Free ARE Project Management Practice Test
Work through 45 original questions in this free ARE 5.0 Project Management (PjM) practice test. Each question has its answer and explanation directly below it; this unofficial set is shorter than NCARB's 75-item division.
Questions 1–37
Question 1
During construction, the owner and architect agree that the corridor flooring must change from vinyl tile to sheet linoleum. The contractor agrees the change is needed but won't accept the owner's proposed price, and the work has to proceed now to hold the schedule. The project uses unmodified AIA A201-2017. What should the architect prepare?
Show answer and explanation, Question 1
Answer: B. A Construction Change Directive
A Construction Change Directive is the tool for directing a change before the price or time adjustment is agreed. The architect prepares it, the owner and architect sign it, and the contractor proceeds while the adjustment is worked out (A201 §7.3.1). A is wrong because a Change Order records agreement among all three parties, so it needs the contractor's signature too (§7.2.1). C fails because a minor change can't adjust the Contract Sum or Contract Time, and this one carries a disputed price. D asks for information; it doesn't authorize changed work.
PjM section 3, Contracts · Objective 3.3 · Source: AIA A201-2017 preview (unmodified text), §7.1.2, §7.2.1, §7.3.1, §7.3.6; AIA summary of G710-2017 (Architect's Supplemental Instructions), Synopsis
Question 2
A project has $18,000 left in its internal labor budget. The project manager must spend 12 hours on the remaining work at an internal cost of $150 per hour. Technical staff cost $90 per hour. These rates already include every cost charged to this budget, and nothing else will be charged to it. What is the maximum number of technical-staff hours the remaining budget can cover?
Show answer and explanation, Question 2
Answer: B. 180 hours
Reserve the project manager's time first: 12 × $150 = $1,800. That leaves $18,000 − $1,800 = $16,200, and $16,200 ÷ $90 = 180 hours. A (160) subtracts the manager's $1,800 twice. C (200) ignores the manager entirely ($18,000 ÷ $90). D (220) adds the manager's cost to the budget instead of subtracting it. These are internal cost rates, so don't add an overhead factor or swap in a billing rate.
PjM section 1, Resource Management · Objective 1.2 · Source: Original calculation (inputs and arithmetic shown above)
Question 3
Your office template lists the newest published edition of a model building code. The project jurisdiction's adoption record, which you've confirmed for this project, adopts an earlier edition with local amendments. What should the team use to set up the project's code review?
Show answer and explanation, Question 3
Answer: D. The jurisdiction's adopted edition and local amendments, recorded in the project code register
A code applies to a project because the jurisdiction adopted it, not because it's the newest. Jurisdictions don't all adopt the same edition, and they amend what they adopt, so the team works from the adopted edition plus amendments and records that decision. A and B substitute a publication date or a template for the governing record. C drops amendments that are part of the adopted requirements.
PjM section 5, Project Quality Control · Objective 5.1 · Source: AIA Best Practices: Research codes now or risk costly delays, pp. 1–2
Question 4
An architect's draft work plan lists three promised issue dates. It doesn't show the consultant inputs or the owner reviews that each issue depends on. Which revision best makes the plan usable for running the project?
Show answer and explanation, Question 4
Answer: D. Tie each milestone to its deliverables, responsible people, dependencies, review activities, and durations
A work plan earns its keep when you can trace each milestone back to the work and decisions that must happen first. D does that. A throws away the intermediate checkpoints that warn you early. B fixes half the problem but still hides owner reviews, which are frequent schedule drivers. C assumes equal effort with no link to tasks or availability.
PjM section 2, Project Work Planning · Objective 2.1 · Source: AIA Best Practices: Plan for success (project management), p. 1; GAO Schedule Assessment Guide (GAO-16-89G), Best Practices 2–3
Question 5
In a B101-2017 agreement, the Supplemental Services table lists a specialist acoustical study and designates the owner as responsible for providing it. Nothing else in the agreement assigns that study to the architect. Must the architect perform the study because it appears in the table?
Show answer and explanation, Question 5
Answer: D. No. The designation controls who provides it, though any separate coordination duties still apply
The Supplemental Services table works by assignment: each listed service is marked as the architect's, the owner's, or not provided. Here the owner provides the study. A and B ignore the assignment. C overreaches: a responsibility designation for one service doesn't erase whatever coordination duties the rest of the agreement creates.
PjM section 3, Contracts · Objective 3.1 · Source: AIA instructions for B101-2017, §4.1.1
Question 6
The owner's budget for the Cost of the Work is $4,800,000. A revised construction estimate, prepared on exactly the same cost basis, is $5,040,000. What overage should the architect report, as a percentage of the budget?
Show answer and explanation, Question 6
Answer: B. $240,000, 5%
The difference is $5,040,000 − $4,800,000 = $240,000, and $240,000 ÷ $4,800,000 = 5%. The budget is the denominator because you're reporting how far over budget the project is. A divides by the estimate. C doubles the difference. D describes the whole estimate as a share of the budget, not the overage. This is a construction-budget comparison, not a fee calculation.
PjM section 4, Project Execution · Objective 4.1 · Source: AIA: What is the architect's obligation to design to budget?
Question 7
The architect approved a curtain-wall shop drawing without noticing that the mullions were drawn deeper than specified. The deeper mullions would block a key sightline the owner approved as a design goal. The contractor's submittal didn't call out the change. Now the contractor says the approval authorizes the deeper mullions. Under unmodified A201-2017, what's the best response?
Show answer and explanation, Question 7
Answer: C. Explain that approval doesn't authorize a deviation the contractor didn't specifically identify, and require Work that conforms to the Contract Documents
Shop drawings aren't Contract Documents; they show how the contractor proposes to meet them. An approval doesn't relieve the contractor of a deviation unless the contractor specifically identified it at submittal and either the architect gave written approval of that specific deviation as a minor change or a Change Order or Construction Change Directive authorized it. The architect can reject nonconforming Work, which protects the approved design goal. A gets the status of shop drawings wrong. B treats a review as a waiver. D is wrong because an order for a minor change cannot adjust the Contract Sum.
PjM section 5, Project Quality Control · Objective 5.4 · Source: AIA A201-2017 preview (unmodified text), §3.12.4 and §3.12.8, p. 16; §4.2.6, p. 18; §7.4, p. 23; AIA summary of G710-2017 (Architect's Supplemental Instructions), Synopsis
Question 8
A signed scope requires a consultant with occupied-museum experience who can give the project at least 20 hours per week during design development. The approved allowance is no more than $3,000 per week for those 20 hours. Each candidate holds the required professional authorization and meets every other condition. Which candidate meets all three conditions?
| Candidate | Occupied-museum experience | Available hours/week | Rate |
|---|---|---|---|
| A | Yes | 12 | $100/hr |
| B | Yes | 24 | $140/hr |
| C | No | 30 | $100/hr |
| D | Yes | 20 | $170/hr |
Show answer and explanation, Question 8
Answer: B. Candidate B
Candidate B has the experience, can provide at least 20 hours, and costs 20 × $140 = $2,800 for the required weekly hours. A can't supply 20 hours. C lacks the required experience. D would cost 20 × $170 = $3,400. Available hours are a ceiling, not an instruction to buy every hour offered, so B's extra 4 hours don't count against the budget.
PjM section 1, Resource Management · Objective 1.1 · Source: GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 3
Question 9
Unmodified B101-2017 applies. The owner and contractor have been discussing a proposed change that affects the architect's design services, without involving the architect. What does the agreement's communication provision call for?
Show answer and explanation, Question 9
Answer: B. Involve the architect in the relevant communications, and tell the architect the substance of what was already discussed
B101-2017 §5.12 requires the architect to be involved in owner communications that affect the architect's services, and if the owner and contractor talk directly, the owner tells the architect the substance. A blocks the required involvement. C goes too far: the agreement permits other direct owner–contractor communications with notice of their substance; communications affecting the architect's services or professional responsibilities require the architect's direct involvement.
PjM section 2, Project Work Planning · Objective 2.3 · Source: AIA summary of B101-2017, §5.12
Question 10
During construction, the owner asks to move a light switch two feet to clear a planned bookcase. The contractor confirms there's no effect on cost or time, and the change fits the design intent. Under A201-2017, what is the simplest proper way to make this change?
Show answer and explanation, Question 10
Answer: C. A written order for a minor change in the Work, issued by the architect
The architect alone can order a minor change that doesn't adjust the Contract Sum or Contract Time and is consistent with the design intent; AIA's G710 form exists for exactly this. A records agreement among all three parties; B is used when the terms of a Change Order aren't fully agreed. Neither is needed for this minor, no-adjustment change. D bypasses the contract's change process and goes around the contractor to a subcontractor.
PjM section 3, Contracts · Objective 3.3 · Source: AIA A201-2017 preview (unmodified text), §7.1.2, §7.2.1, §7.3.2, §7.4; AIA summary of G710-2017 (Architect's Supplemental Instructions), Synopsis
Question 11
The owner asks for a scope expansion. The agreement requires the owner's approval of the additional-service proposal before the architect proceeds with this expansion. You estimate 40 architecture hours billed at $145 per hour and 12 consultant hours billed at $175 per hour. The proposal has no markup, reimbursables, or other charges. What additional fee do you propose?
Show answer and explanation, Question 11
Answer: D. $7,900
Architecture: 40 × $145 = $5,800. Consultant: 12 × $175 = $2,100. Total: $7,900. A leaves out the consultant. B bills all 52 hours at $145. C bills all 52 hours at $175. Note what the number is: a proposed fee. It doesn't authorize anything until the owner approves it under the agreement's process.
PjM section 4, Project Execution · Objective 4.2 · Source: AIA Best Practices: Managing design project costs, pp. 1–2
Question 12
Your firm's review plan calls for an experienced, qualified reviewer who did not prepare the documents. All of these people are available. Who fits?
Show answer and explanation, Question 12
Answer: B. An experienced architect from another project team who meets the review's technical qualifications
The plan sets two conditions: competence and independence from the documents. B meets both. A reviewer from inside the firm can still be independent of the project. A fails independence; people close to a project miss things a fresh reviewer catches. C fails competence. D doesn't provide a qualified reviewer at all.
PjM section 5, Project Quality Control · Objective 5.2 · Source: AIA Best Practices: Using document audits/peer reviews, pp. 1, 3
Question 13
Your firm defines utilization as billable hours divided by total paid hours. An employee was paid for 2,080 hours last year and billed 1,560 of them to projects. What is the employee's utilization rate?
Show answer and explanation, Question 13
Answer: B. 75%
1,560 ÷ 2,080 = 0.75, or 75%. A (25%) is the non-billable share, 520 ÷ 2,080. D (133%) flips the ratio. C assumes every paid hour counts as billable. Utilization matters for resource planning because non-billable hours (administration, marketing, leave) still have to be paid for.
PjM section 1, Resource Management · Objective 1.2 · Source: Original calculation (inputs and arithmetic shown above)
Question 14
The owner asks for a service outside the architect's agreed scope. Both parties agree it falls under B101-2017 §4.2.1. It isn't a §4.2.2 service needed to avoid delay in construction, and the owner hasn't authorized it in writing. What should the architect do before starting?
Show answer and explanation, Question 14
Answer: A. Describe the service and the proposed fee and schedule adjustment, and get the owner's written authorization
Services under §4.2.1 need the owner's written authorization before the architect proceeds; AIA's G801 notice form is built around that step. B and C replace the required authorization with an invoice or a request. Notice the condition in the stem: §4.2.2 is a separate pathway for services needed to avoid construction delay, which is why "every additional service always needs prior written authorization" is too broad.
PjM section 3, Contracts · Objective 3.1 · Source: AIA instructions for G801-2017 (Notice of Additional Services), Completing G801–2017
Question 15
The design team has estimated its own production time, but the schedule leaves out a required local review board's submission deadline, meeting dates, and review period. The owner wants you to confirm a permit milestone. What should you do first?
Show answer and explanation, Question 15
Answer: A. Get the board's actual submission and meeting requirements and build those dependencies into the schedule
Agency calendars often control what's achievable. Planning and zoning boards have meeting schedules and advance submission deadlines, so you map their actual dates to your design phases before promising anything. B and C invent timing the facts don't give you.
PjM section 2, Project Work Planning · Objective 2.2 · Source: AIA Best Practices: Research codes now or risk costly delays, pp. 2, 4
Question 16
On a design-bid-build project, the stated procurement procedure requires numbered addenda to all bidders for any change before bids are due. An approved, coordinated change affects one plan sheet and its matching specification section. What should the architect do?
Show answer and explanation, Question 16
Answer: C. Issue both coordinated revisions in a numbered addendum to all bidders
C follows the stated procedure and keeps every bidder pricing the same documents. A gives one bidder information the others don't have. B leaves conflicting documents in circulation. D guarantees that bids won't reflect the change.
PjM section 4, Project Execution · Objective 4.3 · Source: AIA: Quality control in the preparation of working drawings, Drawing preparation checklist
Question 17
Before issuing documents, you find that a mechanical unit's footprint overlaps a structural beam. The project has no rule that gives either discipline's drawings precedence. Which quality-control action fits?
Show answer and explanation, Question 17
Answer: C. Bring the affected disciplines together, resolve the conflict, and check the revised documents together before release
The job here is to resolve the interface and verify the fix, not to engineer a solution yourself. Coordination among architectural, structural, and MEP documents is a standard review criterion. A invents a precedence rule. B pushes an unresolved conflict into the field, where it can return as an RFI requiring more effort to resolve. D changes metadata only.
PjM section 5, Project Quality Control · Objective 5.3 · Source: AIA Best Practices: Using document audits/peer reviews, pp. 3–4; AIA: Quality control in the preparation of working drawings, Drawing preparation checklist
Question 18
Under unmodified AIA A201-2017, which three are part of the architect's role during construction?
Show answer and explanation, Question 18
Answer: A, C, E.
A, C, and E come straight from A201 §4.2.2, §4.2.6, and §4.2.8. B and D belong to the contractor, who is solely responsible for means, methods, sequences, and jobsite safety (§3.3.1; §10.1). F is expressly excluded: the architect isn't required to make exhaustive or continuous inspections (§4.2.2).
PjM section 3, Contracts · Objective 3.3 · Source: AIA A201-2017 preview (unmodified text), §3.3.1, §4.2.2, §4.2.6, §4.2.8, §10.1
Question 19
The design development phase has a labor budget of $60,000. The team has spent $36,000, and the project manager estimates the phase is 45% complete. If the remaining work costs the same per percent of progress as the work so far, what is the projected total labor cost at completion, including the $36,000 already spent?
Show answer and explanation, Question 19
Answer: C. $80,000, which is $20,000 over budget
So far, $36,000 bought 45% of the work, so the phase is tracking at $36,000 ÷ 0.45 = $80,000, which is $20,000 over the $60,000 budget. A confuses percent spent with percent complete. B assumes the remaining 55% will cost what the budget allotted ($36,000 + 0.55 × $60,000), which ignores the overrun already happening. D is what's left to spend, not a projection. Catch this early and you can re-plan staffing or talk to the owner about scope before the fee is gone.
PjM section 1, Resource Management · Objective 1.2 · Source: Original calculation (inputs and arithmetic shown above)
Question 20
Before signing a C401-2017 agreement with a consultant, the architect notices that the consultant's proposed delivery dates conflict with obligations in the existing owner–architect agreement. What's the best action?
Show answer and explanation, Question 20
Answer: B. Review the prime agreement it incorporates and reconcile the consultant's scope and dates before committing
C401-2017 incorporates the owner–architect agreement (the Prime Agreement) by reference and flows its relevant provisions down to the consultant, so the architect checks the actual requirements and fixes the mismatch before signing. A leaves the architect's promise to the owner unmet. C and D assume transfers the agreements don't make.
PjM section 3, Contracts · Objective 3.2 · Source: AIA summary of C401-2017, Synopsis; Related documents
Question 21
A new retail store, a public accommodation under ADA Title III, has received its building permit, passed inspections, and gotten a certificate of occupancy. The owner says the city's approval proves the store complies with the ADA. What's the accurate response?
Show answer and explanation, Question 21
Answer: B. Not necessarily. Local permits and inspections don't ensure ADA compliance; the design must meet the applicable ADA Standards on its own terms
The ADA Standards are civil-rights design requirements, not a building code. There is no ADA plan review or permit, building departments aren't required or authorized by the ADA to enforce them, and the U.S. Access Board says a local occupancy permit or inspection doesn't ensure ADA compliance. Enforcement comes through federal complaints and litigation. A and D describe review processes that don't exist for the ADA. C is wrong because a local code doesn't displace a federal civil-rights law.
PjM section 5, Project Quality Control · Objective 5.1 · Source: U.S. Access Board: Using the ADA Standards, “How the ADA Standards are Enforced” and “State and Local Access Codes”
Question 22
The project's approval matrix requires both zoning clearance and fire-authority approval before the permit package is complete. Zoning clearance came in. The fire authority asked for a revised plan, which hasn't been submitted. What should the project manager record?
Show answer and explanation, Question 22
Answer: A. The package is still incomplete; the fire response and approval are outstanding and being tracked
The matrix lists two separate requirements, so one approval can't stand in for the other. A keeps the open item visible. B and C treat one agency's approval as satisfying another agency's requirement.
PjM section 4, Project Execution · Objective 4.4 · Source: AIA Best Practices: Research codes now or risk costly delays, pp. 1–2
Question 23
Three equally qualified team members can each give the project 32 net hours per week for four weeks. Those hours already exclude meetings, leave, and other assignments. The remaining work needs 420 hours. What does the staffing plan show?
Show answer and explanation, Question 23
Answer: C. A shortfall of 36 hours
Capacity is 3 × 32 × 4 = 384 hours, and 420 − 384 = a 36-hour shortfall. A reverses the result. B assumes 40-hour availability the facts rule out. D (96) is one week of team capacity, not the gap between demand and capacity.
PjM section 1, Resource Management · Objective 1.2 · Source: GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 3
Question 24
Unmodified B101-2017 applies. The lowest bona fide bid exceeds the owner's budget for the Cost of the Work. The owner chooses to have the documents modified to bring the project within budget. The parties agree the overrun was caused by market conditions the architect could not reasonably have anticipated. How does §6.7 treat the architect's redesign?
Show answer and explanation, Question 24
Answer: C. It's compensated as an Additional Service
The general rule in B101-2017 is redesign without added compensation, but the 2017 edition carves out an exception: when the overrun comes from market conditions the architect couldn't reasonably anticipate, redesign is paid as an Additional Service. The stem establishes that finding, so C applies. A states the general rule without the exception. B and D invent consequences.
PjM section 3, Contracts · Objective 3.1 · Source: AIA summary of B101-2017, §6.7; AIA: What is the architect's obligation to design to budget?
Question 25
During construction, the contractor emails the architect's structural engineer directly, asking to change a steel connection detail. The project uses unmodified A201-2017. How should this be handled?
Show answer and explanation, Question 25
Answer: D. The request comes through the architect, who coordinates the engineer's response
Under A201 §4.2.4, the architect's consultants communicate through the architect, unless the documents say otherwise. That keeps one record of what was asked and decided and keeps the architect in the loop. A and B bypass the architect. C sends a technical question to someone who isn't positioned to answer it.
PjM section 2, Project Work Planning · Objective 2.3 · Source: AIA A201-2017 preview (unmodified text), §4.2.4
Question 26
Which three are warning signs of scope creep that should trigger a change review?
Show answer and explanation, Question 26
Answer: A, C, E.
Scope creep is work that drifts beyond the agreed services without anyone deciding it should. A, C, and E are classic examples, and each calls for documenting the request and its fee and schedule effect, then getting authorization under the agreement's process. B, D, and F are work the agreement and work plan already cover.
PjM section 4, Project Execution · Objective 4.2 · Source: AIA Best Practices: Managing design project costs, pp. 1–2; AIA instructions for G801-2017 (Notice of Additional Services), Completing G801–2017
Question 27
At a phase review, every required sheet exists, but nobody has checked the evolving design against the owner's approved program and performance goals. What should be added to the review?
Show answer and explanation, Question 27
Answer: A. Compare the current design with the approved goals, record any deviations, and assign decisions or corrections
Completeness and compliance are different checks. A design-phase review should test programmatic and performance compliance, not just whether the sheets exist. A adds that comparison and the follow-up. B checks completeness only. C measures spending, not design. D waits until fixes are far more expensive.
PjM section 5, Project Quality Control · Objective 5.4 · Source: AIA Best Practices: Using document audits/peer reviews, p. 3, “Peer review criteria”; AIA Best Practices: Plan for success (project management), p. 1
Question 28
The specifications give a specific temporary shoring sequence. Before starting, the contractor concludes that the specified sequence may not be safe. Under unmodified A201-2017, what should happen?
Show answer and explanation, Question 28
Answer: C. The contractor gives timely written notice to the owner and architect and proposes an alternative, which the architect evaluates only for conformance with the design intent
A201 §3.3.1 makes the contractor solely responsible for means, methods, sequences, and jobsite safety. When the documents specify a method the contractor believes may be unsafe, the contractor must give timely written notice to the owner and architect and propose an alternative, and the architect evaluates that alternative solely for design intent. The contractor uses the proposed alternative if the architect does not object. A ignores the contractor's duty. B moves safety onto the architect, which the contract avoids. D puts the owner in charge of construction methods.
PjM section 3, Contracts · Objective 3.3 · Source: AIA A201-2017 preview (unmodified text), §1.6.1, p. 10; §3.3.1, p. 13
Question 29
You're assembling the team for a mid-size outpatient clinic. Which three are sound criteria for choosing team members?
Show answer and explanation, Question 29
Answer: A, C, E.
Team assembly starts from what the project needs: the right skills, people who are actually available when the work happens, and the credentials required to take responsibility for it. Scheduling guidance makes the same point: assign resources by the skills and availability the work requires. B, D, and F can matter at the margin, but on their own they don't show that the team can deliver.
PjM section 1, Resource Management · Objective 1.1 · Source: GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 3
Question 30
A coordination meeting assigns Lee to get a consultant's equipment dimensions by Friday. The dimensions are still unknown, so the affected layout can't be approved yet. On this project, meeting minutes don't authorize contract changes. Which minutes entry is most useful?
Show answer and explanation, Question 30
Answer: C. "Equipment dimensions open; Lee to obtain by Friday; layout approval pending until received"
Good minutes record status, who owns the next step, the deadline, and what's waiting on it. C does all four. A records an approval that didn't happen. B gives nobody anything to follow up on. D contradicts the project's stated rule about what minutes can authorize.
PjM section 2, Project Work Planning · Objective 2.3 · Source: AIA Community Hub: Documenting construction meeting minutes, Yu-Ngok Lo, AIA; discussion of decisions, follow-up, actions, responsible parties, and due dates
Question 31
At the end of design development, the architect's cost estimate exceeds the owner's budget for the Cost of the Work by 6%. Unmodified B101-2017 applies. What should the architect do before starting construction documents?
Show answer and explanation, Question 31
Answer: A. Notify the owner and recommend adjustments to the project's size, quality, or budget for the owner's decision
AIA's design-to-budget guidance calls for updated estimates, notice of budget variances, and the owner's approval before moving to the next phase. Doing this at the end of design development is far cheaper than redesigning after bids. C postpones a known problem. B makes the owner's decision for them. D increases the estimate instead of closing the gap.
PjM section 4, Project Execution · Objective 4.1 · Source: AIA: What is the architect's obligation to design to budget?, How B101 approaches budget; §6.3 discussion
Question 32
Your firm is setting up a design-development peer review. Which three belong among the review's criteria?
Show answer and explanation, Question 32
Answer: A, C, E.
AIA's peer-review guidance lists compliance, completeness, coordination, and technical detailing as design-phase review criteria. B is wrong: a peer review doesn't shift responsibility away from the project team or management. D is a sliver of completeness, not a review. F is project accounting, not document quality.
PjM section 5, Project Quality Control · Objective 5.2 · Source: AIA Best Practices: Using document audits/peer reviews, pp. 3–4, “Peer review criteria” and “Peer review audit follow-up”
Question 33
The owner hired its own geotechnical consultant. The signed terms make the architect responsible for folding the consultant's report into the design work plan, and only the owner can change that consultant's scope. The report is due after the scheduled foundation-design review. Which response fits those terms?
Show answer and explanation, Question 33
Answer: A. Show the report as a dependency, coordinate the design milestone, and go through the owner for any change to the consultant's scope
A honors both supplied terms: integrating the report is your planning job, and changing the consultant's contract is the owner's call. B contradicts who holds that contract. C drops the coordination you agreed to. D adds a service nobody asked for.
PjM section 3, Contracts · Objective 3.4 · Source: AIA Best Practices: Managing design project costs, pp. 1–2
Question 34
The baseline schedule allowed two weeks for the owner to approve schematic design. The owner took five. Design development work depends on that approval. What's the best schedule action?
Show answer and explanation, Question 34
Answer: A. Update the schedule with the actual approval date and logic, show the effect on later milestones, and tell the owner in writing
A schedule is only useful if it reflects what actually happened. Updating with actual dates and logic shows the true effect on later milestones, and putting it in writing gives the owner a chance to decide. C hides the problem. B risks rework on unapproved design. D erases a real dependency.
PjM section 2, Project Work Planning · Objective 2.2 · Source: GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 9; AIA Best Practices: Plan for success (project management), p. 1
Question 35
A preliminary zoning check shows a planned addition exceeds the lot coverage the local zoning code allows. The city tells you relief requires a variance from its zoning board, which meets monthly and wants submissions four weeks before each meeting. What's the best next step?
Show answer and explanation, Question 35
Answer: D. Explain the risk, cost, and schedule effect to the owner; prepare the variance request and a compliant fallback design the owner agrees to; and add the board's dates to the schedule
Zoning relief comes from the body the city names, here the zoning board, on its calendar. You keep the owner informed of the risk and cost, walk in with an agreed backup plan, and map the board's deadlines into the schedule. A and C send the question to building-code reviewers who don't grant zoning variances in this scenario. B bets construction documents on an approval you don't have.
PjM section 4, Project Execution · Objective 4.4 · Source: AIA Best Practices: Research codes now or risk costly delays, pp. 2–4, “Coordination,” “Completion and approval,” and the project checklist
Question 36
A work plan schedules the first qualified peer review after the final documents are issued, with no earlier review. Which change best addresses the quality risk?
Show answer and explanation, Question 36
Answer: D. Schedule qualified reviews during design, with time to evaluate and fix what they find before release
Reviews pay off when their findings can still change the documents. AIA's peer-review guidance recommends reviews at schematic design, design development, and around 75% or 90% construction documents, with issues addressed early in the next phase. A and B throw away that chance. C promises something no review can deliver.
PjM section 5, Project Quality Control · Objective 5.2 · Source: AIA Best Practices: Using document audits/peer reviews, p. 2, “An audit program”
Question 37
The lowest bona fide bid exceeds the owner's construction budget. For this question, a fictional owner–architect agreement gives the owner three responses: increase the budget; authorize rebidding or renegotiation; or work with the architect to revise scope and quality. The architect does not guarantee bid prices. Which of these is not an option granted by those stated terms?
Show answer and explanation, Question 37
Answer: D. Require the architect to pay the difference between the bid and the budget
The stated agreement gives the owner the options in A, B, and C. It doesn't require the architect to fund the difference between the bid and the budget. D adds a payment obligation the supplied terms don't contain. This question tests the stated budget remedies, not liability under other contract terms or law.
PjM section 3, Contracts · Objective 3.1 · Source: Original fictional agreement terms stated in the question
Case study A: Cedar Office Addition
Questions 38–41 use the two resources below. Each question stands on its own; your answer to one doesn't change the facts in the next.
Exhibit A1: Work-plan schedule
Durations are working days, starting at day 0. All activities use one calendar and finish-to-start links. Parallel activities have enough qualified people. There are no holidays, lags, imposed dates, or other resource limits. An activity with two predecessors waits for both.
| Activity | Work | Duration | Predecessor |
|---|---|---|---|
| A | Owner confirms program | 4 days | None |
| B | Architectural layout | 6 days | A |
| C | Consultant engineering input | 8 days | B |
| D | Construction cost review | 5 days | B |
| E | Interdisciplinary coordination | 3 days | C and D |
| F | Owner review | 2 days | E |
The completion milestone is when F finishes. Total float means how long an activity can slip without delaying that milestone.
Exhibit A2: Scope and change record
The signed services cover design and coordination for the agreed office addition. Marketing renderings are expressly excluded. Additional owner-requested services need written authorization stating the added scope and the agreed fee and schedule adjustments before the work starts. No emergency or construction-delay exception applies.
- Request R1: The owner has asked for marketing renderings but hasn't authorized their scope, fee, or schedule.
- Request R2: The owner is considering an extra office suite. It changes the approved program and may affect design effort, construction cost, and the work plan. Its impacts haven't been assessed or approved.
Question 38
Using Exhibit A1, which three statements are correct?
Show answer and explanation, Question 38
Answer: A, C, D.
Forward pass: A ends day 4; B ends day 10; C ends day 18; D ends day 15. E waits for the later of C and D, so it runs days 18–21, and F ends on day 23. The critical path is A–B–C–E–F. D finishes 3 days before E can start, so it has 3 days of float and isn't critical. E is false because F depends on E. F (28) adds parallel work as if it were sequential.
PjM section 2, Project Work Planning · Objective 2.1 · Source: GAO Schedule Assessment Guide (GAO-16-89G), Best Practices 2, 6, 7
Question 39
Each option is a separate change to the original Exhibit A1 baseline. Don't combine them. Which two give the correct revised completion duration?
Show answer and explanation, Question 39
Answer: A, D.
A: C is critical, so 4 days on C adds 4 days: 27. D: D now ends on day 20, later than C's day 18, so E runs 20–23 and F ends on 25. B is wrong: 2 days uses up 2 of D's 3 float days, so the finish stays at 23. C is wrong: B is critical, so the finish moves to 24. E gives 22, not 21. F gives 25, not 24. At a merge point, recompute which predecessor finishes last instead of adding every delay to the end date.
PjM section 2, Project Work Planning · Objective 2.2 · Source: GAO Schedule Assessment Guide (GAO-16-89G), Best Practices 6–7
Question 40
For Request R1 in Exhibit A2, which two things should happen before the architect starts on the renderings?
Show answer and explanation, Question 40
Answer: D, F.
D defines the change; F meets the stated condition for starting. A and E skip that condition. B contradicts the express exclusion of marketing renderings. C changes the wrong contract; the renderings are a professional service under the owner–architect agreement.
PjM section 3, Contracts · Objective 3.1 · Source: AIA instructions for G801-2017 (Notice of Additional Services), Completing G801–2017
Question 41
For Request R2 in Exhibit A2, which three belong in the project manager's change-impact assessment?
Show answer and explanation, Question 41
Answer: A, C, E.
An added suite can change design effort, construction cost, and timing, so the assessment covers all three before the owner decides. B invents an approval. D treats billing as a measure of progress. F reaches a conclusion before doing the analysis.
PjM section 4, Project Execution · Objective 4.2 · Source: AIA Best Practices: Managing design project costs, pp. 1–2; AIA: What is the architect's obligation to design to budget?
Case study B: Linden Civic Annex
Questions 42–45 use the two resources below. All four questions draw on the same records. RP-3's approval doesn't mean the separate QC-17 issue is resolved.
Exhibit B1: Agreements and document protocol
| Record | Project condition |
|---|---|
| Delivery and participants | Design-bid-build. The owner retains the architect. The architect retains the structural and MEP consultants under C401-2017 agreements. A contractor is under contract. |
| Model permission | Consultant models may be used for project coordination only. Any new reliance use, including fabrication, requires the relevant parties to agree in writing on the permitted use and responsibilities first. |
| Draft status | Coordination uploads are drafts. Uploading or renaming a file doesn't make it a formal issue. |
| Formal release | After required approval, the architect's document controller updates the issue manifest, distributes the coordinated package to affected participants through the agreed channel, and marks earlier issues superseded while preserving the archive. |
| Design objective DO-1 | The owner-approved meeting-hall program requires a column-free room. Changing that objective requires a recorded owner decision and updates to the controlled program and documents. |
Exhibit B2: Release and review records
| Record | Current evidence |
|---|---|
| RP-3: office-wing revision package | All required reviews are complete. Revision 03 is approved for formal release and replaces revision 02. Affected recipients: owner, architect, structural and MEP consultants, contractor. |
| QC-17: meeting-hall coordination issue | A structural beam and a duct conflict on sheets S301 rev. 02 and M301 rev. 02. The issue log says closed, but no revised discipline information or documented coordination review has been provided. These sheets aren't part of RP-3. |
| Proposed response to QC-17 | One proposed fix adds a column inside the meeting hall. No owner decision approving a departure from DO-1 is recorded. No alternative has been selected. |
Question 42
A participant wants to use a consultant's coordination model for fabrication. Which two actions follow Exhibit B1?
Show answer and explanation, Question 42
Answer: B, E.
Exhibit B1 permits coordination use only and requires written agreement before any new reliance use. B identifies the boundary and E follows the required process. This mirrors C401-2017 §1.10.1, which requires protocols for using and relying on building information models. A confuses a software license with project permission. C, D, and F assume transfers or permissions the exhibit doesn't grant.
PjM section 3, Contracts · Objective 3.2 · Source: AIA summary of C401-2017, §§1.10–1.10.1
Question 43
Which three actions carry out the agreed release procedure for package RP-3?
Show answer and explanation, Question 43
Answer: A, C, E.
Each correct answer is one step of the protocol in Exhibit B1: identify the revision (A), distribute it (C), and control the superseded record (E). B skips the formal process. D violates the archive requirement. F neither controls content nor confirms distribution.
PjM section 4, Project Execution · Objective 4.3 · Source: AIA: Quality control in the preparation of working drawings, Drawing preparation checklist
Question 44
For issue QC-17, which two missing pieces of evidence are needed to support the "closed" status?
Show answer and explanation, Question 44
Answer: C, F.
C supplies the fix and F verifies it. Confirming that responses actually made it into the documents is part of good review follow-up. A is a label, not evidence. B is a schedule preference. D concerns a different package. E changes a name only.
PjM section 5, Project Quality Control · Objective 5.3 · Source: AIA Best Practices: Using document audits/peer reviews, p. 4; AIA: Quality control in the preparation of working drawings, Drawing preparation checklist
Question 45
Which three management actions address the proposed column for QC-17?
Show answer and explanation, Question 45
Answer: B, D, F.
B names the goal at risk, D gives the owner real options, and F carries the decision into the controlled record. A hides a material departure from an approved goal. C substitutes someone else's preference for the owner's decision. E ignores the governing record. The question tests the management process, not a structural solution.
PjM section 5, Project Quality Control · Objective 5.4 · Source: AIA Best Practices: Plan for success (project management), p. 1
Score your set and choose what to review
Count your correct answers out of 45. For the twelve "Select TWO" or "Select THREE" questions, give yourself the point only if you chose exactly the right options. That matches NCARB's rule: every item is worth one point, with no partial credit.
| PjM section | Questions in this set | Count | Share of set | NCARB's published range |
|---|---|---|---|---|
| Resource Management | 2, 8, 13, 19, 23, 29 | 6 | 13.3% | 7–13% |
| Project Work Planning | 4, 9, 15, 25, 30, 34, 38, 39 | 8 | 17.8% | 17–23% |
| Contracts | 1, 5, 10, 14, 18, 20, 24, 28, 33, 37, 40, 42 | 12 | 26.7% | 25–31% |
| Project Execution | 6, 11, 16, 22, 26, 31, 35, 41, 43 | 9 | 20.0% | 17–23% |
| Project Quality Control | 3, 7, 12, 17, 21, 27, 32, 36, 44, 45 | 10 | 22.2% | 19–25% |
| Total | 45 | 100% |
This original set samples all five PjM sections. Its section allocation is an editorial choice, not an official exam form; Resource Management is slightly above NCARB's published range, and the displayed shares are rounded to one decimal place. Your score describes how you did on these 45 questions. It isn't a scaled ARE score, and it hasn't been validated to predict whether you'll pass. With only 6 to 12 questions per section, read section results as a pointer to what to study, not a precise measure.
Turn each miss into a next step
| If your miss involved… | Do this next |
|---|---|
| Who is responsible for what (owner, architect, contractor, consultant) | Sketch the parties and who hired whom. Then find the provision or stated term that assigns that specific duty. |
| Scope versus authorization | Separate three things: the request, its fee and schedule impact, and the approval that lets work start. |
| Fee, staffing, or utilization math | Write units on every number. Check whether each rate is an internal cost or a billing rate, and recalculate from what the question says is included. |
| Construction budget | Compare estimate and budget on the same basis, and use the budget as the denominator for any percentage. |
| Schedule logic | Mark predecessors before adding durations. At a merge, the later predecessor controls. Test each change separately. |
| Change instruments (Change Order, Construction Change Directive, minor change) | Ask two questions: does it change the Contract Sum or Time, and has the contractor agreed? |
| Approvals and agencies | Name the authority, its calendar, and the record that shows the approval is complete. |
| Coordination or design objectives | Name the document or goal at risk, the disciplines involved, and the evidence that will show the issue is truly resolved. |
| "Select TWO/THREE" questions | Check the required count, then justify each choice on its own. A reasonable action that the question's facts don't call for is still wrong. |
A simple error log helps: question number, your answer, the correct answer, the rule or fact you missed, and what you'll check first next time.
Take NCARB's free full-length PjM practice exam next
NCARB offers free, full-length practice exams for every ARE 5.0 division, including Project Management. They run in NCARB's own testing interface, so they're the closest thing to the real item formats, including hotspot questions, which this page can't reproduce.
- With active ARE eligibilities: log in to your NCARB Record, open the Exams tab, and go to Additional Resources to reach the Practice Exam Dashboard.
- Without active eligibilities: log in to your NCARB Record and choose Practice the ARE.
- Two modes: test mode mirrors many conditions of a real appointment; practice mode lets you explore the tools and shows correct responses with rationales. Both end with a results page that breaks down your percentage by section.
- Supervisors and mentors can get PDF versions with every item and explanation, but the PDFs leave out the case-study resources, so candidates get the complete experience through their NCARB Record.
NCARB says its practice exams use a static cut score of about 68%. That figure belongs to the practice exams. The real PjM cut score varies by exam form; NCARB publishes a range of 59–71% of scored items. Neither figure is a passing target for this Castleport set. NCARB updated the practice exams in February 2026 to reflect the April 2026 changes. (NCARB: Free ARE 5.0 Practice Exams; NCARB: updated practice exams)
The PjM division at a glance
This is NCARB's architecture licensing exam, not the PMP. U.S. jurisdictional boards grant architectural licenses; passing PjM alone does not confer licensure (Guidelines, pp. 5, 9).
| Item | Current rule |
|---|---|
| Length and time | 75 items; 3 hours of testing; 30 minutes of optional break time; 3 hours 40 minutes total appointment, including 10 minutes of intro and exit screens (Guidelines, p. 8) |
| Where you test | PSI test centers or PSI online proctoring. Schedule at least 48 hours ahead for a test center or 24 hours ahead for online (Guidelines, p. 11) |
| Item types | Multiple choice (3 or 4 options, choose one); check-all-that-apply (6 options, select the stated 2–4 correct answers); hotspot (click an area of an image) (NCARB: ARE 5.0 format) |
| Case studies | Up to seven cases and up to 16 case-study items, included in the 75-item total (Guidelines, p. 78). Each case has one or two resources and independent items. Case-study items come after the discrete items, but you can answer in any order (NCARB: ARE 5.0 format) |
| Sections | Resource Management 7–13%; Project Work Planning 17–23%; Contracts 25–31%; Project Execution 17–23%; Project Quality Control 19–25% (NCARB PjM page) |
| Scoring | Pass/fail against a cut score for the whole division, not section by section. One point per item, no partial credit, no penalty for wrong answers, so answer everything. PjM has 68 scored items and seven unscored pretest items you can't identify (Guidelines, pp. 37–40, 78) |
| Results | Provisional feedback at the end of the exam; official score report in your NCARB Record within 7–10 calendar days (Guidelines, p. 37) |
| Fee | $263 per attempt; retakes also cost $263 (NCARB fees) |
| Retakes | 60 days after a failed attempt; no more than three attempts of the same division in any 12 months (Guidelines, p. 41) |
| Pass rate | 63% in 2025, counting all first-time and repeat attempts; 60% in 2024 (NCARB pass rates) |
What changed on April 27, 2026
NCARB adjusted 12 of the 91 ARE objectives. In PjM, objectives 4.1 (budget compliance during design and documentation), 4.3 (documentation procedures for a delivery method), and 5.3 (quality control for coordination and constructability) were clarified; 5.2 and 5.4 were updated for alignment with descriptions that stayed the same. Case studies now use one or two resources each, down from three to six, and have fewer items per case. The number of items and the testing time didn't change, and divisions you'd already passed aren't affected. (NCARB, Jan. 22, 2026; NCARB, Apr. 27, 2026)
One rule that should shape your pacing
When you take a break, every item you've already viewed locks, including items you marked for review. Finish and review a block of questions before you step away (Guidelines, pp. 22, 33).
How this set compares with the real exam
| Row label | This practice set | Real PjM division |
|---|---|---|
| Questions | 45, all original | 75: 68 scored and seven unscored pretest items |
| Formats | 33 single-answer and 12 multiple-response | Multiple choice, check-all-that-apply, and hotspot |
| Case studies | 2 cases, 4 questions each, 2 resources each | Up to 7 cases and up to 16 case-study items; 1–2 resources per case |
| Timing | Untimed; at the real exam's average pace (3 hours ÷ 75 items = 2.4 minutes each), a matching allowance for 45 questions is 108 minutes | 3 hours of testing |
| Scoring | Your count of correct answers | Pass/fail against the form-specific cut score |
The questions follow NCARB's published PjM objectives and AIA's 2017 contract documents (B101, A201, C401), which NCARB lists among its PjM references (Guidelines, pp. 81, 116). We had no access to live exam content, and you shouldn't want it: NCARB's Candidate Agreement prohibits seeking or sharing actual ARE questions (Guidelines, pp. 43–45).
Sources
Exam rules and format: NCARB ARE 5.0 Guidelines (effective Oct. 1, 2026) · NCARB: ARE Project Management · NCARB: ARE 5.0 format · NCARB: free practice exams · NCARB fees · NCARB pass rates · NCARB cut-score explanation · NCARB: April 2026 objective changes · NCARB: changes implemented
Contract documents: AIA A201-2017 preview · AIA B101-2017 summary · AIA B101-2017 instructions · AIA C401-2017 summary · AIA G801-2017 instructions · AIA G710-2017 summary · AIA: the obligation to design to budget
Practice guidance: AIA Best Practices: Plan for success · Managing design project costs · Using document audits/peer reviews · Research codes now or risk costly delays · AIA: Quality control in working drawings · AIA Community Hub: Documenting construction meeting minutes · GAO Schedule Assessment Guide · U.S. Access Board: Using the ADA Standards
The project scenarios are fictional study exercises. AI tools assisted in developing and checking this resource; Castleport Test Prep remains responsible for the content.
Last verified: October 12, 2026, for NCARB's division format, objectives, practice-exam access, fees, pass rates, and the AIA contract provisions cited in the explanations.
By the Castleport Test Prep Editorial Team. See how we source practice material, or report a question or source error and include the question number.
Castleport Test Prep is an independent exam prep publisher. We are not affiliated with, endorsed by, or approved by the National Council of Architectural Registration Boards (NCARB) or the American Institute of Architects (AIA). These questions are original and unofficial and don't reproduce NCARB exam questions. Exam, credential, and document names are used to identify their subjects; trademarks belong to their respective owners. Practice results don't guarantee an exam result or licensure.