| Section | Share of exam items | What you need to be able to do | Practice questions |
|---|---|---|---|
| Environmental Conditions & Context | 10–16% | Site a building from site analysis, pick sustainable strategies, respond to neighbors and context | PPD-01 to 06 |
| Codes & Regulations | 16–22% | Apply zoning, accessibility, and building codes, and reconcile them when several apply at once | PPD-07 to 12 |
| Building Systems, Materials, & Assemblies | 19–25% | Choose structural, MEP, envelope, acoustic, and other special systems that fit the program and budget | PPD-13 to 21 |
| Project Integration of Program & Systems | 32–38% | Make the plan, section, systems, site, and program work together in one building | PPD-22 to 32 |
| Project Costs & Budgeting | 8–14% | Evaluate design alternatives, cost estimates prepared by others, and long-term cost | PPD-33 to 38 |
Shares are NCARB's ranges for a typical exam form (NCARB PPD page).
Free PPD practice set (38 questions)
These are original, unofficial questions written to NCARB's published PPD objectives. They are not real ARE questions or a full-length exam. As on the real exam, a multiple-choice item has one best answer, and a check-all-that-apply item tells you how many to choose and gives credit only for the exact set.
Environmental Conditions & Context (6 questions)
PPD-01 · Objective 1.2 · Multiple choice
A community center in Ohio will rely on passive solar heating in its multipurpose room. Which orientation for the room's main glazing best supports winter solar gain?
Show answer and explanation, PPD-01
Answer: A. In the Northern Hemisphere, glazing that faces within about 30° of true south, and stays unshaded from roughly 9 a.m. to 3 p.m. in the heating season, collects most of the useful winter sun. North glass gets almost no direct sun. East and west glass gets low-angle sun that is hard to control and adds unwanted summer heat.
Source: U.S. DOE, Guide to Passive Solar Home Design, "Elements of Passive Solar Design," item 1 (Aperture).
PPD-02 · Objective 1.2 · Multiple choice
An office in Phoenix has a long west façade. The client wants to cut afternoon heat gain. Which strategy is most reliable?
Show answer and explanation, PPD-02
Answer: C. Late-day sun from the west sits low in the sky, so a horizontal overhang blocks little of it unless it covers the whole window. Federal daylighting guidance says to minimize east and west windows. A is the classic trap: overhangs work well on south façades because the summer sun is high there. B and D add to the problem.
Sources: DOE, Guide to Passive Solar Home Design, item 5 (Control); Lawrence Berkeley National Laboratory, Tips for Daylighting with Windows (1997), pp. 3-3 and 3-10 (orientation and east/west glazing).
PPD-03 · Objective 1.2 · Check-all-that-apply
A city asks a new big-box store to reduce its contribution to the urban heat island effect. Which strategies apply? Check the four that apply.
Show answer and explanation, PPD-03
Answer: A, B, C, D. EPA identifies trees and vegetation, green roofs, cool roofs, and cool pavements as heat-island reduction strategies. For a cool roof, high solar reflectance matters most, and high thermal emittance helps too. E and F absorb more sun and re-radiate the heat.
Sources: EPA, Heat Island Reduction Solutions; EPA, Using Cool Roofs to Reduce Heat Islands.
PPD-04 · Objective 1.2 · Multiple choice
A site investigation confirms that infiltration is appropriate in a proposed landscape area. Required separation from foundations and utilities, maintenance access, and a safe overflow route can all be provided. The owner wants to reduce the volume of ordinary-storm runoff leaving a paved plaza next to it.
Which proposal most directly meets that goal?
Show answer and explanation, PPD-04
Answer: C. The proposed bioretention area collects runoff and lets it soak into the ground, so less water leaves the site. EPA counts it as a low impact development practice that reduces and slows runoff. A and D change conveyance without reducing the runoff volume through infiltration. B changes when the water leaves, not how much. The stem tells you infiltration suits this site. Don't assume that about every site; soils and separation distances decide it.
Sources: EPA, Urban Runoff: Low Impact Development; EPA, Types of Green Infrastructure, "Bioretention (Rain Gardens)."
PPD-05 · Objective 1.1 · Multiple choice
A clinic site sits in a mapped flood zone with a base flood elevation (BFE) of 12.0 ft. The local floodplain ordinance requires 2 ft of freeboard for the lowest floor. What is the minimum lowest-floor elevation?
Show answer and explanation, PPD-05
Answer: D. BFE is the elevation the 1%-annual-chance ("100-year") flood is expected to reach. Freeboard is extra height above BFE, added as a factor of safety. 12.0 + 2.0 = 14.0 ft. B ignores freeboard, and A and C misapply it. In this exercise, the local ordinance sets the required freeboard.
Source: 44 CFR 59.1, definitions of Base flood, Flood elevation determination, and Freeboard.
PPD-06 · Objective 1.3 · Multiple choice
A library site in a northern U.S. city lies directly north of an existing six-story building, across a narrow street. The library's reading room depends on south daylight and winter sun. Where should the building sit on its site?
Show answer and explanation, PPD-06
Answer: A. Low winter sun casts long shadows north of tall buildings. Pulling the library north puts more distance between its south windows and the obstruction, which improves the odds those windows stay unshaded through the midday heating hours. B puts the reading room in the deepest shadow. C gives up direct sun. D ignores exactly the neighborhood context that objective 1.3 tests.
Source: DOE, Guide to Passive Solar Home Design, item 1 (unshaded 9 a.m.–3 p.m. in the heating season).
Codes & Regulations (6 questions)
PPD-07 · Objective 2.1 · Multiple choice
A 20,000 sq ft lot has a maximum floor area ratio (FAR) of 2.5. The client wants four stories of equal floor area. Ignoring every other limit, what is the largest floor area per story?
Show answer and explanation, PPD-07
Answer: C. FAR × lot area = maximum total floor area: 2.5 × 20,000 = 50,000 sq ft. Divide by 4 stories to get 12,500 sq ft each. D is the building total, not a floor. A divides the lot area by four stories and never applies the FAR. B also falls short of the 12,500 sq ft maximum.
Sources: arithmetic from the exercise inputs; New York City Zoning Resolution §12-10, definitions of floor area ratio and lot coverage. The numerical zoning limits here are exercise data, not a statement of New York City requirements.
PPD-08 · Objective 2.1 · Multiple choice
A rectangular lot is 100 ft wide and 150 ft deep (15,000 sq ft). Zoning requires a 25 ft front setback, a 20 ft rear setback, 10 ft side setbacks on each side, and maximum lot coverage of 50%. What is the largest allowable building footprint?
Show answer and explanation, PPD-08
Answer: A. The setbacks leave a buildable area of (100 − 10 − 10) × (150 − 25 − 20) = 80 × 105 = 8,400 sq ft. Lot coverage caps the footprint at 0.50 × 15,000 = 7,500 sq ft. When two rules apply, the stricter one controls. B forgets coverage, and C ignores the side setbacks (100 × 105). D ignores both limits.
Sources: arithmetic from the exercise inputs; New York City Zoning Resolution §12-10, definitions of floor area ratio and lot coverage. The numerical zoning limits here are exercise data, not a statement of New York City requirements.
PPD-09 · Objective 2.2 · Multiple choice
An accessible ramp in new construction must connect two levels that differ by 36 in. Under the 2010 ADA Standards, what is the minimum configuration?
Show answer and explanation, PPD-09
Answer: D. A ramp's running slope can't be steeper than 1:12, and a single run can't rise more than 30 in. A 36 in rise therefore needs at least two runs. Landings are required at the top and bottom of each run, with at least 60 in of clear length; a landing where runs change direction needs at least 60 × 60 in clear. At 1:12, 36 in of rise takes a combined horizontal run of 432 in (36 ft), plus the required landings. For example, two 18 in-rise runs each need handrails because each run rises more than 6 in. A exceeds the 30 in rise limit. C is too steep for new construction. B invents a 12 in limit.
Source: 2010 ADA Standards §405.2, §405.6, §405.7–405.7.4, §405.8; U.S. Access Board, Guide to Ramps and Curb Ramps.
PPD-10 · Objective 2.3 · Multiple choice
A new general office building has one surface lot of 120 spaces serving a single accessible entrance. For this exercise, a fictional local zoning ordinance requires at least six accessible spaces in this lot, and the 2010 ADA Standards also apply. Which proposal satisfies both?
Show answer and explanation, PPD-10
Answer: C. Table 208.2 requires 5 accessible spaces for a lot of 101–150 spaces. The fictional local ordinance requires 6, so 6 is the minimum that satisfies both. For every 6 accessible spaces, or fraction of 6, at least 1 must be van-accessible. Spaces serving a building go on the shortest accessible route to an accessible entrance. A and B fall short of the local count; A also falls short of the ADA count. D invents an exemption: shared aisles are allowed, but they don't remove the van requirement. The building type matters too. Hospital outpatient facilities, rehabilitation facilities specializing in mobility-related conditions, and outpatient physical therapy facilities have additional requirements for patient and visitor parking, so check the facility type before you read the table.
Source: 2010 ADA Standards Table 208.2, §208.2.1–208.2.4, §208.3.1, §502.3; U.S. Access Board, Guide to Parking Spaces.
PPD-11 · Objective 2.2 · Multiple choice
A site walk on an accessible route rises 9 in over a 12 ft horizontal run, a slope of 1:16. How do the 2010 ADA Standards treat it?
Show answer and explanation, PPD-11
Answer: A. Any walking surface steeper than 1:20 is a ramp by definition. At 1:16 it is within the 1:12 maximum, and because it rises more than 6 in it needs handrails. D misreads the rule: a route can be steeper than 1:20 if it is built as a compliant ramp. C invents a threshold.
Source: 2010 ADA Standards §106.5 ("ramp") in Chapter 1, and §403.3, §405.2, §405.8 in Chapter 4.
PPD-12 · Objective 2.2 · Multiple choice
In a new building covered by the 2010 ADA Standards, a manual swinging door on an accessible route has a clear opening of 31½ in. That is measured between the face of the door and the stop with the door open 90°. The opening is less than 24 in deep, and no exception applies.
Which revision fixes the clear-width deficiency?
Show answer and explanation, PPD-12
Answer: B. The rule sets a 32 in minimum clear opening, measured from the face of the open door to the stop. That is why a nominal 32 in leaf usually falls short once the door's thickness and stop are counted. A relabels without changing the geometry, C uses the wrong measurement, and D leaves the width unchanged. The stem gives the opening depth because openings deeper than 24 in need 36 in clear.
Source: 2010 ADA Standards §404.2.3.
Building Systems, Materials, & Assemblies (9 questions)
PPD-13 · Objective 3.2 · Multiple choice
A two-story steel-framed retail building in a high-seismic region needs a fully glazed, open ground-floor storefront, with no diagonal braces or solid walls along the street. Which lateral system best fits?
Show answer and explanation, PPD-13
Answer: C. Moment frames resist lateral loads through bending in beams and columns and their moment-resisting connections. They need no braces or structural walls, so they allow large open bays, though they can cost more to construct. A and B would block the storefront openings. D is a poor choice for resisting earthquakes.
Source: NIST, Seismic Design of Steel Special Moment Frames, GCR 16-917-41 (2nd ed., 2016), §2.3, p. 7.
PPD-14 · Objective 3.2 · Multiple choice
A schematic shows a three-story office with an open, column-only parking level at grade and stiff, wall-filled floors above. Why should the structural engineer raise this early?
Show answer and explanation, PPD-14
Answer: A. A soft story has comparatively low lateral stiffness; a weak story has comparatively low lateral strength. The open parking level is a reason to evaluate that stiffness change early because lateral deformation can concentrate there. B and C overstate the problem: this is a lateral-load issue that good design can solve. D misses it entirely.
Sources: Zhang et al., Motivators and impediments to seismic retrofit implementation for wood-frame soft-story buildings (2022), introduction and Note 1 (soft versus weak story); NIST GCR 16-917-41, §3.1, p. 10 (concentrated story deformation).
PPD-15 · Objective 3.2 · Multiple choice
A schematic review of a two-story light-frame house finds a break in the wind-uplift load path at the roof-to-wall connection. Roof sheathing-to-framing connections, connections between stories, and wall-to-foundation anchorage are all shown. Which response fixes the problem?
Show answer and explanation, PPD-15
Answer: D. A continuous load path needs every connection from roof to foundation. Connections between major assemblies are usually the weakest links, and if one fails, loads shift to parts that may not be strong enough. D repairs the missing link. A, B, and C strengthen other parts and leave the break in place. The actual connectors still need to be sized for the project's design loads.
Source: DOE Building America Solution Center, Continuous Load Path, "Scope" and "Description".
PPD-16 · Objective 3.3 · Multiple choice
Attorneys in a new law office complain that they can hear conversations through the walls between private offices. Which change targets the problem?
Show answer and explanation, PPD-16
Answer: C. STC (Sound Transmission Class) describes how much sound a wall or floor assembly blocks from one room to the next. NRC (Noise Reduction Coefficient) describes how much sound a material absorbs, which controls echo within a room but does little to stop sound passing between rooms. A and B treat absorption, not isolation, and D doesn't address the wall.
Sources: NIH Office of Research Facilities, "Sound Design Metrics" (Sept. 2019); GSA, Building Systems Upgrades, acoustics guidance.
PPD-17 · Objective 3.3 · Multiple choice
A school cafeteria is loud and echoey, with hard walls, floor, and ceiling. Sound isolation to the next rooms is fine. What is the most direct fix?
Show answer and explanation, PPD-17
Answer: B. This is reverberation inside the room, and absorption (NRC) is the tool for that. A, C, and D improve isolation between rooms, which isn't the complaint. Compare PPD-16: same two ratings, opposite problem.
Source: NIH ORF, "Sound Design Metrics".
PPD-18 · Objective 3.1 · Multiple choice
In a multi-zone office, perimeter offices get very different solar loads depending on their façade. How does a variable air volume (VAV) system respond?
Show answer and explanation, PPD-18
Answer: A. VAV terminal units modulate airflow to each space to match its load. Supply air temperature stays near a setpoint, though it may be reset modestly when loads are low. B does not vary airflow by zone to meet the stated loads. C describes a refrigerant-based system. D describes a ventilation-only unit.
Source: NIST, NISTIR 4605, §1.1.
PPD-19 · Objective 3.1 · Multiple choice
An office building needs tight control of outdoor ventilation air, separate from space heating and cooling. Which approach best fits?
Show answer and explanation, PPD-19
Answer: A. A DOAS conditions and delivers outdoor ventilation air separately from the system that heats and cools the spaces, so ventilation can be controlled on its own. B can't guarantee the air quantity. C bundles ventilation with heating and cooling, and D provides no ventilation.
Source: PNNL, PNNL-34452, Appendix A.
PPD-20 · Objective 3.4 · Multiple choice
A wood-framed wall meets its specified cavity-insulation R-value, but the energy model shows that heat flow through the framing keeps the whole-wall assembly below its thermal-performance target. Which change most directly addresses that problem?
Show answer and explanation, PPD-20
Answer: D. Studs and other framing members conduct heat through the wall, acting as thermal bridges. DOE notes that framing can account for nearly one-fourth of a conventionally framed wall's area. Continuous exterior insulation covers the framing and cuts those losses. C adds more bridges, and B leaves the bridges untouched.
Source: DOE Building America Solution Center, Continuous Rigid Insulation Sheathing.
PPD-21 · Objective 3.4 · Multiple choice
The project brief requires a whole-window U-factor no greater than 0.30 and a visible transmittance (VT) of at least 0.55. Among the options that meet both, choose the lowest solar heat gain coefficient (SHGC). The values are project data for this exercise. U-factor is given in Btu/(h·ft²·°F); SHGC and VT are dimensionless.
| Option | U-factor | SHGC | VT |
|---|---|---|---|
| A | 0.30 | 0.25 | 0.60 |
| B | 0.30 | 0.45 | 0.60 |
| C | 0.45 | 0.25 | 0.60 |
| D | 0.30 | 0.25 | 0.35 |
Which option meets the brief?
Show answer and explanation, PPD-21
Answer: A. A meets both limits and has the lowest SHGC among the options that qualify. B qualifies but lets in more solar heat. C fails the U-factor limit, and D fails the VT minimum. Each rating measures something different. A lower U-factor means better insulation, a lower SHGC means less solar heat, and a higher VT means more visible light. A great number on one rating doesn't make up for failing another.
Source: ENERGY STAR, Independently Tested and Certified Energy Performance, "Performance Ratings."
Project Integration of Program & Systems (11 questions)
PPD-22 · Objective 4.1 · Multiple choice
A one-story, 10,000 sq ft clinic in Minnesota could be a 100 ft × 100 ft square or a 50 ft × 200 ft bar. Both have 12 ft walls. Which statement is correct?
Show answer and explanation, PPD-22
Answer: B. The perimeters are 400 ft and 500 ft. Multiplied by 12 ft, that's 4,800 versus 6,000 sq ft of wall, so the bar has 25% more. Compact, simple shapes expose less envelope, so they gain and lose less heat. The bar might still win on daylight. Weighing that trade-off is what integration questions test.
Sources: Virginia Cooperative Extension, publication 2908-9019; arithmetic from the inputs given.
PPD-23 · Objective 4.1 · Multiple choice
For a small office in Phoenix, compare schemes with the same floor area, total glazing area, and glazing performance. Which configuration best supports controlling solar heat gain?
Show answer and explanation, PPD-23
Answer: D. D combines an east–west long axis with most glazing on the north and south and shading at the south windows, reducing reliance on difficult-to-shade east and west glass. A and B put the most glass where low sun is hardest to shade. C spreads it everywhere.
Sources: LBNL, Tips for Daylighting with Windows (1997), p. 3-10 (orientation and east/west glazing); Virginia Cooperative Extension, 2908-9019.
PPD-24 · Objective 4.4 · Multiple choice
Open offices along a south façade have a window head height of 9 ft above the finished floor and no light shelf. Using LBNL's approximate 1.5× planning rule, what is the estimated useful daylight depth?
Show answer and explanation, PPD-24
Answer: C. For a standard side window, the useful daylit zone is about 1.5 × the window head height: 1.5 × 9 = 13.5 ft. The guide says a reflective light shelf may extend that zone to as much as 2.5× (about 22.5 ft). B applies that light-shelf allowance to a window without a shelf. Treat this as a planning rule of thumb, not a code requirement or a guarantee of performance.
Source: LBNL, Tips for Daylighting with Windows (1997), p. 3-2 (window head height and daylight depth).
PPD-25 · Objective 4.4 · Multiple choice
An art studio in Chicago needs steady, even daylight on work surfaces, with little glare or heat gain from direct sun. Which strategy fits best?
Show answer and explanation, PPD-25
Answer: B. North-facing openings usually receive mainly diffuse skylight, with less direct sun than the other choices. Early-morning and late-afternoon sun can still require shading. A, C, and D all admit direct sun, which brings glare, heat, or both.
Source: LBNL, Tips for Daylighting with Windows, p. 3-3 (north orientation and shading).
PPD-26 · Objective 4.4 · Multiple choice
A client wants a naturally ventilated office in a mild climate, with 10 ft ceilings. For preliminary planning, use a cross-ventilation depth screen of 5 times ceiling height and assume clear internal air paths. Which floor plan best supports cross ventilation within that screen?
Show answer and explanation, PPD-26
Answer: D. D combines operable openings on opposite façades with a 45 ft plan depth, within the supplied 5 × 10 = 50 ft screen. A is single-sided, C has no operable openings, and B exceeds the supplied screen. CBE identifies 5H for cross ventilation and 2H for single-sided ventilation as traditional rules with limited validation. They are preliminary planning aids; actual ventilation depends on opening size, wind, internal air paths, and other conditions.
Source: UC Berkeley Center for the Built Environment, Evidence-Based Natural Ventilation Guidelines.
PPD-27 · Objective 4.4 · Check-all-that-apply
A library in Wisconsin will use passive solar to cut its heating load, with its main glazing facing south. Which design moves support that goal? Check the three that apply.
Show answer and explanation, PPD-27
Answer: A, B, C. These are DOE's core passive-solar moves for a cold climate. E blocks the low winter sun that C protects. D adds hard-to-control west glass, and F gets almost no direct sun.
Source: DOE, Guide to Passive Solar Home Design, items 1 and 5.
PPD-28 · Objective 4.3 · Multiple choice
A civic building's main entrance is up a flight of steps. The schematic adds a separate side ramp entrance for wheelchair users. A design reviewer suggests regrading the plaza so everyone uses one level main entrance. Which Principle of Universal Design is the reviewer applying most directly?
Show answer and explanation, PPD-28
Answer: C. Equitable Use calls for the same means of use for all users, identical whenever possible, and for not segregating or stigmatizing anyone. One shared entrance does that. The other three are real principles but aren't the central issue here.
Source: NC State University, Center for Universal Design, The Principles of Universal Design (Version 2.0, 1997), Principle One.
PPD-29 · Objective 4.3 · Multiple choice
A branch bank wants its parking lot and entry to feel safer during operating hours. Which move applies the CPTED (Crime Prevention Through Environmental Design) principle of natural surveillance?
Show answer and explanation, PPD-29
Answer: A. Natural surveillance puts people and windows where they can see what's happening. B, C, and D all reduce visibility.
Source: North Carolina Department of Public Safety, Prevention Through Environmental Design, "Three Key Concepts" (Natural Surveillance).
PPD-30 · Objective 4.3 · Multiple choice
The program calls for a single-user accessible toilet room. Under the 2010 ADA Standards, which floor clearance must the room's size accommodate?
Show answer and explanation, PPD-30
Answer: B. Toilet rooms need turning space inside the room. That means either a circle at least 60 in across or a T-shape within a 60 in square, with arms and base at least 36 in wide. The T's arms need at least 12 in of clear extension beyond the intersection in each direction, and its base needs at least 24 in. Turning space must be coordinated with fixture clearances and door requirements; its dimensions alone do not determine the room's minimum size. A is too small, C does not provide a required turning-space configuration, and D invents an exemption.
Source: 2010 ADA Standards §603.2 and §304.3.
PPD-31 · Objective 4.2 · Check-all-that-apply
A perimeter office gets plenty of daylight. The owner wants the electric lighting to respond to that daylight and wants occupants protected from glare, without losing useful daylight. Which proposals meet those goals? Check the two that apply.
Show answer and explanation, PPD-31
Answer: A and C. Photosensor dimming adjusts electric light to the daylight available. Automatic shades handle glare. B and E ignore daylight entirely. D confuses letting in more light with controlling glare. F throws away the daylight the owner wants to keep.
Source: GSA, Building Systems Upgrades, lighting and lighting controls.
PPD-32 · Objective 4.2 · Multiple choice
A community learning center has weekday offices and evening classrooms. The owner's requirements for comparing system alternatives are:
- Finished floor to finished floor: 14 ft maximum
- Clear ceiling height: 10 ft minimum
- Independent operating schedules for the office and classroom zones
- Initial installed cost: $460,000 maximum
The consultant's comparison is below. "Combined depth" is everything between the clear ceiling and the finished floor above: floor assembly, structure, services, and ceiling. All values are exercise data.
| Alternative | Combined depth above ceiling | Independent zone schedules | Initial cost |
|---|---|---|---|
| A | 4 ft 6 in | Yes | $420,000 |
| B | 3 ft 6 in | Yes | $450,000 |
| C | 3 ft 0 in | No | $400,000 |
| D | 3 ft 9 in | Yes | $480,000 |
Which alternative meets all four requirements?
Show answer and explanation, PPD-32
Answer: B. At a 14 ft floor-to-floor height, B leaves 14 ft − 3 ft 6 in = 10 ft 6 in of clear ceiling. It also supports separate schedules and comes in under the cost cap. A leaves only 9 ft 6 in. C fails the scheduling requirement, and D is over budget. Being cheapest (C) or thinnest doesn't rescue an option that fails a stated requirement.
Sources: arithmetic from the inputs given; GSA, Building Systems Upgrades (zone HVAC systems and controls to separate space uses).
Project Costs & Budgeting (6 questions)
PPD-33 · Objective 5.2 · Multiple choice
A cost consultant submits this preliminary estimate. The scope is fixed, no other costs are included, and all amounts are exercise data.
| Line | Value |
|---|---|
| Building area | 12,000 gross sq ft |
| Construction allowance | $300 per gross sq ft |
| Base building estimate | $3,600,000 |
| Design contingency | 10% of the base building estimate |
| Reported total (base + contingency) | $4,000,000 |
Which review comment is correct?
Show answer and explanation, PPD-33
Answer: C. The contingency is defined as 10% of the base: 12,000 × $300 = $3,600,000; × 0.10 = $360,000; total $3,960,000. A switches the basis to 10% of the final total, which the estimate doesn't say. B deletes a stated allowance, and D uses a different percentage. This is the skill objective 5.2 now asks for: checking an estimate someone else prepared, not building one from scratch. Fixing the arithmetic doesn't prove the unit price is right for a real project.
Sources: arithmetic from the inputs given; NCARB, Updated ARE Guidelines for April 2026 Exam Changes, PPD objective 5.2.
Mini case study: Maple Street Branch Library (PPD-34 to PPD-38)
Read both resources first. They stay the same for all five questions, and each question can be answered on its own. All project figures are fictional exercise data.
Resource 1: Project brief
- New one-story branch library, 12,000 gross sq ft, in schematic design.
- Owner's construction budget: $4,000,000.
- Owner's program priorities, in order: (1) children's area of at least 2,500 sq ft; (2) community meeting room of 1,200 sq ft; (3) staff work area; (4) a 600 sq ft covered outdoor reading terrace.
- The owner plans to keep the building at least 20 years and wants life-cycle thinking on the roof.
Resource 2: Cost information (prepared by the owner's cost consultant)
- Schematic-design estimate: $4,400,000. It is priced parametrically against past library projects and includes design allowances.
- Roof Option A (baseline) is included in the estimate.
- Roof Option B (more insulation plus a high-reflectance membrane): $100,000 more in first cost, with estimated energy savings of $9,000 per year.
- The owner's basis for analysis: 20-year study period, 3% real discount rate, savings constant in real terms and received at the end of each year. Pay the extra first cost at the start of the study period. Uniform present value (UPV) factor = [(1 + d)ⁿ − 1] ÷ [d(1 + d)ⁿ], where d = 0.03 and n = 20.
- Both roof options meet the required performance over the 20-year study period. For this comparison, all other maintenance, replacement, and operating costs and residual values are equal.
PPD-34 · Objective 5.2 · Multiple choice
Case resources: Maple Street Branch Library (Resources 1 and 2)
The estimate is 10% over the construction budget. What is the architect's most appropriate next step?
Show answer and explanation, PPD-34
Answer: B. Since April 27, 2026, objective 5.2 asks you to evaluate cost estimates prepared by others. You need to know how estimates vary with the estimating method and reconcile them with the budget by considering design alternatives. A jumps to a new detailed estimate before evaluating the basis of the consultant's schematic estimate. C puts off a known problem, and D skips the evaluation.
Sources: NCARB, Updated ARE Guidelines for April 2026 Exam Changes, PPD objective 5.2 description; GSA, P-120 Project Cost and Schedule Management Requirements (2022), §3.10, p. 29 (estimate evaluation and recovery alternatives).
PPD-35 · Objective 5.2 · Multiple choice
Case resources: Maple Street Branch Library (Resources 1 and 2)
How should the architect read a schematic estimate priced parametrically against past projects, with allowances?
Show answer and explanation, PPD-35
Answer: A. Under GSA's P-120 framework, early estimates are parametric and carry allowances. Each phase adds more measured quantities and more detailed pricing, until the final construction-documents estimate uses measured quantities and detailed unit prices, with no lump-sum allowances. Early estimates are useful for decisions, but they carry more uncertainty. B overstates them, C dismisses them, and D confuses an estimate with a bid.
Source: GSA, P-120 Project Cost and Schedule Management Requirements (2022), Table 3-4, pp. 26–27.
PPD-36 · Objective 5.3 · Multiple choice
Case resources: Maple Street Branch Library (Resources 1 and 2)
What is the simple payback period for Roof Option B?
Show answer and explanation, PPD-36
Answer: C. $100,000 ÷ $9,000 per year ≈ 11.1 years. Simple payback ignores the time value of money and any savings after the payback point, which is why the owner also asked for a life-cycle comparison. B is the UPV factor from PPD-37, not a payback period.
Source: NIST, Handbook 135 (2022), §6.4–6.4.1, pp. 82–83 (simple payback and its limits).
PPD-37 · Objective 5.3 · Multiple choice
Case resources: Maple Street Branch Library (Resources 1 and 2)
On the owner's basis, what is the approximate present value of Option B's 20 years of energy savings, and how does it compare with the extra first cost?
Show answer and explanation, PPD-37
Answer: D. UPV = (1.03²⁰ − 1) ÷ (0.03 × 1.03²⁰) ≈ 14.877. Present value of savings ≈ $9,000 × 14.877 ≈ $133,900. Subtract the $100,000 extra first cost to get a net life-cycle benefit of about $33,900. A is the undiscounted total ($9,000 × 20), which ignores the time value of money. B and C understate the savings calculated with the supplied factor. The net benefit depends on the case's equal-other-costs and timing assumptions. This is the objective 5.3 skill: weighing upfront cost against future costs.
Source: NIST, Handbook 135 (2022), §3.2.2.1, p. 26 (uniform present value factor); §4.3.1, pp. 41–42 (timing); §5.1.2, p. 65 (cost categories).
PPD-38 · Objective 5.1 · Multiple choice
Case resources: Maple Street Branch Library (Resources 1 and 2)
To help close the budget gap, the owner will accept removing about 600 sq ft of scope. Which choice best respects the program priorities?
Show answer and explanation, PPD-38
Answer: D. The terrace is the owner's lowest priority and exactly 600 sq ft. A cuts the top priority below its 2,500 sq ft minimum. C cuts the second priority in half. B removes the higher-priority staff work area. Objective 5.1 asks you to judge alternatives against the program, not just against cost.
Source: Resource 1 of the case study.
Check your results by section
NCARB scores the whole division against one cut score, so a weak section won't fail you on its own. Integration alone is about a third of your items, though (ARE 5.0 Guidelines, p. 40).
| Section | Questions | Your correct | NCARB share of exam |
|---|---|---|---|
| Environmental Conditions & Context | 6 | ___ / 6 | 10–16% |
| Codes & Regulations | 6 | ___ / 6 | 16–22% |
| Building Systems, Materials, & Assemblies | 9 | ___ / 9 | 19–25% |
| Project Integration of Program & Systems | 11 | ___ / 11 | 32–38% |
| Project Costs & Budgeting | 6 | ___ / 6 | 8–14% |
| Total | 38 | ___ / 38 |
Use your misses to choose what to study next. Six to eleven questions per section is a small sample. Your score shows how you did on these items, not a predicted ARE score or a pass/fail signal. For each miss, start with the matching section under How to study each PPD section. Then log it in the error log in the study plan.
What changed on April 27, 2026
This guide follows NCARB's ARE 5.0 Guidelines effective October 1, 2026, including the April 27, 2026 objective changes.
NCARB adjusted 12 of the exam's 91 objectives and reformatted case studies. The number of items, testing time, and division structure did not change. Passed divisions are unaffected (NCARB; NCARB).
For PPD, two changes matter:
- Objective 5.2 was narrowed. It now reads "Evaluate cost estimates based on the project design." You're expected to evaluate cost estimates prepared by others, understand how they vary by estimating method, and reconcile them with the budget through design alternatives. The current objective focuses on evaluating supplied estimates rather than preparing them from scratch.
- Objective 5.3 was clarified. You judge cost-effectiveness for both upfront costs (the construction budget) and future maintenance and replacement costs.
Case studies now come with one or two resources each and fewer items per case study, though the total number of case-study items per division stays about the same (NCARB, ARE 5.0 Question Types).
If you're studying from older materials, most of the content still applies. For objective 5.2, prioritize evaluating supplied estimates. A source that presents 120 questions as the current PPD count is outdated; the current count is 100.
How to study each PPD section
Environmental Conditions & Context
Treat every site fact as a design trigger: sun, wind, slope, drainage, flood risk, noise, neighbors, access, and transit. For each one, ask what it does to the building's location, orientation, and form.
- Sun and orientation: main glazing within about 30° of true south for winter gain; shade south glass with overhangs; minimize east and west glass, where low sun is hard to block (DOE).
- Stormwater: low impact development (bioretention, permeable pavement, green roofs) reduces and slows runoff by infiltrating or reusing it, where soils allow (EPA).
- Heat island: trees and vegetation, green roofs, cool roofs, and cool pavements (EPA).
- Flood: know base flood, BFE, and freeboard, and apply the governing requirements supplied in the question; PPD-05 gives a fictional local freeboard rule (44 CFR 59.1).
- Context: shadows from neighbors, the scale and character of the street, and noise sources all shape where the building and its key rooms go.
Codes & Regulations
Work source-first. Name the governing document, find the provision, read its exceptions, then apply it to the facts in the question. NCARB has announced that code-related ARE items reference the 2021 International Code Council (ICC) family of codes, effective February 27, 2024 (NCARB). The current ARE 5.0 Guidelines, p. 115, lists the 2021 International Building Code, ICC A117.1-2017, and 2010 ADA Standards among its building-code and professional-standard references. The exam's reference edition, the federal ADA Standards, and the code your city has adopted are three different things.
- Zoning math: FAR × lot area = maximum floor area. Setbacks define a buildable envelope, and lot coverage caps the footprint. When two limits apply, the stricter one controls (PPD-07, 08).
- Accessibility (2010 ADA Standards): for the new-construction ramp conditions here, use 1:12 maximum slope, no more than 30 in of rise per run, landings at the top and bottom of each run with at least 60 in clear length, and handrails on runs rising more than 6 in. Landings where runs change direction need at least 60 × 60 in clear. Anything steeper than 1:20 is a ramp. For the manual swinging door conditions in PPD-12, allow at least 32 in clear, measured door face to stop at 90°; openings deeper than 24 in require 36 in clear. Turning space is a 60 in circle or a compliant T in a 60 in square. Parking counts come from Table 208.2, with at least 1 van space per 6 accessible spaces or fraction of 6, subject to the facility-specific scoping rules (2010 ADA Standards, §§208, 304, 404–405).
- Multiple codes at once: expect questions where zoning, accessibility, and the building code all bear on one decision. The answer has to satisfy all of them.
Building Systems, Materials, & Assemblies
For each system, learn what it does, what space it takes, what it costs or demands, and what it changes elsewhere in the building.
- Structure: moment frames keep bays open, while braced frames and shear walls occupy bays that must be coordinated with openings (NIST GCR 16-917-41, §2.3). A comparatively flexible first story is a reason to examine seismic behavior early; soft refers to stiffness, while weak refers to strength (Zhang et al., introduction and Note 1). A continuous load path from roof to foundation is required (BASC).
- HVAC: VAV varies airflow by zone (NIST). A DOAS separates ventilation air from heating and cooling (PNNL).
- Envelope: framing creates thermal bridges, and continuous insulation reduces them (BASC). Know U-factor (lower insulates better), SHGC (lower blocks more solar heat), and VT (higher lets in more light) (ENERGY STAR).
- Acoustics: STC is isolation between rooms. NRC is absorption within a room (NIH ORF).
- Special systems: NCARB's objective 3.3 lists acoustics, communications, lighting, security, conveying, and fire suppression. For each one, know its purpose and what it needs from the plan and section.
Project Integration of Program & Systems
This is the biggest section (32–38%), and it's where a good component can still fail inside the whole building. Use this five-check routine on any integration question:
- Requirements: list what the brief requires, such as spaces, adjacencies, accessibility, environmental goals, budget, and heights. Separate requirements from preferences.
- Dealbreakers: find the stated limit each option might break. Name the failing limit when you reject an option.
- Fit: compare each system's performance, space needs, and maintenance access with the requirements.
- Knock-on effects: trace one consequence for structure, ceiling space, envelope, circulation, or another system.
- Same basis: when costs are compared, check that they cover the same scope and the same time period.
Worked example: does the building section fit? Floor-to-floor height is 14 ft 0 in. From the upper finished floor down to the underside of the structure, including the floor assembly, is 2 ft 0 in. The required service zone below the structure is 1 ft 6 in, and the ceiling assembly is 3 in. The owner wants at least 10 ft 0 in of clear ceiling height. These are exercise values, not recommended dimensions.
| Zone | Inches |
|---|---|
| Floor to floor (14 ft × 12) | 168 |
| Floor assembly and structure (2 ft) | − 24 |
| Service zone (1 ft 6 in) | − 18 |
| Ceiling assembly | − 3 |
| Clear ceiling height | 123 in = 10 ft 3 in |
It works, with 3 in to spare. The trap is counting the floor assembly twice: it's already inside the 2 ft structural zone. If the required service zone later increases by 4 in, the section fails, so redo the check every time a zone changes. PPD-32 uses the same logic.
Daylight, ventilation, and form also show up here as integration decisions. For preliminary daylight planning, LBNL gives a typical useful depth of about 1.5 × window head height, with a possible extension to 2.5× using a reflective light shelf (LBNL, p. 3-2). A plan-depth screen of five times the ceiling height is a traditional starting point for cross ventilation, not a guarantee of adequate ventilation or comfort (CBE). Compact forms reduce exposed envelope for a given floor area; east–west orientation helps when glazing and shading respond to the sun (VT Extension). The program side includes universal design (NC State) and CPTED (North Carolina DPS).
Project Costs & Budgeting
- Objective 5.2: evaluate supplied estimates. Check an estimate's scope, area basis, unit rates, allowances, and arithmetic. Then compare it with the budget, and if it's over, propose design alternatives for the owner to choose from (PPD-33, 34).
- Know how estimates evolve. Early estimates are parametric with allowances. Later ones use measured quantities and detailed unit prices (GSA P-120).
- Life-cycle cost. Bring future costs to present value: PV = F ÷ (1 + d)ⁿ for a one-time future amount F received or paid after n years. For an equal amount at the end of each year, multiply that annual amount by the UPV factor: [(1 + d)ⁿ − 1] ÷ [d(1 + d)ⁿ]. At a 0% discount rate, the UPV factor is simply n. Here d is the annual discount rate as a decimal and n is the number of years; keep real cash flows with a real rate, as in the case study. Simple payback = extra first cost ÷ annual savings, but it ignores the time value of money and anything after payback (NIST HB 135).
- Value engineering means analyzing functions to deliver the essential ones at the lowest life-cycle cost, consistent with required performance, reliability, quality, and safety (OMB Circular A-131, §5(k)). It is not just cutting cost.
- Program first. When the owner permits scope reduction, compare the stated priorities and preserve the higher-priority requirements; PPD-38 identifies the terrace as the lowest priority.
Your 8-week PPD study plan
This plan assumes about 8 hours a week for someone who has started studying for the ARE. Treat these as working targets, not a required number of hours.
| Week | Focus | Tasks |
|---|---|---|
| 1 | Baseline | Read the 17 PPD objectives. Take this practice set untimed and log every miss and every guess. Note which sections you scored lowest in. |
| 2 | Environmental Conditions & Context | Solar orientation and shading, daylight, stormwater and LID, heat island, flood terms, site context. Redo PPD-01 to 06 after changing one fact in each stem. |
| 3 | Codes & Regulations | Zoning math; 2010 ADA ramps, routes, doors, turning space, and parking. Read the code references NCARB lists, and practice finding provisions rather than memorizing tables. |
| 4 | Systems I: structure and envelope | Lateral systems, load path, irregularities, thermal bridging, glazing ratings. |
| 5 | Systems II: MEP, acoustics, special systems | VAV, DOAS, lighting controls, STC vs NRC, fire suppression, conveying, security, communications. |
| 6 | Integration (largest section) | Use the five-check routine on every integration item you can find. Sketch sections like the worked example. Redo PPD-22 to 32. |
| 7 | Costs and case studies | Estimate review, life-cycle cost, payback, value engineering. Practice case studies with resources open, finding the facts and provisions each question needs, then applying them. |
| 8 | Rehearse and repair | Take NCARB's free PPD practice exam in test mode, timed, with your break planned. Review every rationale by section, fix the top gaps, and confirm your test date. |
Adjusting it:
- Strong background: compress to 6 weeks by merging weeks 2–3 and 4–5 only if you already know much of the combined material. To keep the full workload, allow about 16 hours in each merged week.
- About 4 hours a week: stretch each row across two weeks.
- Retaking: the second page of a failing score report shows your relative strengths and weaknesses (Guidelines, p. 41). Start with weeks 1, 6, and 8, then add the rows for your weak sections. You can retake after 60 days.
- Changing your appointment: rescheduling is free 31 or more days out, $75 at 15–30 days, and $150 at 7–14 days. You can't reschedule fewer than 7 days (168 hours) before the appointment, and each appointment may be rescheduled at most 3 times (NCARB Fees; Guidelines, p. 12). If you want the free window, decide at least 31 days before your appointment.
Error log
| Question or objective | What I chose | Why it was wrong (or why I guessed) | Rule or source to reread | New version to try | Retry result |
|---|---|---|---|---|---|
| Example: PPD-08 | B (8,400 sq ft) | Stopped at the setback envelope and forgot lot coverage | Zoning: apply every limit, take the strictest | Same lot, coverage 60% | Correct; setbacks now control (8,400 < 9,000) |
Remembering a question's answer isn't the same as being able to use the rule. For each miss, change one condition and work it again.
Test-day rules that cost people points
- Answer every item. Wrong answers cost nothing, and blanks count as wrong. Each scored item is worth one point, with no partial credit (Guidelines, p. 40).
- Watch the count on check-all-that-apply. The item tells you in bold how many to choose, and you only get credit for the exact correct set (Guidelines, item types).
- Breaks lock what you've seen. After any break, every item you've already viewed is locked, including flagged or unanswered ones. Finish and review a block before you step away (Guidelines, pp. 22 and 33).
- Pace yourself. 245 minutes for 100 items works out to about 2.45 minutes per item on average, including resource lookup and review within that time budget.
- Case studies need their resources. Case-study questions can't be answered without the resources, and each question stands on its own (NCARB).
- Talk about topics, not items. NCARB says it's fine to tell a study group "make sure you understand daylighting design for PPD." Describing questions you saw is a violation (Guidelines, p. 44).
Use NCARB's free PPD practice exam
NCARB offers a free, full-length, scored PPD practice exam with the same number of items as the real division. You open it through your NCARB Record. Use practice mode to see the correct answers and rationales as you go, and test mode for a timed rehearsal. Your results show a percentage for each section plus the rationale for every item. NCARB uses a fixed cut of about 68% for practice exams only. It isn't the live exam's passing standard (NCARB Free ARE 5.0 Practice Exams).
Open NCARB's free PPD practice exam: instructions on NCARB's site.
PPD at a glance
| Item | Current rule |
|---|---|
| Exam owner / delivery | NCARB / PSI test centers or PSI online proctoring |
| Items | 100 total: 91 scored and 9 unscored pretest items you can't identify |
| Time | 4 hr 5 min of testing, 45 min of optional break time, and 10 min for introductory/conclusion screens; 5 hr total appointment |
| Item types | Multiple choice (3–4 options), check-all-that-apply (6 options), hotspot; as standalone items and case studies |
| Case studies | Up to 9 case studies and up to 20 case-study items; 1–2 resources per case study |
| Scoring | Pass/fail on the whole division; 1 point per scored item; no partial credit or penalty for a wrong answer |
| Results | Provisional feedback at the end; official report in 7–10 calendar days |
| Retakes | After 60 days; at most 3 attempts of the same division in any 12 months |
| Fee | $263 per attempt |
| Pass rate (all candidates) | 2020: 45% · 2021: 47% · 2022: 47% · 2023: 50% · 2024: 47% · 2025: 48% |
PPD has had the lowest pass rate of the six divisions every year from 2020 through 2025. These figures cover first-time and repeat takers combined (NCARB Pass Rates). Sources for the other rows: ARE 5.0 Guidelines pp. 8, 11, 37–41, 92; NCARB PPD page; ARE 5.0 Question Types; NCARB Fees.
Questions candidates ask
How many questions are on ARE PPD, and how long is it? 100 items in 4 hours 5 minutes of testing, plus 45 minutes of optional break time and 10 minutes for introductory/conclusion screens, for a 5-hour appointment (Guidelines, pp. 8 and 92).
Do I need to memorize the IBC? NCARB says candidates should understand the concepts and commonly used code sections; it does not expect memorization of specific sections or details (Guidelines, p. 115). PPD tests whether you can apply codes and reconcile several at once. Know which references NCARB uses—including the 2021 IBC, ICC A117.1-2017, and 2010 ADA Standards—and practice locating and applying provisions.
How is PPD different from PA and PDD?
| Division | Focus, in NCARB's words |
|---|---|
| Programming & Analysis (PA) | "The evaluation of project requirements, constraints, and opportunities" |
| Project Planning & Design (PPD) | "The preliminary design of sites and buildings," including "the generation or evaluation of design alternatives" |
| Project Development & Documentation (PDD) | "The integration and documentation of building systems" |
The subjects overlap. PPD sits between analyzing a project and documenting it (PA, PPD, PDD). You can take the divisions in any order.
Is NCARB's practice exam enough on its own? It's NCARB's free full-length rehearsal, and it explains every answer. But it's a single form. Use it as your final check after targeted practice, not as your only study material.
Are these real ARE questions? No. They're original. Seeking out, using, or sharing confidential ARE exam content violates NCARB's Candidate Agreement (Guidelines, p. 45).
Will a new version of the ARE wipe out my PPD pass? NCARB's current Guidelines say passed ARE 5.0 divisions stay valid for as long as ARE 5.0 is delivered and carry credit into the next version (Guidelines, p. 10). NCARB's Pathways to Practice timeline says no launch date has been established for the next ARE version.
Where does PPD fit in the whole ARE? See NCARB's ARE 5.0 preparation resources for all six divisions.
Sources
NCARB (exam owner)
- ARE 5.0 Guidelines, effective October 1, 2026: pp. 8, 10–12, 22, 33, 37–41, 44–45, 91–97, 115; item types section
- ARE: Project Planning & Design
- Updated ARE Guidelines for April 2026 Exam Changes Now Available (January 22, 2026)
- NCARB Implements Changes to ARE Objectives and Case Studies (April 27, 2026)
- ARE 5.0 Question Types
- ARE 5.0 Pass Rates
- Free ARE 5.0 Practice Exams
- Fees
- Updates to the ARE 5.0 Guidelines (2021 ICC code references)
- Pathways to Practice timeline
- ARE 5.0 preparation resources
Codes and standards
- DOJ, 2010 ADA Standards for Accessible Design; U.S. Access Board Chapter 1, Chapter 4, ramps guide, and parking guide
- New York City Zoning Resolution §12-10, definitions only; the questions supply fictional numerical limits
- 44 CFR 59.1, flood and freeboard definitions
Technical teaching sources
- DOE, Guide to Passive Solar Home Design
- LBNL, Tips for Daylighting with Windows (1997)
- UC Berkeley CBE, Natural Ventilation Guidelines
- EPA: Low Impact Development, Types of Green Infrastructure, Heat Islands, Cool Roofs
- Virginia Cooperative Extension, 2908-9019
- NIST, Seismic Design of Steel Special Moment Frames, GCR 16-917-41 (2nd ed., 2016), §§2.3 and 3.1
- Zhang et al., Motivators and impediments to seismic retrofit implementation for wood-frame soft-story buildings (2022), introduction and Note 1
- DOE Building America Solution Center: Continuous Load Path, Continuous Rigid Insulation
- NIST, NISTIR 4605; PNNL, PNNL-34452
- ENERGY STAR, Window Performance Ratings
- NIH ORF, "Sound Design Metrics"
- GSA, Building Systems Upgrades; P-120 Project Cost and Schedule Management Requirements (2022)
- NIST, Handbook 135 (2022)
- OMB, Circular A-131
- NC State Center for Universal Design, The Principles of Universal Design
- North Carolina Department of Public Safety, Prevention Through Environmental Design
Last verified: October 13, 2026 (Asia/Manila). We checked NCARB's PPD format, objectives, April 2026 changes, pass rates, fees, and practice-exam details, plus the federal and technical sources cited in the explanations. All calculations use the inputs shown with each question.
By the Castleport Test Prep Editorial Team
Castleport Test Prep is an independent exam prep publisher. We are not affiliated with, endorsed by, or approved by the National Council of Architectural Registration Boards (NCARB), PSI, or any architectural licensing board. ARE and other exam and division names are used only to identify their subjects. Trademarks belong to their respective owners. The practice questions here are original and unofficial, and they do not guarantee an exam result or licensure.