses the natural log instead of log base 10. D: Uses Cc, as if the clay were loaded past its preconsolidation stress.

If the fill pushed the stress past 2,500 psf, you'd add a Cc term for the part above the preconsolidation stress.

Source: USACE EM 1110-1-1904, Settlement Analysis (Sept. 1990), hosted copy, Para. 3-12; Eq. 3-20, p. 3-28; Eq. 3-23 and following instructions, p. 3-34 (when σ′f < σ′p, omit the Cc term and substitute σ′f for σ′p in the Cr term).

Question 31

Hydraulics and Hydrology · Pipe flow (continuity) · Enter a number · PECON-31

Steady flow of 1.80 m³/s enters a storm drain junction. A side branch takes 0.45 m³/s. All the rest flows full through a circular pipe with an inside diameter of 0.75 m. There's no storage or other inflow. What is the mean velocity in that pipe?

Enter your answer in m/s, rounded to two decimal places.

Answer and explanation, Question 31

Answer: 3.06 m/s. Any entry that rounds to 3.06 at the stated precision counts as correct.

Flow in the pipe = 1.80 − 0.45 = 1.35 m³/s. Area = π(0.75)²/4 = 0.4418 m². Velocity = Q/A = 1.35 / 0.4418 = 3.06 m/s.

Common wrong answers: 4.07 m/s: Forgets to subtract the side branch. 0.76 m/s: Uses the diameter as the radius in the area.

Source: OpenStax, University Physics Vol. 1, Section 14.5: Fluid Dynamics, Q = Av and Eq. 14.14 (continuity for incompressible flow).

Question 32

Material, Production, and Execution Quality Control · Concrete maturity · Select one · PECON-32

Two slabs are placed from the same mix, which has a valid strength–maturity calibration curve. Using the Nurse-Saul function with a datum temperature of −10 °C: slab X averages 25 °C for the first 24 hours and 5 °C for the next 24 hours; slab Y averages 15 °C for all 48 hours. Which statement about their 48-hour strength estimates is correct?

  • A. Both have a maturity of 1,200 °C·h, so the curve gives the same strength estimate
  • B. X is higher, because it was warmer during the first day
  • C. Y is higher, because its temperature was steadier
  • D. They can't be compared, because they cured at different temperatures
Answer and explanation, Question 32

Answer: A. Both have a maturity of 1,200 °C·h.

M = Σ(T − T0)Δt. Slab X: (25 + 10)(24) + (5 + 10)(24) = 840 + 360 = 1,200 °C·h. Slab Y: (15 + 10)(48) = 1,200 °C·h. Same mix, same curve, same maturity, so the same estimated strength. That's the point of the maturity method: it converts different temperature histories to a common index.

Why the other choices miss: B: The order of these temperature intervals does not change the accumulated Nurse-Saul maturity. C: Steadiness isn't a factor in the function. D: Comparing different temperature histories is exactly what the maturity method is for, as long as the curve matches the mix.

The curve has to come from this mix; a change in materials or proportions requires a new curve.

Source: FHWA-IF-06-004, Maturity Testing for Concrete Pavement Applications (TechBrief, Nov. 2005), Nurse-Saul equation, p. 2; calibration curve requirements, p. 3.

Question 33

Site Layout and Development · Leveling and grade stakes · Select one · PECON-33

From a benchmark at elevation 512.40 ft, a level run takes a backsight of 3.85 ft, then a foresight of 7.10 ft on a turning point. After moving the level, the backsight on that turning point is 2.64 ft. The rod reading on existing ground at a stake is 5.27 ft. The design subgrade elevation at the stake is 505.90 ft. What goes on the stake?

  • A. Cut 0.62 ft
  • B. Fill 0.62 ft
  • C. Fill 4.66 ft
  • D. Cut 6.50 ft
Answer and explanation, Question 33

Answer: A. Cut 0.62 ft.

HI₁ = 512.40 + 3.85 = 516.25. TP = 516.25 − 7.10 = 509.15. HI₂ = 509.15 + 2.64 = 511.79. Ground = 511.79 − 5.27 = 506.52. Ground is 506.52 − 505.90 = 0.62 ft above design, so cut 0.62 ft.

Why the other choices miss: B: Right size, wrong direction: ground above grade means cut. C: Subtracts the backsight at the turning point instead of adding it. D: Compares the design elevation to the benchmark instead of to the ground at the stake.

Source: FHWA-HRT-08-056, LTPP Manual for Profile Measurements, Chapter 4 (rod and level), §4.3.5, instrument height at turning points (new HI = old HI − FS + BS).

Question 34

Design for Support of Construction Loads · Formwork and shore removal · Select two · PECON-34

For an elevated cast-in-place slab (not a slab on grade or a slip form), 29 CFR 1926.703(e)(1) says forms and shores can't be removed until the employer determines the concrete can support its own weight and superimposed loads. Which two are permitted bases for that determination?

Select two.

  • A. The plans and specifications stipulate conditions for removal, and those conditions have been followed.
  • B. Seven days have passed since placement.
  • C. The concrete was properly tested using an appropriate ASTM method for indicating compressive strength, and the results show enough strength to support its own weight and superimposed loads.
  • D. The surface looks hard and dry.
Answer and explanation, Question 34

Answer: A and C. Both must be selected, and nothing else, to score the point.

The rule gives two routes: following the removal conditions in the plans and specifications, or proper ASTM compressive-strength testing showing that the concrete has gained enough strength to support its own weight and superimposed loads.

Why the other choices miss: B: A fixed age isn't one of the routes. The rule doesn't set any default number of days. D: Appearance tells you nothing reliable about in-place strength.

Removing reshores is covered separately by 1926.703(e)(2).

Edition check: The provisions used in this question match in the July 2020 and 2024 CFR editions listed by NCEES.

Source: 29 CFR 1926.703, Requirements for cast-in-place concrete, (e)(1)(i)–(ii) and (e)(2).

Question 35

Project Planning and Scheduling · Time-cost trade-off · Select one · PECON-35

Two parallel branches each take 20 days, and both must finish before a common final activity that takes 2 days. The project takes 22 days. Branch 1 can be shortened up to 2 days at $200/day. Branch 2 can be shortened up to 2 days at $350/day. The final activity can be shortened by 1 day at $800. Costs are linear and only whole days can be bought. What is the minimum added cost to finish in 20 days?

  • A. $400
  • B. $1,100
  • C. $1,350
  • D. $1,900
Answer and explanation, Question 35

Answer: B. $1,100.

Both branches are critical, so each day of time saved on the branches has to be bought on both: $200 + $350 = $550 per day. The final activity saves a day for $800 but can only give one day. Cheapest way to save two days: two days on each branch, 2($200) + 2($350) = $1,100. The next-cheapest feasible mix, one day on each branch plus the final activity, costs $550 + $800 = $1,350.

Why the other choices miss: A: Shortens only branch 1; branch 2 still controls at 22 days. C: Feasible, but $250 more than the cheapest option. D: Crashes everything available (both branches 2 days plus the final activity). That buys a third day nobody asked for.

Source: GAO-16-89G, Schedule Assessment Guide (Dec. 2015), Table 6, p. 145 (shortening a schedule by crashing); Worked from the stated inputs (enumerating the feasible whole-day options).

Question 36

Material Properties · High-strength bolts · Select one · PECON-36

Which of these high-strength bolts may be reused, if the engineer of record approves?

  • A. A galvanized ASTM A325 bolt
  • B. An uncoated ASTM A490 bolt
  • C. Any high-strength bolt, as long as the nut runs down the threads by hand
  • D. An uncoated (black) ASTM A325 bolt
Answer and explanation, Question 36

Answer: D. An uncoated (black) A325 bolt.

Both RCSC editions on the exam ban reuse of A490-family bolts and of galvanized bolts. Plain (black) A325 bolts are the reusable ones: the 2014 Specification allows it with the engineer of record's approval, and the 2020 edition allows it with that approval in pretensioned and slip-critical joints (and without it in snug-tightened joints). Touching up or retightening bolts loosened by nearby installation isn't reuse.

Why the other choices miss: A: Galvanized A325 bolts can't be reused. B: A490 bolts can't be reused, coated or not. C: The hand-run nut check is a commentary rule of thumb for black A325 bolts only.

Edition check: The 2014 RCSC Specification (AISC 15th edition Manual) also bans reuse of twist-off tension-control assemblies. The 2020 edition (16th edition Manual) uses Group 120 (A325 family) and Group 150 (A490 family) names, bans reuse of Group 150 and of galvanized or coated bolts, and drops the EOR approval for plain Group 120 bolts in snug-tightened joints. The keyed answer is correct under both.

Source: RCSC, Specification for Structural Joints Using High-Strength Bolts (Aug. 2014, with April 2015 errata), §2.3.3, Reuse, and its commentary, p. 16.2-6; RCSC, Specification for Structural Joints Using High-Strength Bolts (June 2020), §2.11 (2.11.1–2.11.3) and commentary, pp. 16.2-19–16.2-20.

Question 37

Estimating Quantities and Costs · Earned value · Select two · PECON-37

At a status date, three cost accounts show:

Question 37
AccountBudgetPercent complete
Excavation$200,00080%
Concrete$500,00040%
Steel erection$300,0000%

Planned value (PV) to date is $400,000 and actual cost (AC) to date is $450,000. Which two statements are correct?

Select two.

  • A. Earned value (EV) is $360,000.
  • B. The cost performance index (CPI) is 1.25.
  • C. The work done so far has cost more than its budgeted value.
  • D. Schedule variance is +$40,000.
Answer and explanation, Question 37

Answer: A and C. Both must be selected, and nothing else, to score the point.

EV = 0.80(200,000) + 0.40(500,000) + 0(300,000) = $360,000. AC ($450,000) is more than EV, so the work performed cost more than budgeted (CPI = 360,000 / 450,000 = 0.80). SPI = 360,000 / 400,000 = 0.90.

Why the other choices miss: B: Inverts the ratio (AC/EV). CPI is EV/AC. D: Schedule variance is EV − PV = −$40,000: behind schedule, not ahead.

Source: NSF, Earned Value Management Gold Card, EVM definitions; CPI = EV/AC, SPI = EV/PV, SV = EV − PV.

Question 38

Construction Operations and Methods · Dewatering (seepage) · Enter a number · PECON-38

Groundwater seeps through a sand layer into an excavation. The sand's hydraulic conductivity is K = 2.0 × 10⁻⁴ m/s, the hydraulic gradient is 0.25, and the flow area perpendicular to the flow is 120 m². Assume steady, saturated, laminar flow (Darcy's law applies). What is the seepage rate?

Enter your answer in liters per second, rounded to one decimal place.

Answer and explanation, Question 38

Answer: 6.0 L/s. Any entry that rounds to 6.0 at the stated precision counts as correct.

Q = K·i·A = (2.0 × 10⁻⁴)(0.25)(120) = 0.0060 m³/s = 6.0 L/s. That's about 518 m³ per day for the pumps to handle.

Common wrong answers: 24.0 L/s: Leaves out the hydraulic gradient. 0.0060 L/s: Correct in m³/s, but the question asks for L/s.

Source: FHWA/IN/JTRP-2019/04, Investigating the Need for Drainage Layers in Flexible Pavements (Feb. 2019), Eq. 2.7, p. 9 (PDF p. 20): Q = kiA and the steady, saturated, laminar-flow conditions.

Question 39

Structural Mechanics · Retaining structures (overturning) · Select one · PECON-39

A precast barrier with a 2.5 ft wide base is used as a short temporary retaining wall for 3.6 ft of soil. It weighs 2,400 lb per foot of length, and its weight acts 1.25 ft horizontally from the toe. The retained soil exerts a lateral thrust of 900 lb per foot, acting 1.2 ft above the base (one-third of the retained height). Ignore passive resistance and any other forces. What is the factor of safety against overturning about the toe?

  • A. 0.36
  • B. 1.85
  • C. 2.78
  • D. 5.56
Answer and explanation, Question 39

Answer: C. 2.78.

Resisting moment = 2,400 × 1.25 = 3,000 lb-ft per ft. Overturning moment = 900 × 1.2 = 1,080 lb-ft per ft. FS = 3,000 / 1,080 = 2.78.

Why the other choices miss: A: Inverts the ratio (overturning ÷ resisting). B: Puts the thrust at mid-height (1.8 ft) instead of one-third of the height (1.2 ft), where a triangular pressure resultant acts. D: Uses the full 2.5 ft base width as the weight's lever arm instead of the distance to the weight's line of action.

Overturning is one check; sliding and bearing are separate.

Source: OpenStax, University Physics Vol. 1, Section 12.1: Conditions for Static Equilibrium, Eq. 12.5, torque equilibrium; Eq. 12.10, moment arm; FHWA, Rockery Design and Construction Guidelines, Chapter 4, Overturning, Figures 37–39: resisting and overturning moments about the toe; FS = resisting moment / overturning moment.

Question 40

Health and Safety · Work zone tapers · Select one · PECON-40

A lane shift moves traffic 11 ft laterally on a road where the speed used for taper design is 35 mph. Using the MUTCD Part 6 taper-length guidance, what is the minimum shifting taper length?

  • A. About 112 ft
  • B. About 193 ft
  • C. About 225 ft
  • D. About 385 ft
Answer and explanation, Question 40

Answer: A. About 112 ft.

At 40 mph or less, L = WS²/60 = 11 × 35² / 60 = 224.6 ft. A shifting taper needs at least 0.5L = 112.3 ft, so about 112 ft.

Why the other choices miss: B: Half of WS, the formula for 45 mph and above. C: The full L, which is the merging-taper length, not a shift. D: WS, the high-speed formula, unhalved.

Edition check: Same formulas and taper fractions in the 2009 MUTCD (current exam) and the 11th edition (from April 2027); only the table numbers changed.

Source: MUTCD 2009 Edition with Revisions 1 and 2 (May 2012), Part 6, §6C.08; Tables 6C-3 and 6C-4, p. 557; MUTCD 11th Edition (Dec. 2023), Part 6, §6B.08; Tables 6B-3 and 6B-4, p. 775.

Score your attempt

Give yourself one point for each question you got right before reading its explanation.

  • Select two and Put in order questions are all-or-nothing, the way NCEES scores its alternative item types. One wrong or missing choice scores zero.
  • Enter a number questions count if your answer rounds to the key at the precision the question asks for.
  • Your score is correct answers ÷ 40. Count unanswered questions separately, so you can tell "didn't know" from "ran out of time."

Answer key

Answer key
QuestionKnowledge areaFormatAnswer
1Design for Support of Construction LoadsSelect oneC
2Project Planning and SchedulingSelect oneC
3Soil MechanicsEnter a number23.4 kPa
4Estimating Quantities and CostsSelect oneB
5Construction Operations and MethodsSelect oneA
6Material, Production, and Execution Quality ControlEnter a number11.7%
7Structural MechanicsSelect oneD
8Health and SafetySelect twoA and B
9Site Layout and DevelopmentSelect oneB
10Material PropertiesSelect oneA
11Design for Support of Construction LoadsEnter a number5.0 ft
12Construction Operations and MethodsSelect oneB
13Hydraulics and HydrologyEnter a number2.04 in
14Project Planning and SchedulingSelect oneB
15Estimating Quantities and CostsSelect oneC
16Material, Production, and Execution Quality ControlSelect oneD
17Soil MechanicsSelect oneB
18Structural MechanicsSelect oneA
19Design for Support of Construction LoadsSelect twoA and D
20Construction Operations and MethodsEnter a number9.09 hp
21Material PropertiesSelect oneC
22Site Layout and DevelopmentEnter a number360 ft
23Health and SafetyPut in orderAdvance warning → Transition → Activity → Termination
24Project Planning and SchedulingSelect oneC
25Material, Production, and Execution Quality ControlSelect twoA and C
26Estimating Quantities and CostsSelect oneD
27Design for Support of Construction LoadsSelect oneC
28Construction Operations and MethodsEnter a number77.8 BCY
29Structural MechanicsSelect oneD
30Soil MechanicsSelect oneA
31Hydraulics and HydrologyEnter a number3.06 m/s
32Material, Production, and Execution Quality ControlSelect oneA
33Site Layout and DevelopmentSelect oneA
34Design for Support of Construction LoadsSelect twoA and C
35Project Planning and SchedulingSelect oneB
36Material PropertiesSelect oneD
37Estimating Quantities and CostsSelect twoA and C
38Construction Operations and MethodsEnter a number6.0 L/s
39Structural MechanicsSelect oneC
40Health and SafetySelect oneA

Tally by knowledge area

Tally by knowledge area
Knowledge areaQuestionsYour correct
Soil Mechanics3, 17, 30___ of 3
Site Layout and Development9, 22, 33___ of 3
Material Properties10, 21, 36___ of 3
Estimating Quantities and Costs4, 15, 26, 37___ of 4
Project Planning and Scheduling2, 14, 24, 35___ of 4
Material, Production, and Execution Quality Control6, 16, 25, 32___ of 4
Structural Mechanics7, 18, 29, 39___ of 4
Hydraulics and Hydrology13, 31___ of 2
Construction Operations and Methods5, 12, 20, 28, 38___ of 5
Design for Support of Construction Loads1, 11, 19, 27, 34___ of 5
Health and Safety8, 23, 40___ of 3

What your score means

Your percentage describes how you did on these 40 questions. It isn't an NCEES score, and it doesn't predict a pass. NCEES counts correct answers, converts that count to a scaled score to adjust for differences between exam forms, and doesn't publish the passing score (NCEES Examinee Guide, May 2026, p. 14). Each knowledge area here has two to five questions, so a miss points to a skill worth checking, not a measured weakness in the whole area.

One rule carries straight to exam day: NCEES doesn't take points off for wrong answers, so make your best guess on any remaining unanswered question.

Turn each miss into a fix

For every miss (and every lucky guess), write down the first step that went wrong. Fix that step, not the whole topic.

Turn each miss into a fix
What went wrongWhat to do nextYou've fixed it when
Wrong method or modelSay in one sentence what the question asks for and which relationship fits, then rework it from a blank pageYou can explain why the method you first chose doesn't apply
Units or states mixed upRewrite every input in consistent units before substituting; label volumes as bank, loose, or compacted and angles by where they're measured fromThe units cancel to exactly what the question asks for
Missed a conditionUnderline the controlling detail: water table depth, "less than 5 ft," "same load per foot," "one crane"You can name the condition that changes the answer
Reference or ruleFind the provision in the handbook or standard you'll have on exam day, and note the sectionYou can find it again in under two minutes
Read a result as an approvalWrite what the number shows and what else a real decision would need (capacity, bracing, the competent person's judgment)You stop treating a demand calculation as a design check
Too slowNote where the time went, then repeat the method on a fresh problemThe same setup takes noticeably less time

Error log fields: question · your answer · first wrong step · error type · corrected method · where the rule is (document and section) · retry date. A day later, rework the missed question cold, then change one input and solve it again. Use the changed version to check whether you can apply the method beyond the answer you remember.

What this practice test covers

NCEES publishes a question range for each of the 11 knowledge areas (Civil: Construction specifications, pp. 1–3). We gave each area roughly half its range. That allocation is our editorial choice, not an official weighting.

What this practice test covers
#NCEES knowledge areaNCEES questions (of 80)This test (of 40)Question numbers
1Soil Mechanics6–933, 17, 30
2Site Layout and Development5–839, 22, 33
3Material Properties5–8310, 21, 36
4Estimating Quantities and Costs6–944, 15, 26, 37
5Project Planning and Scheduling7–1142, 14, 24, 35
6Material, Production, and Execution Quality Control7–1146, 16, 25, 32
7Structural Mechanics7–1147, 18, 29, 39
8Hydraulics and Hydrology4–6213, 31
9Construction Operations and Methods9–1455, 12, 20, 28, 38
10Design for Support of Construction Loads10–1551, 11, 19, 27, 34
11Health and Safety4–638, 23, 40
Total8040

The set has 25 single-answer questions, 9 numeric-entry questions, 5 select-two questions, and 1 ordering question. Nine of the 40 use SI units, since the exam uses both SI and U.S. customary units. NCEES says the subtopics in its specification are examples, not a complete list, and 40 questions can only sample each area, not cover it.

Is there still a breadth section?

No. Under the specification effective April 2024, all 80 questions come from the 11 Construction knowledge areas. Soils, hydraulics, and structures still show up, written in a construction context, which is why they're in this test. If a book or course describes a breadth morning and a depth afternoon, it was built for the older format. Its problems can still teach methods, but not the exam's structure.

Which references match your test date

Your appointment date decides which design standards NCEES supplies on screen. The knowledge areas and question ranges don't change; only the reference list does, beginning with the April 2027 exam.

Which references match your test date
ReferenceExams before April 2027Exams beginning April 2027
ACI 318Not listed2019 (2022), added
ACI 347R, formwork guide2014, listed on its ownIncluded in the ACI SP-4 appendix
AISC Steel Construction Manual15th edition16th edition
CMWB, masonry wall bracing2012Not listed
MUTCD Part 62009 edition with Revisions 1 and 2 (May 2012)11th edition (2023)
29 CFRJuly 2020: Parts 1903 and 19262024: Parts 1903, 1904, and 1926

ACI SP-4 (8th edition), ASCE 37-14, and PCA EB001 (17th edition) stay the same. Sources: standards for exams before April 2027 and standards for exams beginning April 2027, last page of each.

Every question on this page gives you the loads, properties, and assumptions it needs, so none depends on a value that changes between editions. Where the edition changes how you'd look something up, the explanation says so: MUTCD Part 6 tables moved from 6C to 6B, and the 2020 RCSC bolt specification renames the bolt groups. For the full reference list and a lookup drill, see our PE Civil Construction exam prep guide.

How close is this to the real exam?

How close is this to the real exam?
Row labelNCEES PE Civil: ConstructionThis practice test
Questions8040
Time8 hours of exam time in a 9-hour appointment, which also covers a 2-minute nondisclosure agreement, an 8-minute tutorial, and an optional 50-minute breakUntimed, or 240 minutes at exam pace
StructureTwo sections. After you submit the first, you can't go back to itOne set; revisit anything
Question formatsMultiple choice plus alternative item types: multiple correct, point-and-click, drag-and-drop, and fill-in-the-blankMultiple choice, numeric entry, select two, and ordering; no point-and-click
ReferencesNCEES PE Civil Reference Handbook and the listed standards, on screen onlyWhatever you have; practicing with the handbook is better
UnitsSI and U.S. customarySI and U.S. customary
ScoringCorrect answers converted to a scaled score; pass or fail; no partial credit; unscored pretest questions you can't identifyOne point per question; a percentage
ResultsTypically 7–10 daysSelf-score with the answer key

Sources: NCEES PE Civil exam page; Examinee Guide, pp. 10–12, 14, 16; NCEES computer-based testing.

Practice with the references you'll actually get. Download the current NCEES PE Civil Reference Handbook from MyNCEES and practice finding the relevant formulas in it and the cited provisions in the standards for your test date. On exam day the handbook and standards open in a viewer with its own search box; Ctrl+F doesn't work, and standards open one chapter at a time. You can bring one NCEES-approved calculator, and a TI-30XS is also on screen (Examinee Guide, pp. 8 and 10).

Where to go next

Sources and verification

Exam facts on this page were last verified October 7, 2026, against the NCEES documents below. We re-solved every question against its cited source and recalculated each numeric answer. The questions haven't been statistically tested or reviewed by NCEES or a licensed engineer, and source checking isn't professional engineering review.

NCEES

Regulations and standards used in the questions

Teaching references used in the explanations

These teaching references explain the methods. They aren't references NCEES supplies on the exam.

By Castleport Test Prep Editorial Team. This page was developed with AI-assisted research, drafting, question development, and editing. See how Castleport uses sources and AI assistance and our editorial standards.

Castleport Test Prep is an independent exam prep publisher. It is not affiliated with, endorsed by, or approved by the National Council of Examiners for Engineering and Surveying (NCEES). Exam and credential names are used for identification, and trademarks belong to their respective owners. These practice questions are original and unofficial, and nothing on this page guarantees a passing result or a license.

Free PE Civil Construction Practice Test: 40 Questions + Solutions